LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.006131.6
Parish: Jackson
Routes:
Description: OLIVE GROVE ROAD BRIDGES
Type Const: CLEARING AND GRUBBING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost: $649,972.00


RankLicenseBidderConstruction Bid
1 23112 Ben Allen, Inc. $549,240.80
2 49864 Terral Construction L.L.C. $629,623.20
3 18546 C W & W Contractors, Inc. $633,022.57
4 39462 Jb James Construction Llc $695,625.50
5 56288 Guinn Services, LLC $705,085.50
6 34567 James Construction Group LLC $751,721.35


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Ben Allen, Inc.
- 2 -
Terral Construction L.L.C.
- 3 -
C W & W Contractors, Inc.
- 4 -
Jb James Construction Llc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 8,000.00 8,000.00 78,408.00 78,408.00 15,000.00 15,000.00 45,000.00 45,000.00
0002 202-02-04000 Removal of Bridge (STA 14+99.83; 15.27' X 30.55' TIMBER BRIDGE) 1      EACH 3,000.00 3,000.00 10,000.00 10,000.00 7,500.00 7,500.00 7,500.00 7,500.00
0003 202-02-04000 Removal of Bridge (STA 35+00.14; 16.02' X 27.24' TIMBER BRIDGE) 1      EACH 3,000.00 3,000.00 4,500.00 4,500.00 7,500.00 7,500.00 7,500.00 7,500.00
0004 203-05-00100 Excavation and Embankment 1      LUMP 18,000.00 18,000.00 40,000.00 40,000.00 15,000.00 15,000.00 21,000.00 21,000.00
0005 204-02-00100 Temporary Hay or Straw Bales 20      EACH 0.00 0.00 30.00 600.00 10.00 200.00 15.00 300.00
0006 204-03-00100 Temporary Slope Drains 60      LNFT 0.00 0.00 20.00 1,200.00 25.00 1,500.00 12.00 720.00
0007 204-06-00100 Temporary Silt Fencing 1,864      LNFT 2.00 3,728.00 2.00 3,728.00 3.00 5,592.00 3.00 5,592.00
0008 302-01-00800 Class II Base Course (Stone or Recycled Portland Cement Concrete) 542.5    CUYD 105.00 56,962.50 100.00 54,250.00 125.00 67,812.50 100.00 54,250.00
0009 304-01-00100 Lime 8.57   TON 330.00 2,828.10 100.00 857.00 1.00 8.57 150.00 1,285.50
0010 304-04-00400 Lime Treatment (Type D) (12" Thick) 604      SQYD 11.00 6,644.00 2.00 1,208.00 1.00 604.00 1.00 604.00
0011 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 10.00 1,000.00 100.00 10,000.00 100.00 10,000.00 25.00 2,500.00
0012 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 64.4    CUYD 105.00 6,762.00 100.00 6,440.00 100.00 6,440.00 100.00 6,440.00
0013 502-01-00100 Superpave Asphaltic Concrete 421.4    TON 158.00 66,581.20 168.00 70,795.20 240.00 101,136.00 155.00 65,317.00
0014 701-01-01040 Cross Drain Pipe (36" RCP/PP) 50      LNFT 120.00 6,000.00 100.00 5,000.00 105.00 5,250.00 126.00 6,300.00
0016 701-15-00100 Concrete Collar 2      EACH 750.00 1,500.00 1,000.00 2,000.00 1,000.00 2,000.00 800.00 1,600.00
0017 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,800.00 11,200.00 3,000.00 12,000.00 2,250.00 9,000.00 2,150.00 8,600.00
0018 711-01-04000 Riprap (55 lb, 18" Thick) 312      SQYD 62.00 19,344.00 6.00 1,872.00 75.00 23,400.00 65.00 20,280.00
0019 711-04-00100 Geotextile Fabric 312      SQYD 3.00 936.00 3.00 936.00 3.00 936.00 2.00 624.00
0020 713-01-00100 Temporary Signs and Barricades 1      LUMP 7,000.00 7,000.00 5,000.00 5,000.00 7,500.00 7,500.00 20,000.00 20,000.00
0021 716-01-00100 Mulch (Vegetative) 0.74   TON 1,100.00 814.00 6,000.00 4,440.00 1,400.00 1,036.00 1,500.00 1,110.00
0022 717-01-00100 Seeding 19      LB 20.00 380.00 400.00 7,600.00 10.00 190.00 20.00 380.00
0023 718-01-00100 Fertilizer 370      LB 2.00 740.00 2.00 740.00 2.25 832.50 1.50 555.00
0024 726-01-00100 Bedding Material 202.2    CUYD 85.00 17,187.00 110.00 22,242.00 120.00 24,264.00 100.00 20,220.00
0025 727-01-00100 Mobilization 1      LUMP 35,000.00 35,000.00 30,000.00 30,000.00 55,000.00 55,000.00 65,000.00 65,000.00
0026 729-16-00200 Object Marker Assembly (Type 2) 4      EACH 85.00 340.00 100.00 400.00 85.00 340.00 70.00 280.00
0027 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 85.00 340.00 100.00 400.00 85.00 340.00 80.00 320.00
0028 740-01-00100 Construction Layout 1      LUMP 7,000.00 7,000.00 6,000.00 6,000.00 10,000.00 10,000.00 25,000.00 25,000.00
0029 804-01-00300 Precast Concrete Piles (16") 960      LNFT 53.00 50,880.00 63.00 60,480.00 78.00 74,880.00 80.00 76,800.00
0030 804-12-00100 Loading Permanent Piles 1      EACH 0.00 0.00 1.00 1.00 1.00 1.00 100.00 100.00
0031 805-01-00300 Class A Concrete (Box Culvert Headwalls) 26.07   CUYD 1,200.00 31,284.00 1,400.00 36,498.00 1,200.00 31,284.00 1,300.00 33,891.00
0032 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 3      SPAN 29,000.00 87,000.00 25,000.00 75,000.00 25,000.00 75,000.00 34,000.00 102,000.00
0033 805-12-03040 Reinforced Concrete Box Culverts (8' x 6') 120      LNFT 605.00 72,600.00 470.00 56,400.00 470.00 56,400.00 645.00 77,400.00
0034 806-01-00100 Deformed Reinforcing Steel 2,076      LB 2.50 5,190.00 3.00 6,228.00 1.00 2,076.00 0.75 1,557.00
0035 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 9,000.00 18,000.00 7,200.00 14,400.00 7,500.00 15,000.00 7,800.00 15,600.00
                         
