Bid Tabulations
Letting of
01/09/2013
LA DOTD Headquarters
| Lead Project: H.002912.6 | |
| Parish: Lafourche | |
| Routes: US 90 | |
| Description: US 90: NORTH SERVICE ROAD LA 1 - LA 182 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,662,923.30 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06487 | Huey Stockstill, Inc. | $1,098,598.40 |
| 2 | 06276 | Barriere Construction Co., LLC | $1,212,530.10 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Huey Stockstill, Inc. |
- 2 - Barriere Construction Co., LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 787.5 | LNFT | 17.00 | 13,387.50 | 5.00 | 3,937.50 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,500 | CUYD | 10.00 | 15,000.00 | 5.00 | 7,500.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,200 | CUYD | 50.00 | 110,000.00 | 10.00 | 22,000.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 8,089.7 | TON | 69.00 | 558,189.30 | 85.00 | 687,624.50 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 484 | TON | 69.00 | 33,396.00 | 130.00 | 62,920.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 17,186 | SQYD | 2.00 | 34,372.00 | 1.25 | 21,482.50 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -716 | CUYD | 0.00 | 0.00 | 0.10 | -71.60 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,500 | SQYD | 80.00 | 120,000.00 | 70.00 | 105,000.00 |
| 0009 | 704-03-00100 | Blocked Out Guard Rail | 188 | LNFT | 20.00 | 3,760.00 | 23.00 | 4,324.00 |
| 0010 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 65.00 | 19,500.00 | 67.00 | 20,100.00 |
| 0011 | 704-11-00100 | Guard Rail End Treatment (Flared) | 12 | EACH | 2,600.00 | 31,200.00 | 2,400.00 | 28,800.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,000.00 | 8,000.00 | 90,000.00 | 90,000.00 |
| 0013 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 144 | LNFT | 0.60 | 86.40 | 0.50 | 72.00 |
| 0014 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.232 | MILE | 250.00 | 808.00 | 125.00 | 404.00 |
| 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.996 | MILE | 450.00 | 3,148.20 | 250.00 | 1,749.00 |
| 0016 | 717-01-00100 | Seeding | 195 | LB | 5.00 | 975.00 | 5.00 | 975.00 |
| 0017 | 718-01-00100 | Fertilizer | 6,500 | LB | 0.20 | 1,300.00 | 0.50 | 3,250.00 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 89,000.00 | 89,000.00 | 100,000.00 | 100,000.00 |
| 0019 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 75.00 | 900.00 | 80.00 | 960.00 |
| 0020 | 731-02-00100 | Reflectorized Raised Pavement Markers | 725 | EACH | 5.00 | 3,625.00 | 5.50 | 3,987.50 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 144 | LNFT | 4.50 | 648.00 | 5.25 | 756.00 |
| 0022 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.308 | MILE | 2,350.00 | 12,473.80 | 2,600.00 | 13,800.80 |
| 0023 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.556 | MILE | 700.00 | 1,789.20 | 900.00 | 2,300.40 |
| 0024 | 732-05-00100 | Removal of Existing Markings BRIDGES | 0.204 | MILE | 10,000.00 | 2,040.00 | 5,250.00 | 1,071.00 |
| 0025 | 735-01-00100 | Mailboxes | 45 | EACH | 10.00 | 450.00 | 12.50 | 562.50 |
| 0026 | 735-02-00100 | Mailbox Supports (Single) | 43 | EACH | 130.00 | 5,590.00 | 100.00 | 4,300.00 |
| 0027 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 500.00 | 500.00 | 125.00 | 125.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 |
| 0029 | NS-500-00280 | Surface Preparation | 1 | LUMP | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 |
| 0030 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 46,000 | INLF | 0.01 | 460.00 | 0.10 | 4,600.00 |
| CONTRACTOR TOTAL | 1,098,598.40 | 1,212,530.10 | ||||||