Bid Tabulations
Letting of
02/13/2013
LA DOTD Headquarters
| Lead Project: H.006057.6 | |
| Parish: Calcasieu | |
| Routes: | |
| Description: WILLIAM STREET AND WRIGHT ROAD BRIDGES | |
| Type Const: Bridge repairs and related work. | |
| Estimated Construction Cost: $301,300.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00044 | Guinn Construction, LLC | $197,900.00 |
| 2 | 39462 | Jb James Construction Llc | $235,030.00 |
| 3 | 33678 | Sealevel Construction Inc. | $246,700.00 |
| 4 | MAT03 | Matt L Guinn Construction, LLC | $302,850.00 |
| 00060 | F. Miller Construction LLC | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Guinn Construction, LLC |
- 2 - Jb James Construction Llc |
- 3 - Sealevel Construction Inc. |
- 4 - Matt L Guinn Construction, LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 9,000.00 | 9,000.00 | 18,000.00 | 18,000.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 40,000.00 | 40,000.00 |
| 0003 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 20,000.00 | 20,000.00 | 4,200.00 | 4,200.00 | 11,500.00 | 11,500.00 |
| 0004 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 2,300 | LNFT | 35.00 | 80,500.00 | 36.50 | 83,950.00 | 50.00 | 115,000.00 | 48.50 | 111,550.00 |
| 0005 | 805-09-00100 | Expansion Joint Seal | 68 | LNFT | 50.00 | 3,400.00 | 60.00 | 4,080.00 | 25.00 | 1,700.00 | 100.00 | 6,800.00 |
| 0006 | NS-805-00016 | Bridge Superstructure Repair (SPAN, REMOVE AND REINSTALL) | 4 | EACH | 15,000.00 | 60,000.00 | 15,000.00 | 60,000.00 | 9,200.00 | 36,800.00 | 17,500.00 | 70,000.00 |
| 0007 | NS-805-00020 | Bridge Substructure Repair (CAP, REMOVE AND REINSTALL) | 6 | EACH | 2,000.00 | 12,000.00 | 4,500.00 | 27,000.00 | 10,000.00 | 60,000.00 | 7,500.00 | 45,000.00 |
| CONTRACTOR TOTAL | 197,900.00 | 235,030.00 | 246,700.00 | 302,850.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
F. Miller Construction LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,800.00 | 10,800.00 |
| 0002 | 727-01-00100 | Mobilization | 1 | LUMP | 26,500.00 | 26,500.00 |
| 0003 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 |
| 0004 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 2,300 | LNFT | 34.00 | 78,200.00 |
| 0005 | 805-09-00100 | Expansion Joint Seal | 68 | LNFT | 14.00 | 952.00 |
| 0006 | NS-805-00016 | Bridge Superstructure Repair (SPAN, REMOVE AND REINSTALL) | 4 | EACH | 7,800.00 | 31,200.00 |
| 0007 | NS-805-00020 | Bridge Substructure Repair (CAP, REMOVE AND REINSTALL) | 6 | EACH | 4,500.00 | 27,000.00 |
| CONTRACTOR TOTAL | IRREGULAR | |||||