Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.006473.6 | |
| Parish: Caddo | |
| Routes: | |
| Description: Caddo Parish Bridge Guard Rail Improvements | |
| Type Const: guard rail removal, installation and related work. | |
| Estimated Construction Cost: $263,846.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34068 | Alpha Service and Products, Inc. | $235,380.00 |
| 2 | 41747 | Odum Services, L.P. | $250,560.00 |
| 3 | 35849 | T.L. Construction LLC | $254,944.50 |
| 4 | 43371 | RMD Holdings Ltd | $363,550.19 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Alpha Service and Products, Inc. |
- 2 - Odum Services, L.P. |
- 3 - T.L. Construction LLC |
- 4 - RMD Holdings Ltd |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-04024 | Removal of Bridge Components Flexible Bridge Railing and Componenets | 1 | LUMP | 4,000.00 | 4,000.00 | 4,000.00 | 4,000.00 | 5,200.00 | 5,200.00 | 23,333.33 | 23,333.33 |
| 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 36 | EACH | 20.00 | 720.00 | 25.00 | 900.00 | 1.00 | 36.00 | 6.67 | 240.12 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 500 | CUYD | 32.00 | 16,000.00 | 30.00 | 15,000.00 | 20.00 | 10,000.00 | 30.67 | 15,335.00 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 40.5 | TON | 220.00 | 8,910.00 | 300.00 | 12,150.00 | 450.00 | 18,225.00 | 313.62 | 12,701.61 |
| 0005 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 900 | LNFT | 32.00 | 28,800.00 | 38.00 | 34,200.00 | 41.00 | 36,900.00 | 44.52 | 40,068.00 |
| 0006 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 1,025 | LNFT | 57.00 | 58,425.00 | 60.00 | 61,500.00 | 41.00 | 42,025.00 | 56.56 | 57,974.00 |
| 0007 | 704-03-00100 | Blocked Out Guard Rail | 862.5 | LNFT | 18.00 | 15,525.00 | 20.00 | 17,250.00 | 17.00 | 14,662.50 | 32.26 | 27,824.25 |
| 0008 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 36 | EACH | 2,400.00 | 86,400.00 | 2,100.00 | 75,600.00 | 1,800.00 | 64,800.00 | 2,730.08 | 98,282.88 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 20,000.00 | 20,000.00 | 32,000.00 | 32,000.00 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 35,000.00 | 35,000.00 | 47,333.33 | 47,333.33 |
| 0011 | 729-16-00300 | Object Marker Assembly (Type 3) | 36 | EACH | 100.00 | 3,600.00 | 110.00 | 3,960.00 | 86.00 | 3,096.00 | 49.75 | 1,791.00 |
| 0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 6,666.67 | 6,666.67 |
| CONTRACTOR TOTAL | 235,380.00 | 250,560.00 | 254,944.50 | 363,550.19 | ||||||||