Bid Tabulations
Letting of
09/28/2011
LA DOTD Headquarters
| Lead Project: H.006526.6 | |
| Parish: Jefferson | |
| Routes: | |
| Description: LOYOLA DRIVE INTERCHANGE MODIFICATIONS | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, TRAFFIC SIGNALIZATION, AND RELATED WORK. | |
| Estimated Construction Cost: $626,800.93 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 48896 | Command Construction Industries LLC | $793,763.00 |
| 2 | 00935 | Fleming Construction Co., Inc. | $840,857.50 |
| 3 | 06276 | Barriere Construction Co., LLC | $943,286.88 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Command Construction Industries LLC |
- 2 - Fleming Construction Co., Inc. |
- 3 - Barriere Construction Co., LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 75,000.00 | 75,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-02020 | Removal of Asphalt Pavement | 269 | SQYD | 30.00 | 8,070.00 | 20.00 | 5,380.00 | 23.00 | 6,187.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 966 | LNFT | 30.00 | 28,980.00 | 5.00 | 4,830.00 | 13.00 | 12,558.00 |
| 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 50.4 | SQYD | 30.00 | 1,512.00 | 30.00 | 1,512.00 | 13.00 | 655.20 |
| 0005 | 202-02-14500 | Removal of Guard Rail | 135 | LNFT | 1.00 | 135.00 | 10.00 | 1,350.00 | 8.00 | 1,080.00 |
| 0006 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 1,000.00 | 1,000.00 | 4,000.00 | 4,000.00 | 4,500.00 | 4,500.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 2,500.00 | 2,500.00 | 25,000.00 | 25,000.00 | 33,000.00 | 33,000.00 |
| 0008 | 302-02-03080 | Class II Base Course (8" Thick) (Asphaltic Concrete Base on Embankment Layer) | 1,402.5 | SQYD | 75.00 | 105,187.50 | 60.00 | 84,150.00 | 65.00 | 91,162.50 |
| 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 1.00 | 100.00 | 30.00 | 3,000.00 | 50.00 | 5,000.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 974 | TON | 100.00 | 97,400.00 | 125.00 | 121,750.00 | 120.00 | 116,880.00 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 33.7 | TON | 100.00 | 3,370.00 | 250.00 | 8,425.00 | 225.00 | 7,582.50 |
| 0012 | 509-01-00100 | Cold Planing Asphaltic Pavement | 4,536 | SQYD | 3.00 | 13,608.00 | 3.00 | 13,608.00 | 6.00 | 27,216.00 |
| 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -251 | CUYD | 1.00 | -251.00 | 10.00 | -2,510.00 | 1.00 | -251.00 |
| 0014 | 704-03-00100 | Blocked Out Guard Rail | 141.3 | LNFT | 25.00 | 3,532.50 | 25.00 | 3,532.50 | 26.00 | 3,673.80 |
| 0015 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 6.3 | LNFT | 75.00 | 472.50 | 100.00 | 630.00 | 100.00 | 630.00 |
| 0016 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 2,000.00 | 2,000.00 | 2,200.00 | 2,200.00 | 2,500.00 | 2,500.00 |
| 0017 | 706-01-00100 | Concrete Walk (4" Thick) | 17.8 | SQYD | 50.00 | 890.00 | 150.00 | 2,670.00 | 80.00 | 1,424.00 |
| 0018 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 509.5 | SQYD | 75.00 | 38,212.50 | 80.00 | 40,760.00 | 52.25 | 26,621.38 |
| 0019 | 706-04-00100 | Handicapped Curb Ramps | 18 | EACH | 250.00 | 4,500.00 | 2,500.00 | 45,000.00 | 1,575.00 | 28,350.00 |
| 0020 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,149 | LNFT | 50.00 | 57,450.00 | 30.00 | 34,470.00 | 26.60 | 30,563.40 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000.00 | 1,000.00 | 25,000.00 | 25,000.00 | 80,000.00 | 80,000.00 |
| 0022 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 2,220 | LNFT | 0.10 | 222.00 | 0.20 | 444.00 | 0.05 | 111.00 |
| 0023 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,000 | LNFT | 0.10 | 300.00 | 0.30 | 900.00 | 0.15 | 450.00 |
