Bid Tabulations
Letting of
08/31/2011
LA DOTD Headquarters
| Lead Project: H.003338.6 | |
| Parish: Richland | |
| Routes: I-20 | |
| Description: I-20: BEE BAYOU TO HOLLY RIDGE | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $2,738,089.15 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $3,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $3,000,853.70 | 95 | $3,285,853.70 |
| 2 | 05789 | D & J Construction Co., Inc. | $3,050,025.53 | 110 | $3,380,025.53 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - D & J Construction Co., Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 1 | LUMP | 42,000.00 | 42,000.00 | 20,000.00 | 20,000.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) AS LISTED IN SUMMARY OF DRAINAGE STRUCTU | 204 | LNFT | 7.00 | 1,428.00 | 5.00 | 1,020.00 |
| 0003 | 202-02-32180 | Removal of Pipe Headwalls | 26 | EACH | 180.00 | 4,680.00 | 125.00 | 3,250.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 16,000.00 | 16,000.00 | 12,000.00 | 12,000.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 475 | CUYD | 30.00 | 14,250.00 | 25.00 | 11,875.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 1,500 | LNFT | 2.85 | 4,275.00 | 3.00 | 4,500.00 |
| 0007 | 501-01-00006 | Thin Asphaltic Concrete (OGFC) | 4,756.6 | TON | 172.00 | 818,135.20 | 165.00 | 784,839.00 |
| 0008 | 501-02-00001 | Tack Coat | 22,953 | GAL | 5.00 | 114,765.00 | 4.25 | 97,550.25 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 11,534.9 | TON | 90.00 | 1,038,141.00 | 98.50 | 1,136,187.65 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 104,863 | SQYD | 1.50 | 157,294.50 | 2.50 | 262,157.50 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,370 | CUYD | 0.10 | -437.00 | 0.10 | -437.00 |
| 0012 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | 27 | SQYD | 325.00 | 8,775.00 | 300.00 | 8,100.00 |
| 0013 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 32 | LNFT | 80.00 | 2,560.00 | 60.00 | 1,920.00 |
| 0014 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 88 | LNFT | 128.00 | 11,264.00 | 95.00 | 8,360.00 |
| 0015 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 176 | LNFT | 150.00 | 26,400.00 | 110.00 | 19,360.00 |
| 0016 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 104 | LNFT | 170.00 | 17,680.00 | 125.00 | 13,000.00 |
| 0017 | 701-10-01120 | Reinforced Concrete Pipe (Extension) (42") | 16 | LNFT | 200.00 | 3,200.00 | 145.00 | 2,320.00 |
| 0018 | 701-10-01140 | Reinforced Concrete Pipe (Extension) (48") | 48 | LNFT | 255.00 | 12,240.00 | 185.00 | 8,880.00 |
| 0019 | 701-15-00100 | Concrete Collar | 32 | EACH | 1,100.00 | 35,200.00 | 750.00 | 24,000.00 |
| 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 140,000.00 | 140,000.00 | 210,000.00 | 210,000.00 |
| 0021 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,700 | LNFT | 0.75 | 1,275.00 | 0.50 | 850.00 |
| 0022 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 550 | LNFT | 1.00 | 550.00 | 0.75 | 412.50 |
| 0023 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 22.359 | MILE | 200.00 | 4,471.80 | 225.00 | 5,030.78 |
| 0024 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 22.359 | MILE | 200.00 | 4,471.80 | 150.00 | 3,353.85 |
| 0025 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 44.718 | MILE | 400.00 | 17,887.20 | 300.00 | 13,415.40 |
| 0026 | 716-01-00100 | Mulch (Vegetative) | 32 | TON | 800.00 | 25,600.00 | 350.00 | 11,200.00 |
| 0027 | 717-01-00100 | Seeding | 720 | LB | 14.00 | 10,080.00 | 7.00 | 5,040.00 |
| 0028 | 718-01-00100 | Fertilizer | 16,000 | LB | 0.75 | 12,000.00 | 0.38 | 6,080.00 |
| 0029 | 726-01-00100 | Bedding Material | 212.4 | CUYD | 140.00 | 29,736.00 | 100.00 | 21,240.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 225,000.00 | 225,000.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 26 | EACH | 100.00 | 2,600.00 | 100.00 | 2,600.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,140 | EACH | 6.00 | 12,840.00 | 5.00 | 10,700.00 |
| 0033 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,700 | LNFT | 4.00 | 6,800.00 | 4.00 | 6,800.00 |
| 0034 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 550 | LNFT | 7.00 | 3,850.00 | 6.00 | 3,300.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.906 | MILE | 3,700.00 | 55,152.20 | 2,700.00 | 40,246.20 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.453 | MILE | 1,000.00 | 7,453.00 | 800.00 | 5,962.40 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,500.00 | 12,500.00 | 25,000.00 | 25,000.00 |
| 0038 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,536 | INLF | 3.50 | 5,376.00 | 2.00 | 3,072.00 |
| 0039 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 2,500.00 | 10,000.00 | 5,000.00 | 20,000.00 |
| 0040 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 14.8 | MILE | 700.00 | 10,360.00 | 800.00 | 11,840.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 3,000,853.70 | 3,050,025.53 | ||||||
| NUMBER OF DAYS BID AT $3000 PER DAY. | 285,000.00 | 330,000.00 | ||||||
| TOTAL BID | 3,285,853.70 | 3,380,025.53 | ||||||