| Lead Project: H.003678.6-R1 | |
| Parish: St. Martin | |
| Routes: I-10 | |
| Description: Butte Larose Rest Area Improvements | |
| Type Const: GRADING, DRAINAGE STRUCTURES, PORTLAND CEMENT CONCRETE PAVEMENT, SIDEWALKS, BUILDING CONSTRUCTION, LANDSCAPING, AND RELATED WORK. | |
| Estimated Construction Cost: $3,371,684.00 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 18943 | Bulliard Construction Co. Inc. | $3,839,000.00 |
| 2 | 39594 | Arrighi Construction LLC | $3,878,000.00 |
| 3 | 55505 | Merrick, LLC | $4,189,036.00 |
| 4 | 30774 | Progressive Construction Co., LLC | $5,358,000.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Bulliard Construction Co. Inc. |
- 2 - Arrighi Construction LLC |
- 3 - Merrick, LLC |
- 4 - Progressive Construction Co., LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | NS-MSC-00261 | Rest Area Improvements | 1 | LUMP | 3,839,000.00 | 3,839,000.00 | 3,878,000.00 | 3,878,000.00 | 4,189,036.00 | 4,189,036.00 | 5,358,000.00 | 5,358,000.00 |
| CONTRACTOR TOTAL | 3,839,000.00 | 3,878,000.00 | 4,189,036.00 | 5,358,000.00 | ||||||||