Bid Tabulations
Letting of
10/10/2012
LA DOTD Headquarters
| Lead Project: H.005823.6 | |
| Parish: Orleans | |
| Routes: | |
| Description: IHNC-ALMONASTER AVE. BR. HURRICANE KATRINA DAMAGE REPAIRS | |
| Type Const: BRIDGE REPAIRS AND RELATED WORK | |
| Estimated Construction Cost: $1,620,153.93 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $3,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 00481 | Coastal Bridge Co., L.L.C. | $1,990,213.50 | 140 | $2,410,213.50 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $2,139,720.10 | 125 | $2,514,720.10 |
| 3 | 25747 | Kostmayer Construction, LLC | $2,275,710.75 | 120 | $2,635,710.75 |
| 4 | 37302 | Double Aught Construction LLC | $2,287,123.00 | 120 | $2,647,123.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Coastal Bridge Co., L.L.C. |
- 2 - Boh Bros. Construction Co., LLC. |
- 3 - Kostmayer Construction, LLC |
- 4 - Double Aught Construction LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-00010 | Removal of Steel Checkered Plate | 2 | EACH | 7,000.00 | 14,000.00 | 8,000.00 | 16,000.00 | 6,500.00 | 13,000.00 | 22,500.00 | 45,000.00 |
| 0002 | 202-02-00010 | Removal of Traffic Warning Gate | 4 | EACH | 1,600.00 | 6,400.00 | 105.00 | 420.00 | 3,000.00 | 12,000.00 | 4,000.00 | 16,000.00 |
| 0003 | 202-02-10000 | Removal of Existing Steel Grid Deck | 1 | LUMP | 4,000.00 | 4,000.00 | 18,000.00 | 18,000.00 | 6,500.00 | 6,500.00 | 15,000.00 | 15,000.00 |
| 0004 | 202-02-12300 | Removal of Fender System | 1 | EACH | 15,000.00 | 15,000.00 | 115,000.00 | 115,000.00 | 65,000.00 | 65,000.00 | 50,000.00 | 50,000.00 |
| 0005 | 202-02-14500 | Removal of Guard Rail | 1,215 | LNFT | 15.00 | 18,225.00 | 9.25 | 11,238.75 | 13.25 | 16,098.75 | 30.00 | 36,450.00 |
| 0006 | 202-02-40000 | Removal of Timber Piles | 2,785 | LNFT | 8.00 | 22,280.00 | 37.00 | 103,045.00 | 8.00 | 22,280.00 | 20.00 | 55,700.00 |
| 0007 | 203-03-00100 | Embankment | 90 | CUYD | 75.00 | 6,750.00 | 34.00 | 3,060.00 | 150.00 | 13,500.00 | 60.00 | 5,400.00 |
| 0008 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 1,070 | LNFT | 90.00 | 96,300.00 | 115.00 | 123,050.00 | 103.00 | 110,210.00 | 95.00 | 101,650.00 |
| 0009 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 150 | LNFT | 90.00 | 13,500.00 | 65.00 | 9,750.00 | 80.00 | 12,000.00 | 60.00 | 9,000.00 |
| 0010 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 20.00 | 5,000.00 | 24.00 | 6,000.00 | 30.00 | 7,500.00 | 30.00 | 7,500.00 |
| 0014 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 5,400.00 | 21,600.00 | 2,500.00 | 10,000.00 | 3,000.00 | 12,000.00 |
| 0015 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 10 | LNFT | 250.00 | 2,500.00 | 100.00 | 1,000.00 | 100.00 | 1,000.00 | 250.00 | 2,500.00 |
| 0016 | 710-01-00100 | Flowable Fill | 50 | CUYD | 850.00 | 42,500.00 | 155.00 | 7,750.00 | 1,000.00 | 50,000.00 | 270.00 | 13,500.00 |
