LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.006039.6
Parish: Bienville
Routes:
Description: GUIN ROAD BRIDGE and GROVER JONES ROAD BRIDGE
Type Const: CLEARING AND GRUBBING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGE AND RELATED WORK
Estimated Construction Cost: $697,262.00


RankLicenseBidderConstruction Bid
1 18546 C W & W Contractors, Inc. $623,877.50
2 56288 Guinn Services, LLC $648,004.50
3 49864 Terral Construction LLC $656,949.11
4 00044 Guinn Construction, LLC $663,712.50
5 23112 Ben Allen, Inc. $740,584.00
6 01012 Cecil D. Gassiott, LLC $786,168.00
7 12135 Blount Bros. Construction, Inc. $807,665.00
8 39462 Jb James Construction Llc $862,548.80


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
C W & W Contractors, Inc.
- 2 -
Guinn Services, LLC
- 3 -
Terral Construction LLC
- 4 -
Guinn Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 22,000.00 22,000.00 25,000.00 25,000.00 35,000.00 35,000.00 15,000.00 15,000.00
0002 202-02-04000 Removal of Bridge STA 105+27.50;19.1' X 55' TIMBER BRIDGE 1      EACH 8,000.00 8,000.00 5,500.00 5,500.00 7,500.00 7,500.00 10,000.00 10,000.00
0003 202-02-04000 Removal of Bridge STA 200+19.50;20.5' X 39' TIMBER BRIDGE 1      EACH 6,000.00 6,000.00 4,000.00 4,000.00 7,500.00 7,500.00 6,000.00 6,000.00
0004 203-05-00100 Excavation and Embankment 1      LUMP 54,000.00 54,000.00 20,000.00 20,000.00 25,000.00 25,000.00 20,000.00 20,000.00
0005 204-02-00100 Temporary Hay or Straw Bales 100      EACH 20.00 2,000.00 8.50 850.00 20.00 2,000.00 10.00 1,000.00
0006 204-03-00100 Temporary Slope Drains 60      LNFT 10.00 600.00 15.00 900.00 10.00 600.00 0.00 0.00
0007 204-05-00100 Temporary Sediment Check Dams (Hay) 12      EACH 100.00 1,200.00 125.00 1,500.00 100.00 1,200.00 100.00 1,200.00
0008 204-06-00100 Temporary Silt Fencing 1,342      LNFT 2.00 2,684.00 2.25 3,019.50 2.00 2,684.00 1.50 2,013.00
0009 302-01-00100 Class II Base Course 312.7    CUYD 130.00 40,651.00 85.00 26,579.50 126.19 39,459.61 80.00 25,016.00
0010 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 8      CUYD 110.00 880.00 150.00 1,200.00 100.00 800.00 200.00 1,600.00
0011 502-01-00100 Superpave Asphaltic Concrete 243.5    TON 175.00 42,612.50 200.00 48,700.00 221.00 53,813.50 175.00 42,612.50
0012 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 440      LNFT 75.00 33,000.00 60.00 26,400.00 46.00 20,240.00 55.00 24,200.00
0013 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 65.00 13,000.00 70.00 14,000.00 70.00 14,000.00 72.00 14,400.00