| 0024 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 400 | LNFT | 0.10 | 40.00 | 1.00 | 400.00 | 0.50 | 200.00 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.42 | MILE | 100.00 | 42.00 | 350.00 | 147.00 | 300.00 | 126.00 |
| 0026 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.42 | MILE | 100.00 | 42.00 | 425.00 | 178.50 | 425.00 | 178.50 |
| 0027 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.275 | MILE | 100.00 | 27.50 | 600.00 | 165.00 | 500.00 | 137.50 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 500.00 | 100.00 | 250.00 | 50.00 | 5,500.00 | 1,100.00 |
| 0029 | 717-01-00100 | Seeding | 10 | LB | 1.00 | 10.00 | 15.00 | 150.00 | 26.00 | 260.00 |
| 0030 | 718-01-00100 | Fertilizer | 200 | LB | 0.10 | 20.00 | 2.00 | 400.00 | 3.00 | 600.00 |
| 0031 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | 90,000.00 | 90,000.00 |
| 0033 | 729-01-00100 | Sign (Type A) | 52 | SQFT | 30.00 | 1,560.00 | 50.00 | 2,600.00 | 45.00 | 2,340.00 |
| 0034 | 730-01-00100 | Trenching and Backfilling | 470 | LNFT | 4.00 | 1,880.00 | 4.50 | 2,115.00 | 4.25 | 1,997.50 |
| 0035 | 731-02-00100 | Reflectorized Raised Pavement Markers | 185 | EACH | 6.00 | 1,110.00 | 5.00 | 925.00 | 6.00 | 1,110.00 |
| 0036 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,525 | LNFT | 1.00 | 2,525.00 | 0.80 | 2,020.00 | 1.00 | 2,525.00 |
| 0039 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.123 | MILE | 2,500.00 | 307.50 | 3,000.00 | 369.00 | 3,200.00 | 393.60 |
| 0040 | 732-03-02010 | Plastic Pvmt Strip (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.104 | MILE | 2,500.00 | 260.00 | 2,000.00 | 208.00 | 2,100.00 | 218.40 |
| 0041 | 732-03-02030 | Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 2,500.00 | 335.00 | 2,500.00 | 335.00 | 2,750.00 | 368.50 |
| 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 200.00 | 800.00 | 190.00 | 760.00 | 225.00 | 900.00 |
| 0043 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 200.00 | 400.00 | 190.00 | 380.00 | 225.00 | 450.00 |
| 0044 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 200.00 | 800.00 | 210.00 | 840.00 | 225.00 | 900.00 |
| 0045 | 732-04-19040 | Plastic Pavement Legends and Symbols (Shield - Interstate) (Preformed Heat Applied Retroreflective Thermoplastic) | 4 | EACH | 2,000.00 | 8,000.00 | 180.00 | 720.00 | 2,000.00 | 8,000.00 |
| 0046 | 732-05-00100 | Removal of Existing Markings | 0.275 | MILE | 1,000.00 | 275.00 | 5,000.00 | 1,375.00 | 6,500.00 | 1,787.50 |
| 0047 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 890 | LNFT | 20.00 | 17,800.00 | 14.00 | 12,460.00 | 14.00 | 12,460.00 |
| 0048 | 736-04-02000 | Signal Support (Pedestal Pole) | 7 | EACH | 1,500.00 | 10,500.00 | 1,500.00 | 10,500.00 | 1,400.00 | 9,800.00 |
| 0049 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 1 | EACH | 10,000.00 | 10,000.00 | 8,500.00 | 8,500.00 | 9,000.00 | 9,000.00 |
| 0050 | 736-04-04160 | Signal Support (45' Single Mast Arm) | 2 | EACH | 10,000.00 | 20,000.00 | 12,000.00 | 24,000.00 | 14,000.00 | 28,000.00 |
| 0051 | 736-04-04180 | Signal Support (50' Single Mast Arm) | 2 | EACH | 10,000.00 | 20,000.00 | 13,500.00 | 27,000.00 | 15,000.00 | 30,000.00 |
| 0052 | 736-04-05100 | Signal Support (Clamp on 30' Arm) | 1 | EACH | 2,500.00 | 2,500.00 | 2,500.00 | 2,500.00 | 3,200.00 | 3,200.00 |
| 0053 | 736-04-05140 | Signal Support (Clamp on 40' Arm) | 1 | EACH | 3,500.00 | 3,500.00 | 4,000.00 | 4,000.00 | 4,800.00 | 4,800.00 |
| 0054 | 736-04-05160 | Signal Support (Clamp on 45' Arm) | 2 | EACH | 4,000.00 | 8,000.00 | 4,500.00 | 9,000.00 | 5,400.00 | 10,800.00 |
| 0055 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 18 | EACH | 1,000.00 | 18,000.00 | 1,000.00 | 18,000.00 | 1,100.00 | 19,800.00 |
| 0056 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 3 | EACH | 1,000.00 | 3,000.00 | 1,000.00 | 3,000.00 | 1,100.00 | 3,300.00 |
