LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.003261.6
Parish: Caddo, Bienville
Routes: I-20
Description: I-20: DISTRICT WIDE APPROACH SLAB JACKING
Type Const: COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, APPROACH SLAB JACKING AND RELATED WORK.
Estimated Construction Cost: $211,351.13


RankLicenseBidderConstruction Bid
1 49239 WL Bass Construction Inc. $316,956.10
2 30774 Progressive Construction Co., LLC $332,555.86


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
WL Bass Construction Inc.
- 2 -
Progressive Construction Co., LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 502-01-00100 Superpave Asphaltic Concrete 100      TON 175.00 17,500.00 344.00 34,400.00
0002 509-01-00100 Cold Planing Asphaltic Pavement 250      SQYD 25.00 6,250.00 60.00 15,000.00
0003 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -13.9    CUYD 1.00 -13.90 0.01 -0.14
0004 710-01-00100 Flowable Fill 141      CUYD 165.00 23,265.00 214.00 30,174.00
0005 713-01-00100 Temporary Signs and Barricades 1      LUMP 65,000.00 65,000.00 49,000.00 49,000.00
0006 727-01-00100 Mobilization 1      LUMP 50,000.00 50,000.00 22,000.00 22,000.00
0007 740-01-00100 Construction Layout 1      LUMP 30,000.00 30,000.00 2,300.00 2,300.00
0008 NS-602-00003 Raising and/or Under-sealing Concrete Slabs (Polyurethane) 16,810      LB 5.50 92,455.00 8.00 134,480.00
0009 NS-700-00020 Adjusting Guard Rail 500      LNFT 5.00 2,500.00 65.00 32,500.00
0010 NS-713-00001 Dynamic Message Sign Unit 6      EACH 5,000.00 30,000.00 2,117.00 12,702.00
                 
    CONTRACTOR TOTAL       316,956.10   332,555.86