Bid Tabulations
Letting of
05/15/2013
LA DOTD Headquarters
| Lead Project: H.006153.6 | |
| Parish: LaSalle | |
| Routes: | |
| Description: SPARROW STREET BRIDGE OVER TROUT CREEK | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $346,078.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49239 | WL Bass Construction Inc. | $327,987.70 |
| 2 | 23112 | Ben Allen, Inc. | $336,096.50 |
| 3 | 56288 | Guinn Services, LLC | $369,011.00 |
| 4 | 30774 | Progressive Construction Co., LLC | $381,464.10 |
| 5 | 00044 | Guinn Construction, LLC | $408,805.00 |
| 6 | 32044 | Quality Design & Construction, LLC | $421,052.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - WL Bass Construction Inc. |
- 2 - Ben Allen, Inc. |
- 3 - Guinn Services, LLC |
- 4 - Progressive Construction Co., LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 10,000.00 | 10,000.00 | 17,500.00 | 17,500.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 24.0'X27.2' TIMBER BRIDGE) | 1 | EACH | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 5,400.00 | 5,400.00 |
| 0003 | 202-02-04000 | Removal of Bridge (STA 200+00; 22.9'X27.9' TIMBER BRIDGE) | 1 | EACH | 2,500.00 | 2,500.00 | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 5,400.00 | 5,400.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 8,500.00 | 8,500.00 | 18,000.00 | 18,000.00 | 20,000.00 | 20,000.00 | 26,500.00 | 26,500.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 14 | EACH | 1.00 | 14.00 | 0.00 | 0.00 | 15.00 | 210.00 | 21.00 | 294.00 |
| 0006 | 204-03-00100 | Temporary Slope Drains | 120 | LNFT | 1.00 | 120.00 | 0.00 | 0.00 | 10.00 | 1,200.00 | 37.00 | 4,440.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 1.00 | 4.00 | 0.00 | 0.00 | 100.00 | 400.00 | 235.00 | 940.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 1,080 | LNFT | 0.10 | 108.00 | 2.00 | 2,160.00 | 2.00 | 2,160.00 | 2.25 | 2,430.00 |
| 0009 | 302-01-00100 | Class II Base Course | 140 | CUYD | 135.00 | 18,900.00 | 100.00 | 14,000.00 | 100.00 | 14,000.00 | 111.00 | 15,540.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 108.2 | TON | 175.00 | 18,935.00 | 165.00 | 17,853.00 | 210.00 | 22,722.00 | 250.00 | 27,050.00 |
| 0011 | 701-05-02040 | Side Drain Pipe (Erosion) (18" PP/CMP) | 122 | LNFT | 65.00 | 7,930.00 | 65.00 | 7,930.00 | 40.00 | 4,880.00 | 41.50 | 5,063.00 |
| 0012 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 340 | SQYD | 55.00 | 18,700.00 | 65.00 | 22,100.00 | 55.00 | 18,700.00 | 61.75 | 20,995.00 |
| 0013 | 711-04-00100 | Geotextile Fabric | 340 | SQYD | 1.25 | 425.00 | 3.00 | 1,020.00 | 3.75 | 1,275.00 | 2.00 | 680.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,500.00 | 4,500.00 | 6,000.00 | 6,000.00 | 12,500.00 | 12,500.00 | 6,000.00 | 6,000.00 |
| 0015 | 716-01-00100 | Mulch (Vegetative) | 0.5 | TON | 2,000.00 | 1,000.00 | 2,000.00 | 1,000.00 | 3,000.00 | 1,500.00 | 2,115.00 | 1,057.50 |
| 0016 | 717-01-00100 | Seeding | 13 | LB | 20.00 | 260.00 | 75.00 | 975.00 | 25.00 | 325.00 | 23.50 | 305.50 |
| 0017 | 718-01-00100 | Fertilizer | 276 | LB | 1.00 | 276.00 | 2.00 | 552.00 | 1.75 | 483.00 | 2.35 | 648.60 |
| 0018 | 726-01-00100 | Bedding Material | 207.7 | CUYD | 1.00 | 207.70 | 85.00 | 17,654.50 | 90.00 | 18,693.00 | 105.00 | 21,808.50 |
| 0019 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 22,000.00 | 22,000.00 |
| 0020 | 729-01-00100 | Sign (Type A) LA. NATURAL & SCENIC RIVER SYSTEM SIGN | 9 | SQFT | 60.00 | 540.00 | 25.00 | 225.00 | 50.00 | 450.00 | 54.00 | 486.00 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 8 | EACH | 75.00 | 600.00 | 75.00 | 600.00 | 125.00 | 1,000.00 | 20.00 | 160.00 |