    CONTRACTOR TOTAL       549,240.80   629,623.20   633,022.57   695,625.50



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Guinn Services, LLC
- 6 -
James Construction Group LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 26,500.00 26,500.00 30,000.00 30,000.00
0002 202-02-04000 Removal of Bridge (STA 14+99.83; 15.27' X 30.55' TIMBER BRIDGE) 1      EACH 3,500.00 3,500.00 10,000.00 10,000.00
0003 202-02-04000 Removal of Bridge (STA 35+00.14; 16.02' X 27.24' TIMBER BRIDGE) 1      EACH 3,100.00 3,100.00 10,000.00 10,000.00
0004 203-05-00100 Excavation and Embankment 1      LUMP 34,000.00 34,000.00 30,000.00 30,000.00
0005 204-02-00100 Temporary Hay or Straw Bales 20      EACH 15.00 300.00 18.00 360.00
0006 204-03-00100 Temporary Slope Drains 60      LNFT 12.50 750.00 21.00 1,260.00
0007 204-06-00100 Temporary Silt Fencing 1,864      LNFT 2.00 3,728.00 5.00 9,320.00
0008 302-01-00800 Class II Base Course (Stone or Recycled Portland Cement Concrete) 542.5    CUYD 95.00 51,537.50 145.00 78,662.50
0009 304-01-00100 Lime 8.57   TON 1,000.00 8,570.00 100.00 857.00
0010 304-04-00400 Lime Treatment (Type D) (12" Thick) 604      SQYD 18.50 11,174.00 10.00 6,040.00
0011 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 88.50 8,850.00 5.00 500.00
0012 403-01-00100 Aggregate Roadway Surfacing (Vehicular Measurement) 64.4    CUYD 100.00 6,440.00 90.00 5,796.00
0013 502-01-00100 Superpave Asphaltic Concrete 421.4    TON 205.00 86,387.00 150.00 63,210.00
0014 701-01-01040 Cross Drain Pipe (36" RCP/PP) 50      LNFT 100.00 5,000.00 195.00 9,750.00
0016 701-15-00100 Concrete Collar 2      EACH 2,000.00 4,000.00 1,200.00 2,400.00
0017 704-11-00100 Guard Rail End Treatment (Flared) 4      EACH 2,500.00 10,000.00 2,150.00 8,600.00
0018 711-01-04000 Riprap (55 lb, 18" Thick) 312      SQYD 65.00 20,280.00 65.00 20,280.00
0019 711-04-00100 Geotextile Fabric 312      SQYD 4.00 1,248.00 3.25 1,014.00
0020 713-01-00100 Temporary Signs and Barricades 1      LUMP 12,000.00 12,000.00 3,000.00 3,000.00
0021 716-01-00100 Mulch (Vegetative) 0.74   TON 1,850.00 1,369.00 1,500.00 1,110.00
0022 717-01-00100 Seeding 19      LB 20.00 380.00 20.00 380.00
0023 718-01-00100 Fertilizer 370      LB 1.50 555.00 1.50 555.00
0024 726-01-00100 Bedding Material 202.2    CUYD 100.00 20,220.00 97.00 19,613.40
0025 727-01-00100 Mobilization 1      LUMP 65,000.00 65,000.00 90,000.00 90,000.00
0026 729-16-00200 Object Marker Assembly (Type 2) 4      EACH 100.00 400.00 70.00 280.00
0027 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 100.00 400.00 80.00 320.00
0028 740-01-00100 Construction Layout 1      LUMP 8,500.00 8,500.00 7,500.00 7,500.00
0029 804-01-00300 Precast Concrete Piles (16") 960      LNFT 72.00 69,120.00 89.00 85,440.00
0030 804-12-00100 Loading Permanent Piles 1      EACH 1.00 1.00 5,000.00 5,000.00
0031 805-01-00300 Class A Concrete (Box Culvert Headwalls) 26.07   CUYD 1,500.00 39,105.00 855.00 22,289.85
0032 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 3      SPAN 34,000.00 102,000.00 42,500.00 127,500.00
0033 805-12-03040 Reinforced Concrete Box Culverts (8' x 6') 120      LNFT 650.00 78,000.00 670.00 80,400.00
0034 806-01-00100 Deformed Reinforcing Steel 2,076      LB 2.25 4,671.00 1.10 2,283.60
0035 NS-800-00040 Concrete Approach Slabs (24' CLR RDWY, 90 DEG CROSSING) (W/O ASPHALT) 2      EACH 9,000.00 18,000.00 9,000.00 18,000.00
                 
    CONTRACTOR TOTAL       705,085.50   751,721.35