| 0017 | 711-02-00400 | Riprap (55 lb) | 1,100 | CUYD | 150.00 | 165,000.00 | 125.00 | 137,500.00 | 150.00 | 165,000.00 | 95.00 | 104,500.00 |
| 0018 | 711-04-00100 | Geotextile Fabric | 15 | SQYD | 30.00 | 450.00 | 700.00 | 10,500.00 | 10.00 | 150.00 | 30.00 | 450.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 40,000.00 | 40,000.00 | 17,000.00 | 17,000.00 | 6,000.00 | 6,000.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 180,000.00 | 180,000.00 | 200,000.00 | 200,000.00 | 250,000.00 | 250,000.00 | 180,000.00 | 180,000.00 |
| 0021 | 730-02-03020 | Conduit with Conductors (Rigid Galvanized Steel) (3/4") (UL Approved, PVC-Coated Conduit) | 2,100 | LNFT | 25.00 | 52,500.00 | 27.00 | 56,700.00 | 18.91 | 39,711.00 | 23.00 | 48,300.00 |
| 0022 | 730-02-03040 | Conduit with Conductors (Rigid Galvanized Steel) (1") (UL Approved, PVC-Coated Conduit) | 1,000 | LNFT | 25.00 | 25,000.00 | 33.00 | 33,000.00 | 29.20 | 29,200.00 | 23.10 | 23,100.00 |
| 0023 | 730-02-03060 | Conduit with Conductors (Rigid Galvanized Steel) (1 1/4") (UL Approved, PVC-Coated Conduit) | 200 | LNFT | 52.50 | 10,500.00 | 36.00 | 7,200.00 | 64.35 | 12,870.00 | 48.00 | 9,600.00 |
| 0024 | 730-02-03080 | Conduit with Conductors (Rigid Galvanized Steel) (1 1/2") (UL Approved, PVC-Coated Conduit) | 600 | LNFT | 55.00 | 33,000.00 | 41.00 | 24,600.00 | 44.55 | 26,730.00 | 49.00 | 29,400.00 |
| 0025 | 730-02-03100 | Conduit with Conductors (Rigid Galvanized Steel) (2") (UL Approved, PVC-Coated Conduit) | 1,200 | LNFT | 35.00 | 42,000.00 | 55.00 | 66,000.00 | 54.82 | 65,784.00 | 33.00 | 39,600.00 |
| 0026 | 730-02-03140 | Conduit with Conductors (Rigid Galvanized Steel) (3") (UL Approved, PVC-Coated Conduit) | 500 | LNFT | 65.00 | 32,500.00 | 88.00 | 44,000.00 | 136.00 | 68,000.00 | 60.00 | 30,000.00 |
| 0027 | 730-09-00100 | Electrical System | 1 | LUMP | 195,000.00 | 195,000.00 | 213,000.00 | 213,000.00 | 175,000.00 | 175,000.00 | 185,000.00 | 185,000.00 |
| 0028 | 730-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 24,000.00 | 24,000.00 | 3,500.00 | 3,500.00 |
| 0029 | 736-04-03020 | Signal Support (22' Steel Strain Pole) | 1 | EACH | 4,000.00 | 4,000.00 | 11,000.00 | 11,000.00 | 13,750.00 | 13,750.00 | 6,000.00 | 6,000.00 |
| 0030 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 2 | EACH | 3,650.00 | 7,300.00 | 1,200.00 | 2,400.00 | 1,485.00 | 2,970.00 | 4,000.00 | 8,000.00 |
| 0031 | 736-06-00600 | Signal Service (Existing Pole) | 2 | EACH | 3,650.00 | 7,300.00 | 235.00 | 470.00 | 17,050.00 | 34,100.00 | 4,000.00 | 8,000.00 |
| 0032 | 741-02-00050 | Gate Valve (1") | 2 | EACH | 2,800.00 | 5,600.00 | 500.00 | 1,000.00 | 400.00 | 800.00 | 1,500.00 | 3,000.00 |
| 0033 | 741-05-02040 | Water Service Line (1" Polyethylene) | 775 | LNFT | 60.00 | 46,500.00 | 5.00 | 3,875.00 | 11.00 | 8,525.00 | 110.00 | 85,250.00 |
| 0034 | 741-12-00100 | Remove Water Valve Including Box | 2 | EACH | 1,800.00 | 3,600.00 | 500.00 | 1,000.00 | 250.00 | 500.00 | 2,500.00 | 5,000.00 |