| 0022 | 729-21-00100 | U-Channel Post | 2 | EACH | 50.00 | 100.00 | 50.00 | 100.00 | 85.00 | 170.00 | 50.00 | 100.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,500.00 | 5,500.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0024 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 69.94 | CUYD | 1,050.00 | 73,437.00 | 950.00 | 66,443.00 | 1,100.00 | 76,934.00 | 1,100.00 | 76,934.00 |
| 0025 | 805-12-04000 | Reinforced Concrete Box Culverts (7' x 7') | 197 | LNFT | 625.00 | 123,125.00 | 575.00 | 113,275.00 | 600.00 | 118,200.00 | 558.00 | 109,926.00 |
| 0026 | 806-01-00100 | Deformed Reinforcing Steel | 4,806 | LB | 1.00 | 4,806.00 | 1.50 | 7,209.00 | 1.50 | 7,209.00 | 1.00 | 4,806.00 |
| CONTRACTOR TOTAL | 327,987.70 | 336,096.50 | 369,011.00 | 381,464.10 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Guinn Construction, LLC |
- 6 - Quality Design & Construction, LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 11,000.00 | 11,000.00 | 20,400.00 | 20,400.00 |
| 0002 | 202-02-04000 | Removal of Bridge (STA 100+00; 24.0'X27.2' TIMBER BRIDGE) | 1 | EACH | 4,500.00 | 4,500.00 | 10,300.00 | 10,300.00 |
| 0003 | 202-02-04000 | Removal of Bridge (STA 200+00; 22.9'X27.9' TIMBER BRIDGE) | 1 | EACH | 4,500.00 | 4,500.00 | 8,900.00 | 8,900.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 12,200.00 | 12,200.00 |
| 0005 | 204-02-00100 | Temporary Hay or Straw Bales | 14 | EACH | 10.00 | 140.00 | 14.00 | 196.00 |
| 0006 | 204-03-00100 | Temporary Slope Drains | 120 | LNFT | 1.00 | 120.00 | 12.00 | 1,440.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 100.00 | 400.00 | 500.00 | 2,000.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 1,080 | LNFT | 2.00 | 2,160.00 | 2.00 | 2,160.00 |
| 0009 | 302-01-00100 | Class II Base Course | 140 | CUYD | 100.00 | 14,000.00 | 121.00 | 16,940.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 108.2 | TON | 300.00 | 32,460.00 | 265.00 | 28,673.00 |
| 0011 | 701-05-02040 | Side Drain Pipe (Erosion) (18" PP/CMP) | 122 | LNFT | 35.00 | 4,270.00 | 48.00 | 5,856.00 |
| 0012 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 340 | SQYD | 70.00 | 23,800.00 | 39.00 | 13,260.00 |
| 0013 | 711-04-00100 | Geotextile Fabric | 340 | SQYD | 5.00 | 1,700.00 | 5.00 | 1,700.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 12,000.00 | 12,000.00 | 18,300.00 | 18,300.00 |
| 0015 | 716-01-00100 | Mulch (Vegetative) | 0.5 | TON | 2,000.00 | 1,000.00 | 4,500.00 | 2,250.00 |
| 0016 | 717-01-00100 | Seeding | 13 | LB | 15.00 | 195.00 | 14.00 | 182.00 |
| 0017 | 718-01-00100 | Fertilizer | 276 | LB | 1.00 | 276.00 | 3.20 | 883.20 |
| 0018 | 726-01-00100 | Bedding Material | 207.7 | CUYD | 100.00 | 20,770.00 | 133.00 | 27,624.10 |
| 0019 | 727-01-00100 | Mobilization | 1 | LUMP | 42,000.00 | 42,000.00 | 15,000.00 | 15,000.00 |
| 0020 | 729-01-00100 | Sign (Type A) LA. NATURAL & SCENIC RIVER SYSTEM SIGN | 9 | SQFT | 50.00 | 450.00 | 33.00 | 297.00 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 8 | EACH | 100.00 | 800.00 | 99.00 | 792.00 |
| 0022 | 729-21-00100 | U-Channel Post | 2 | EACH | 100.00 | 200.00 | 78.00 | 156.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 9,200.00 | 9,200.00 |
| 0024 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 69.94 | CUYD | 1,150.00 | 80,431.00 | 1,050.00 | 73,437.00 |
| 0025 | 805-12-04000 | Reinforced Concrete Box Culverts (7' x 7') | 197 | LNFT | 595.00 | 117,215.00 | 690.00 | 135,930.00 |
| 0026 | 806-01-00100 | Deformed Reinforcing Steel | 4,806 | LB | 3.00 | 14,418.00 | 2.70 | 12,976.20 |
| CONTRACTOR TOTAL | 408,805.00 | 421,052.50 | ||||||