Bid Tabulations
Letting of
04/11/2012
LA DOTD Headquarters
| Lead Project: H.003486.6 | |
| Parish: Desoto | |
| Routes: I-49 | |
| Description: Natchitoches Parish Line to South of KCS Overpass | |
| Type Const: COLD PLANNING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PAVEMENT MARKINGS, AND RELATED WORK | |
| Estimated Construction Cost: $11,274,863.60 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $10,105,766.25 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $11,542,980.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Gilchrist Construction Co. LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 3,640 | LNFT | 6.50 | 23,660.00 | 5.00 | 18,200.00 |
| 0002 | 203-07-00300 | Borrow (Vehicular Measurement) (Plastic Soils) | 6,000 | CUYD | 22.00 | 132,000.00 | 16.50 | 99,000.00 |
| 0003 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 14,683.4 | TON | 120.00 | 1,762,008.00 | 135.00 | 1,982,259.00 |
| 0004 | 501-02-00001 | Tack Coat For use w/ thin asphaltic concrete, OGFC | 53,394 | GAL | 3.90 | 208,236.60 | 4.00 | 213,576.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 83,903.3 | TON | 80.00 | 6,712,264.00 | 89.00 | 7,467,393.70 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 356,962 | SQYD | 1.25 | 446,202.50 | 1.00 | 356,962.00 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -14,873 | CUYD | 0.10 | -1,487.30 | 0.10 | -1,487.30 |
| 0008 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) For shoulder patching, as directed by PE | 1,000 | SQYD | 56.50 | 56,500.00 | 78.00 | 78,000.00 |
| 0009 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 500 | SQYD | 10.00 | 5,000.00 | 155.00 | 77,500.00 |
| 0010 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 125 | LNFT | 43.00 | 5,375.00 | 45.00 | 5,625.00 |
| 0011 | 704-03-00100 | Blocked Out Guard Rail | 4,260 | LNFT | 17.00 | 72,420.00 | 18.00 | 76,680.00 |
| 0012 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 12.6 | LNFT | 83.00 | 1,045.80 | 90.00 | 1,134.00 |
| 0013 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 250 | LNFT | 38.50 | 9,625.00 | 40.00 | 10,000.00 |
| 0014 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 500 | LNFT | 53.00 | 26,500.00 | 55.00 | 27,500.00 |
| 0015 | 704-11-00100 | Guard Rail End Treatment (Flared) | 20 | EACH | 1,980.00 | 39,600.00 | 2,000.00 | 40,000.00 |
| 0016 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 2 | EACH | 2,300.00 | 4,600.00 | 2,400.00 | 4,800.00 |
| 0017 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 158,000.00 | 158,000.00 | 200,000.00 | 200,000.00 |
| 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 101.464 | MILE | 1.00 | 101.46 | 400.00 | 40,585.60 |
| 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 101.464 | MILE | 1.00 | 101.46 | 300.00 | 30,439.20 |
| 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 202.928 | MILE | 1.00 | 202.93 | 400.00 | 81,171.20 |
| 0021 | 716-01-00100 | Mulch (Vegetative) | 36 | TON | 600.00 | 21,600.00 | 550.00 | 19,800.00 |
| 0022 | 717-01-00100 | Seeding | 733 | LB | 15.00 | 10,995.00 | 8.20 | 6,010.60 |
| 0023 | 718-01-00100 | Fertilizer | 18,000 | LB | 0.75 | 13,500.00 | 0.50 | 9,000.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 158,000.00 | 158,000.00 | 450,000.00 | 450,000.00 |
| 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 24 | EACH | 75.00 | 1,800.00 | 80.00 | 1,920.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,000 | EACH | 4.00 | 16,000.00 | 7.00 | 28,000.00 |
| 0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 4,266 | LNFT | 1.00 | 4,266.00 | 1.50 | 6,399.00 |
| 0028 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 400 | LNFT | 3.00 | 1,200.00 | 4.90 | 1,960.00 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 52 | MILE | 2,600.00 | 135,200.00 | 2,700.00 | 140,400.00 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 26 | MILE | 700.00 | 18,200.00 | 940.00 | 24,440.00 |
| 0031 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 1.6 | MILE | 4,000.00 | 6,400.00 | 3,300.00 | 5,280.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 |
| 0033 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 48.692 | MILE | 650.00 | 31,649.80 | 625.00 | 30,432.50 |
| CONTRACTOR TOTAL | 10,105,766.25 | 11,542,980.50 | ||||||