| 0035 | 741-15-00025 | Casing (2.5") (Water Distribution System) Schedule 40 Steel | 165 | LNFT | 115.00 | 18,975.00 | 35.00 | 5,775.00 | 85.00 | 14,025.00 | 180.00 | 29,700.00 |
| 0036 | 741-15-00090 | Casing (6") (Water Distribution System) Polyethylene Pipe | 20 | LNFT | 1,000.00 | 20,000.00 | 15.00 | 300.00 | 100.00 | 2,000.00 | 200.00 | 4,000.00 |
| 0037 | 741-18-00001 | Valve Box | 2 | EACH | 3,000.00 | 6,000.00 | 1,000.00 | 2,000.00 | 500.00 | 1,000.00 | 1,600.00 | 3,200.00 |
| 0038 | 804-02-00200 | Treated Timber Piles (Coastal Treatment) | 2,385 | LNFT | 68.00 | 162,180.00 | 60.00 | 143,100.00 | 50.00 | 119,250.00 | 75.00 | 178,875.00 |
| 0039 | 805-01-00100 | Class A Concrete | 11.5 | CUYD | 5,000.00 | 57,500.00 | 885.00 | 10,177.50 | 1,500.00 | 17,250.00 | 3,000.00 | 34,500.00 |
| 0040 | 807-08-00100 | Structural Metalwork ASTM (A36) | 1 | LUMP | 80,000.00 | 80,000.00 | 95,000.00 | 95,000.00 | 235,000.00 | 235,000.00 | 300,000.00 | 300,000.00 |
| 0041 | 808-01-00100 | Steel Grid Flooring | 28.6 | SQFT | 450.00 | 12,870.00 | 125.00 | 3,575.00 | 200.00 | 5,720.00 | 750.00 | 21,450.00 |
| 0042 | 809-01-00100 | Movable Bridge Machinery | 1 | LUMP | 6,500.00 | 6,500.00 | 10,300.00 | 10,300.00 | 76,000.00 | 76,000.00 | 35,000.00 | 35,000.00 |
| 0043 | 809-03-00100 | Operating House | 1 | LUMP | 210,000.00 | 210,000.00 | 235,000.00 | 235,000.00 | 201,000.00 | 201,000.00 | 96,000.00 | 96,000.00 |
| 0044 | 812-01-00200 | Treated Timber (Coastal Treatment) | 10.845 | MFBM | 15,000.00 | 162,675.00 | 22,000.00 | 238,590.00 | 15,000.00 | 162,675.00 | 15,000.00 | 162,675.00 |
| 0046 | NS-800-00020 | Cleaning, Painting and Disposal (Near White Finish) | 1 | LUMP | 25,000.00 | 25,000.00 | 11,500.00 | 11,500.00 | 15,000.00 | 15,000.00 | 125,000.00 | 125,000.00 |
| 0047 | NS-800-00260 | Hand Railing | 250 | LNFT | 240.00 | 60,000.00 | 50.00 | 12,500.00 | 320.00 | 80,000.00 | 250.00 | 62,500.00 |
| 0048 | NS-805-00027 | Structural Concrete Patching | 1.39 | SQFT | 150.00 | 208.50 | 715.00 | 993.85 | 300.00 | 417.00 | 700.00 | 973.00 |
| 0049 | NS-805-00028 | Rubber Fender Elements | 3 | EACH | 4,200.00 | 12,600.00 | 7,000.00 | 21,000.00 | 4,000.00 | 12,000.00 | 15,000.00 | 45,000.00 |
| 0050 | 202-02-00010 | Removal of Hand Railing (10 Foot Section) | 25 | EACH | 320.00 | 8,000.00 | 550.00 | 13,750.00 | 1,000.00 | 25,000.00 | 500.00 | 12,500.00 |
| 0051 | 730-02-03180 | Conduit with Conductors (Rigid Galvanized Steel) (4") (UL Approved, PVC Coated Conduit) | 190 | LNFT | 180.00 | 34,200.00 | 200.00 | 38,000.00 | 190.50 | 36,195.00 | 165.00 | 31,350.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 1,990,213.50 | 2,139,720.10 | 2,275,710.75 | 2,287,123.00 | ||||||||
| NUMBER OF DAYS BID AT $3000 PER DAY. | 420,000.00 | 375,000.00 | 360,000.00 | 360,000.00 | ||||||||
| TOTAL BID | 2,410,213.50 | 2,514,720.10 | 2,635,710.75 | 2,647,123.00 | ||||||||