Bid Tabulations
Letting of
05/09/2012
LA DOTD Headquarters
| Lead Project: H.003240.6 | |
| Parish: Caddo | |
| Routes: I-20 | |
| Description: I-20 WB OFF RAMP IMPROVEMENTS AT PINES ROAD | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, PCC PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $363,109.43 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 28218 | F. J. Burnell, Inc. | $280,518.25 |
| 2 | 52306 | Cecil Perry Improvements Llc | $326,417.00 |
| 3 | 36374 | Best-Yet Builders, Llc | $331,590.13 |
| 4 | 39001 | Jd's Rebar & Construction Inc. | $388,504.67 |
| 5 | 55505 | Merrick, LLC | $405,388.70 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F. J. Burnell, Inc. |
- 2 - Cecil Perry Improvements Llc |
- 3 - Best-Yet Builders, Llc |
- 4 - Jd's Rebar & Construction Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 166.7 | SQYD | 10.00 | 1,667.00 | 18.91 | 3,152.30 | 42.00 | 7,001.40 | 19.84 | 3,307.33 |
| 0002 | 202-02-32000 | Removal of Paved Ditches | 5 | SQYD | 75.00 | 375.00 | 31.00 | 155.00 | 250.00 | 1,250.00 | 307.81 | 1,539.05 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 11,000.00 | 11,000.00 | 23,852.00 | 23,852.00 | 12,500.00 | 12,500.00 | 15,292.80 | 15,292.80 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 2,342 | LNFT | 1.00 | 2,342.00 | 1.25 | 2,927.50 | 2.25 | 5,269.50 | 2.23 | 5,222.66 |
| 0005 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 1,551.9 | SQYD | 25.00 | 38,797.50 | 36.75 | 57,032.33 | 26.70 | 41,435.73 | 67.10 | 104,132.49 |
| 0006 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 1,462 | SQYD | 60.00 | 87,720.00 | 64.00 | 93,568.00 | 76.00 | 111,112.00 | 80.03 | 117,003.86 |
| 0007 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 10 | LNFT | 100.00 | 1,000.00 | 65.00 | 650.00 | 200.00 | 2,000.00 | 286.48 | 2,864.80 |
| 0008 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 4,000.00 | 4,000.00 | 2,862.00 | 2,862.00 | 1,500.00 | 1,500.00 | 5,039.30 | 5,039.30 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,500.00 | 7,500.00 | 8,676.00 | 8,676.00 | 20,000.00 | 20,000.00 | 6,542.77 | 6,542.77 |
| 0010 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 1,140 | LNFT | 2.00 | 2,280.00 | 0.29 | 330.60 | 0.20 | 228.00 | 0.32 | 364.80 |
| 0011 | 716-01-00100 | Mulch (Vegetative) | 1.1 | TON | 1,000.00 | 1,100.00 | 1,374.00 | 1,511.40 | 1,500.00 | 1,650.00 | 1,529.28 | 1,682.21 |
| 0012 | 717-01-00100 | Seeding | 16 | LB | 15.00 | 240.00 | 28.63 | 458.08 | 25.00 | 400.00 | 31.86 | 509.76 |
| 0013 | 718-01-00100 | Fertilizer | 521 | LB | 1.00 | 521.00 | 1.15 | 599.15 | 1.00 | 521.00 | 1.27 | 661.67 |
| 0014 | 726-01-00100 | Bedding Material | 0.6 | CUYD | 200.00 | 120.00 | 119.00 | 71.40 | 1,000.00 | 600.00 | 1,624.86 | 974.92 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 22,500.00 | 22,500.00 | 34,235.00 | 34,235.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 |
| 0016 | 729-01-00103 | Sign (Type A)(Relocate) | 10 | SQFT | 50.00 | 500.00 | 57.25 | 572.50 | 100.00 | 1,000.00 | 140.18 | 1,401.80 |
| 0017 | 729-08-00200 | Mounting (3 1/2" Size Post) | 1 | EACH | 1,100.00 | 1,100.00 | 150.00 | 150.00 | 250.00 | 250.00 | 286.74 | 286.74 |
| 0018 | 729-16-00200 | Object Marker Assembly (Type 2) | 1 | EACH | 125.00 | 125.00 | 86.00 | 86.00 | 100.00 | 100.00 | 286.74 | 286.74 |
| 0019 | 730-01-00100 | Trenching and Backfilling | 1,210 | LNFT | 3.25 | 3,932.50 | 3.40 | 4,114.00 | 3.30 | 3,993.00 | 3.82 | 4,622.20 |
| 0020 | 730-02-01080 | Conduit with Conductors (PVC/HDPE) (1 1/2") (2#6, 1#6 Bare Solid Ground) | 1,210 | LNFT | 5.00 | 6,050.00 | 5.10 | 6,171.00 | 4.95 | 5,989.50 | 5.75 | 6,957.50 |
| 0021 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) | 130 | LNFT | 45.00 | 5,850.00 | 45.00 | 5,850.00 | 44.00 | 5,720.00 | 50.98 | 6,627.40 |
| 0022 | 730-05-11100 | Light Pole (40') (Steel) (Single Arm) | 4 | EACH | 5,600.00 | 22,400.00 | 5,500.00 | 22,000.00 | 5,500.00 | 22,000.00 | 637.20 | 2,548.80 |