0014 704-09-00100 Guard Rail Anchor Sections (Turndown) 200      LNFT 40.00 8,000.00 45.00 9,000.00 38.00 7,600.00 40.00 8,000.00
0015 705-09-00100 Rebuilt Fence 300      LNFT 10.00 3,000.00 15.00 4,500.00 10.00 3,000.00 10.00 3,000.00
0016 711-01-04000 Riprap (55 lb, 18" Thick) 488      SQYD 70.00 34,160.00 68.00 33,184.00 80.00 39,040.00 70.00 34,160.00
0017 711-04-00100 Geotextile Fabric 488      SQYD 3.00 1,464.00 4.00 1,952.00 2.00 976.00 5.00 2,440.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 10,000.00 10,000.00 13,000.00 13,000.00 8,000.00 8,000.00 12,000.00 12,000.00
0019 716-01-00100 Mulch (Vegetative) 1.1    TON 810.00 891.00 1,700.00 1,870.00 2,000.00 2,200.00 2,000.00 2,200.00
0020 717-01-00100 Seeding 20      LB 10.00 200.00 20.00 400.00 10.00 200.00 25.00 500.00
0021 718-01-00100 Fertilizer 495      LB 1.00 495.00 1.50 742.50 2.00 990.00 1.00 495.00
0022 720-01-01000 Erosion Control System (Slope Protection) (Type A) 1,577      SQYD 4.00 6,308.00 5.00 7,885.00 2.00 3,154.00 2.00 3,154.00
0023 727-01-00100 Mobilization 1      LUMP 45,000.00 45,000.00 55,000.00 55,000.00 34,000.00 34,000.00 60,000.00 60,000.00
0024 729-16-00300 Object Marker Assembly (Type 3) 16      EACH 85.00 1,360.00 90.00 1,440.00 100.00 1,600.00 100.00 1,600.00
0025 740-01-00100 Construction Layout 1      LUMP 8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 7,000.00 7,000.00
0026 804-01-00200 Precast Concrete Piles (14") 648      LNFT 65.00 42,120.00 60.00 38,880.00 55.00 35,640.00 65.00 42,120.00
0027 804-01-00300 Precast Concrete Piles (16") 750      LNFT 75.00 56,250.00 70.00 52,500.00 65.00 48,750.00 80.00 60,000.00
0028 804-12-00100 Loading Permanent Piles 2      EACH 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00
0029 805-10-01300 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) 4      SPAN 22,000.00 88,000.00 30,000.00 120,000.00 30,000.00 120,000.00 32,000.00 128,000.00
0030 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 3      SPAN 22,000.00 66,000.00 30,000.00 90,000.00 30,000.00 90,000.00 32,000.00 96,000.00
0031 NS-800-00040 Concrete Approach Slabs 24' CLR RDWY, 90 DEG CROSSING W/O ASPHALT 3      EACH 6,500.00 19,500.00 8,000.00 24,000.00 11,000.00 33,000.00 10,000.00 30,000.00
0032 NS-800-00040 Concrete Approach Slabs 24' CLR RDWY, 90 DEG CROSSING; CURVED W/O ASPHALT 1      EACH 6,500.00 6,500.00 8,000.00 8,000.00 11,000.00 11,000.00 10,000.00 10,000.00
                         