| 0057 | 736-05-02040 | Signal Heads (3 Section, 12" Led Lens, R, RT. Y, RT. G) | 2 | EACH | 1,000.00 | 2,000.00 | 1,000.00 | 2,000.00 | 1,100.00 | 2,200.00 |
| 0058 | 736-05-05000 | Signal Heads (3 Section, 12" Optically Programmed Lens, R, Y, G) | 4 | EACH | 4,000.00 | 16,000.00 | 4,000.00 | 16,000.00 | 4,500.00 | 18,000.00 |
| 0059 | 736-06-00200 | Signal Service (Pedestal Required) | 1 | EACH | 2,500.00 | 2,500.00 | 1,800.00 | 1,800.00 | 2,100.00 | 2,100.00 |
| 0061 | 736-10-00200 | Underground Junction Box (Type E) | 1 | EACH | 1,000.00 | 1,000.00 | 330.00 | 330.00 | 375.00 | 375.00 |
| 0062 | 736-10-00300 | Underground Junction Box (Type F) | 10 | EACH | 500.00 | 5,000.00 | 360.00 | 3,600.00 | 375.00 | 3,750.00 |
| 0063 | 736-10-00500 | Underground Junction Box (Type H) | 1 | EACH | 1,000.00 | 1,000.00 | 750.00 | 750.00 | 800.00 | 800.00 |
| 0064 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 205 | LNFT | 1.00 | 205.00 | 2.00 | 410.00 | 2.00 | 410.00 |
| 0065 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 430 | LNFT | 1.00 | 430.00 | 3.00 | 1,290.00 | 3.00 | 1,290.00 |
| 0066 | 736-12-01040 | Conductor (2c, #14 awg) | 2,650 | LNFT | 1.00 | 2,650.00 | 1.50 | 3,975.00 | 1.50 | 3,975.00 |
| 0067 | 736-12-02000 | Conductor (3c, 6 gauge / #6 awg) | 350 | LNFT | 1.00 | 350.00 | 3.00 | 1,050.00 | 3.50 | 1,225.00 |
| 0068 | 736-12-02020 | Conductor (3c, #14 awg) | 1,005 | LNFT | 1.00 | 1,005.00 | 1.50 | 1,507.50 | 1.50 | 1,507.50 |
| 0069 | 736-13-00400 | Cable (6C Signal) | 4,650 | LNFT | 1.00 | 4,650.00 | 2.00 | 9,300.00 | 2.00 | 9,300.00 |
| 0070 | 736-13-00500 | Cable (10C Signal) | 3,400 | LNFT | 1.00 | 3,400.00 | 2.30 | 7,820.00 | 2.50 | 8,500.00 |
| 0071 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 |
| 0072 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 200 | LNFT | 100.00 | 20,000.00 | 80.00 | 16,000.00 | 95.00 | 19,000.00 |
| 0073 | NS-201-00001 | Tree and Stump Removal (Under 36" - 36" Diameter) | 4 | EACH | 1,000.00 | 4,000.00 | 600.00 | 2,400.00 | 750.00 | 3,000.00 |
| 0074 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 9,980 | INLF | 0.10 | 998.00 | 1.00 | 9,980.00 | 0.85 | 8,483.00 |
| 0075 | NS-736-00004 | LED Blank-Out Sign | 4 | EACH | 4,000.00 | 16,000.00 | 3,500.00 | 14,000.00 | 3,500.00 | 14,000.00 |
| 0076 | NS-736-00005 | Video Detection Cabinet Components | 1 | EACH | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 9,000.00 | 9,000.00 |
| 0077 | NS-736-00006 | Video Detection Camera | 6 | EACH | 2,500.00 | 15,000.00 | 2,000.00 | 12,000.00 | 2,300.00 | 13,800.00 |
| 0078 | NS-736-00007 | Video Detection Training | 1 | LUMP | 100.00 | 100.00 | 1.00 | 1.00 | 0.10 | 0.10 |
| 0079 | NS-736-00010 | LED Pedestrian Countdown Signal Head | 12 | EACH | 100.00 | 1,200.00 | 650.00 | 7,800.00 | 700.00 | 8,400.00 |
| 0080 | NS-736-00011 | Pedestrian Push Buttons | 12 | EACH | 100.00 | 1,200.00 | 1,700.00 | 20,400.00 | 200.00 | 2,400.00 |
| 0081 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 140 | SQYD | 100.00 | 14,000.00 | 120.00 | 16,800.00 | 105.00 | 14,700.00 |
| 0082 | 729-21-00100 | U-Channel Post | 3 | EACH | 100.00 | 300.00 | 180.00 | 540.00 | 300.00 | 900.00 |
| 0083 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,275 | LNFT | 1.00 | 1,275.00 | 1.20 | 1,530.00 | 1.50 | 1,912.50 |
| 0084 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 475 | LNFT | 1.00 | 475.00 | 5.00 | 2,375.00 | 5.50 | 2,612.50 |
| 0085 | 736-08-00111 | Sig Cntrlr (TS-2, Type 2)(Type 6E Cabinet)(Furnish & Install) | 1 | EACH | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 32,000.00 | 32,000.00 |
| CONTRACTOR TOTAL | 793,763.00 | 840,857.50 | 943,286.88 | |||||||