| 0023 | 730-07-10000 | Luminaire (200 Watt, High Pressure Sodium) | 8 | EACH | 500.00 | 4,000.00 | 500.00 | 4,000.00 | 495.00 | 3,960.00 | 573.48 | 4,587.84 |
| 0024 | 730-09-00100 | Electrical System | 1 | LUMP | 2,300.00 | 2,300.00 | 2,300.00 | 2,300.00 | 2,200.00 | 2,200.00 | 2,548.80 | 2,548.80 |
| 0025 | 730-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 2,300.00 | 2,300.00 | 2,250.00 | 2,250.00 | 2,200.00 | 2,200.00 | 2,548.80 | 2,548.80 |
| 0026 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) (Steel, Single Arm, 40') | 1 | EACH | 1,100.00 | 1,100.00 | 1,150.00 | 1,150.00 | 1,100.00 | 1,100.00 | 1,274.40 | 1,274.40 |
| 0027 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) (Steel, Double Arm, 40') | 1 | EACH | 1,100.00 | 1,100.00 | 1,150.00 | 1,150.00 | 1,100.00 | 1,100.00 | 3,148.60 | 3,148.60 |
| 0028 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 2 | EACH | 600.00 | 1,200.00 | 550.00 | 1,100.00 | 550.00 | 1,100.00 | 318.60 | 637.20 |
| 0029 | 730-14-00100 | Removal and Disposal of Luminaires | 7 | EACH | 56.00 | 392.00 | 55.00 | 385.00 | 55.00 | 385.00 | 63.72 | 446.04 |
| 0030 | 730-15-11100 | Relocate Light Poles (40') (Steel) (Single Arm) | 4 | EACH | 3,400.00 | 13,600.00 | 3,400.00 | 13,600.00 | 3,300.00 | 13,200.00 | 3,823.20 | 15,292.80 |
| 0031 | 730-16-00100 | Underground Junction Box (12" x 12") | 8 | EACH | 280.00 | 2,240.00 | 270.00 | 2,160.00 | 275.00 | 2,200.00 | 318.60 | 2,548.80 |
| 0032 | 730-16-00300 | Underground Junction Box (13" x 24") | 4 | EACH | 450.00 | 1,800.00 | 450.00 | 1,800.00 | 440.00 | 1,760.00 | 509.76 | 2,039.04 |
| 0033 | 730-19-00010 | Modular Breakaway Cable System | 8 | EACH | 2,000.00 | 16,000.00 | 2,050.00 | 16,400.00 | 1,980.00 | 15,840.00 | 2,293.00 | 18,344.00 |
| 0034 | 730-21-00020 | Duct Marker (Concrete) | 4 | EACH | 110.00 | 440.00 | 114.00 | 456.00 | 110.00 | 440.00 | 128.00 | 512.00 |
| 0035 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 1,210 | LNFT | 1.10 | 1,331.00 | 1.15 | 1,391.50 | 1.10 | 1,331.00 | 1.30 | 1,573.00 |
| 0036 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 327 | LNFT | 1.75 | 572.25 | 1.70 | 555.90 | 2.00 | 654.00 | 2.00 | 654.00 |
| 0037 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 27 | LNFT | 20.00 | 540.00 | 9.20 | 248.40 | 10.00 | 270.00 | 10.00 | 270.00 |
| 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.208 | MILE | 4,500.00 | 936.00 | 4,580.00 | 952.64 | 3,000.00 | 624.00 | 5,098.00 | 1,060.38 |
| 0039 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.106 | MILE | 7,000.00 | 742.00 | 6,870.00 | 728.22 | 6,000.00 | 636.00 | 7,647.00 | 810.58 |
| 0040 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 3 | EACH | 250.00 | 750.00 | 257.00 | 771.00 | 200.00 | 600.00 | 287.00 | 861.00 |
| 0041 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 225.00 | 675.00 | 228.00 | 684.00 | 200.00 | 600.00 | 255.00 | 765.00 |
| 0042 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 400.00 | 1,200.00 | 400.00 | 1,200.00 | 200.00 | 600.00 | 446.00 | 1,338.00 |
| 0043 | 732-05-00100 | Removal of Existing Markings | 0.17 | MILE | 4,000.00 | 680.00 | 4,008.00 | 681.36 | 6,000.00 | 1,020.00 | 4,460.40 | 758.27 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 2,003.72 | 2,003.72 | 5,000.00 | 5,000.00 | 7,391.52 | 7,391.52 |
| 0045 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,500 | INLF | 1.00 | 1,500.00 | 0.95 | 1,425.00 | 3.50 | 5,250.00 | 4.15 | 6,225.00 |
| CONTRACTOR TOTAL | 280,518.25 | 326,417.00 | 331,590.13 | 388,504.67 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Merrick, LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 166.7 | SQYD | 7.00 | 1,166.90 |
| 0002 | 202-02-32000 | Removal of Paved Ditches | 5 | SQYD | 0.00 | 0.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 35,000.00 | 35,000.00 |