    CONTRACTOR TOTAL       623,877.50   648,004.50   656,949.11   663,712.50



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Ben Allen, Inc.
- 6 -
Cecil D. Gassiott, LLC
- 7 -
Blount Bros. Construction, Inc.
- 8 -
Jb James Construction Llc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 14,000.00 14,000.00 20,000.00 20,000.00 10,000.00 10,000.00 90,000.00 90,000.00
0002 202-02-04000 Removal of Bridge STA 105+27.50;19.1' X 55' TIMBER BRIDGE 1      EACH 5,000.00 5,000.00 20,000.00 20,000.00 20,000.00 20,000.00 21,000.00 21,000.00
0003 202-02-04000 Removal of Bridge STA 200+19.50;20.5' X 39' TIMBER BRIDGE 1      EACH 5,000.00 5,000.00 15,000.00 15,000.00 15,000.00 15,000.00 20,000.00 20,000.00
0004 203-05-00100 Excavation and Embankment 1      LUMP 35,000.00 35,000.00 35,000.00 35,000.00 20,000.00 20,000.00 50,000.00 50,000.00
0005 204-02-00100 Temporary Hay or Straw Bales 100      EACH 0.00 0.00 9.00 900.00 20.00 2,000.00 10.00 1,000.00
0006 204-03-00100 Temporary Slope Drains 60      LNFT 0.00 0.00 19.00 1,140.00 20.00 1,200.00 15.00 900.00
0007 204-05-00100 Temporary Sediment Check Dams (Hay) 12      EACH 0.00 0.00 180.00 2,160.00 400.00 4,800.00 150.00 1,800.00
0008 204-06-00100 Temporary Silt Fencing 1,342      LNFT 4.00 5,368.00 2.75 3,690.50 3.00 4,026.00 3.00 4,026.00
0009 302-01-00100 Class II Base Course 312.7    CUYD 125.00 39,087.50 30.00 9,381.00 80.00 25,016.00 90.00 28,143.00
0010 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 8      CUYD 125.00 1,000.00 95.00 760.00 100.00 800.00 200.00 1,600.00
0011 502-01-00100 Superpave Asphaltic Concrete 243.5    TON 225.00 54,787.50 250.00 60,875.00 120.00 29,220.00 230.00 56,005.00
0012 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 440      LNFT 75.00 33,000.00 80.00 35,200.00 60.00 26,400.00 45.00 19,800.00
0013 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 55.00 11,000.00 21.00 4,200.00 70.00 14,000.00 62.00 12,400.00
0014 704-09-00100 Guard Rail Anchor Sections (Turndown) 200      LNFT 85.00 17,000.00 61.00 12,200.00 50.00 10,000.00 32.00 6,400.00
0015 705-09-00100 Rebuilt Fence 300      LNFT 15.00 4,500.00 11.00 3,300.00 12.00 3,600.00 12.00 3,600.00
0016 711-01-04000 Riprap (55 lb, 18" Thick) 488      SQYD 75.00 36,600.00 70.00 34,160.00 70.00 34,160.00 57.00 27,816.00
0017 711-04-00100 Geotextile Fabric 488      SQYD 5.00 2,440.00 5.00 2,440.00 3.00 1,464.00 2.00 976.00
0018 713-01-00100 Temporary Signs and Barricades 1      LUMP 12,000.00 12,000.00 12,000.00 12,000.00 20,000.00 20,000.00 20,000.00 20,000.00
0019 716-01-00100 Mulch (Vegetative) 1.1    TON 1,500.00 1,650.00 2,000.00 2,200.00 700.00 770.00 2,800.00 3,080.00
0020 717-01-00100 Seeding 20      LB 15.00 300.00 20.00 400.00 20.00 400.00 50.00 1,000.00
0021 718-01-00100 Fertilizer 495      LB 2.00 990.00 0.50 247.50 1.00 495.00 5.00 2,475.00
0022 720-01-01000 Erosion Control System (Slope Protection) (Type A) 1,577      SQYD 3.00 4,731.00 2.00 3,154.00 2.00 3,154.00 1.40 2,207.80
0023 727-01-00100 Mobilization 1      LUMP 56,000.00 56,000.00 85,000.00 85,000.00 60,000.00 60,000.00 80,000.00 80,000.00
0024 729-16-00300 Object Marker Assembly (Type 3) 16      EACH 110.00 1,760.00 75.00 1,200.00 150.00 2,400.00 80.00 1,280.00
0025 740-01-00100 Construction Layout 1      LUMP 12,000.00 12,000.00 10,000.00 10,000.00 20,000.00 20,000.00 20,000.00 20,000.00
0026 804-01-00200 Precast Concrete Piles (14") 648      LNFT 65.00 42,120.00 95.00 61,560.00 120.00 77,760.00 80.00 51,840.00
0027 804-01-00300 Precast Concrete Piles (16") 750      LNFT 75.00 56,250.00 100.00 75,000.00 140.00 105,000.00 84.00 63,000.00
0028 804-12-00100 Loading Permanent Piles 2      EACH 0.00 0.00 1,000.00 2,000.00 2,000.00 4,000.00 100.00 200.00
0029 805-10-01300 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) 4      SPAN 36,000.00 144,000.00 32,000.00 128,000.00 40,000.00 160,000.00 35,000.00 140,000.00
0030 805-10-01320 Bridge Superstructure and Substructure (24' Clear Roadway; 90 Degree Crossing) (Cast-in-Place) 3      SPAN 33,000.00 99,000.00 35,000.00 105,000.00 40,000.00 120,000.00 36,000.00 108,000.00
0031 NS-800-00040 Concrete Approach Slabs 24' CLR RDWY, 90 DEG CROSSING W/O ASPHALT 3      EACH 11,500.00 34,500.00 10,000.00 30,000.00 1,000.00 3,000.00 6,000.00 18,000.00
0032 NS-800-00040 Concrete Approach Slabs 24' CLR RDWY, 90 DEG CROSSING; CURVED W/O ASPHALT 1      EACH 11,500.00 11,500.00 10,000.00 10,000.00 9,000.00 9,000.00 6,000.00 6,000.00
                         
    CONTRACTOR TOTAL       740,584.00   786,168.00   807,665.00   862,548.80