| 0004 | 204-06-00100 | Temporary Silt Fencing | 2,342 | LNFT | 0.40 | 936.80 |
| 0005 | 302-02-06121 | Class II Base Course (12" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 1,551.9 | SQYD | 40.00 | 62,076.00 |
| 0006 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 1,462 | SQYD | 75.00 | 109,650.00 |
| 0007 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 10 | LNFT | 30.00 | 300.00 |
| 0008 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,000.00 | 5,000.00 |
| 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 |
| 0010 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 1,140 | LNFT | 0.25 | 285.00 |
| 0011 | 716-01-00100 | Mulch (Vegetative) | 1.1 | TON | 500.00 | 550.00 |
| 0012 | 717-01-00100 | Seeding | 16 | LB | 6.00 | 96.00 |
| 0013 | 718-01-00100 | Fertilizer | 521 | LB | 0.50 | 260.50 |
| 0014 | 726-01-00100 | Bedding Material | 0.6 | CUYD | 10.00 | 6.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 40,000.00 | 40,000.00 |
| 0016 | 729-01-00103 | Sign (Type A)(Relocate) | 10 | SQFT | 5.00 | 50.00 |
| 0017 | 729-08-00200 | Mounting (3 1/2" Size Post) | 1 | EACH | 1,500.00 | 1,500.00 |
| 0018 | 729-16-00200 | Object Marker Assembly (Type 2) | 1 | EACH | 50.00 | 50.00 |
| 0019 | 730-01-00100 | Trenching and Backfilling | 1,210 | LNFT | 3.00 | 3,630.00 |
| 0020 | 730-02-01080 | Conduit with Conductors (PVC/HDPE) (1 1/2") (2#6, 1#6 Bare Solid Ground) | 1,210 | LNFT | 4.50 | 5,445.00 |
| 0021 | 730-04-00200 | Jacked or Bored Casing (6" Diameter) (PVC/HDPE) | 130 | LNFT | 40.00 | 5,200.00 |
| 0022 | 730-05-11100 | Light Pole (40') (Steel) (Single Arm) | 4 | EACH | 5,000.00 | 20,000.00 |
| 0023 | 730-07-10000 | Luminaire (200 Watt, High Pressure Sodium) | 8 | EACH | 450.00 | 3,600.00 |
| 0024 | 730-09-00100 | Electrical System | 1 | LUMP | 2,000.00 | 2,000.00 |
| 0025 | 730-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 2,000.00 | 2,000.00 |
| 0026 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) (Steel, Single Arm, 40') | 1 | EACH | 1,000.00 | 1,000.00 |
| 0027 | 730-12-00100 | Removal and Storage of Light Poles (Ground Mounted) (Steel, Double Arm, 40') | 1 | EACH | 1,000.00 | 1,000.00 |
| 0028 | 730-13-00100 | Removal and Disposal of Light Pole Foundation | 2 | EACH | 500.00 | 1,000.00 |
| 0029 | 730-14-00100 | Removal and Disposal of Luminaires | 7 | EACH | 50.00 | 350.00 |
| 0030 | 730-15-11100 | Relocate Light Poles (40') (Steel) (Single Arm) | 4 | EACH | 3,000.00 | 12,000.00 |
| 0031 | 730-16-00100 | Underground Junction Box (12" x 12") | 8 | EACH | 250.00 | 2,000.00 |
| 0032 | 730-16-00300 | Underground Junction Box (13" x 24") | 4 | EACH | 400.00 | 1,600.00 |
| 0033 | 730-19-00010 | Modular Breakaway Cable System | 8 | EACH | 1,800.00 | 14,400.00 |
| 0034 | 730-21-00020 | Duct Marker (Concrete) | 4 | EACH | 100.00 | 400.00 |
| 0035 | 730-22-00420 | Underground Marker Tape (6")(Detectable) | 1,210 | LNFT | 1.00 | 1,210.00 |
| 0036 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 327 | LNFT | 1.50 | 490.50 |
| 0037 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 27 | LNFT | 8.00 | 216.00 |
| 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.208 | MILE | 4,038.46 | 840.00 |
| 0039 | 732-03-02040 | Plastic Pvmt Strip (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.106 | MILE | 6,226.42 | 660.00 |
| 0040 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 3 | EACH | 225.00 | 675.00 |
| 0041 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 200.00 | 600.00 |
| 0042 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 350.00 | 1,050.00 |
| 0043 | 732-05-00100 | Removal of Existing Markings | 0.17 | MILE | 3,500.00 | 595.00 |
| 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 36,500.00 | 36,500.00 |
| 0045 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,500 | INLF | 0.00 | 0.00 |
| CONTRACTOR TOTAL | 405,388.70 | |||||