Bid Tabulations
Letting of
06/27/2012
LA DOTD Headquarters
| Lead Project: H.002550.6-R1 | |
| Parish: Jefferson | |
| Routes: US 90 B/I-910 | |
| Description: MACARTHUR INTERCHANGE COMPLETION - PH. 1A | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, TRAFFIC SIGNALIZATION, AND RELATED WORK. | |
| Estimated Construction Cost: $5,340,777.59 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $1,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $4,385,467.70 | 210 | $4,595,467.70 |
| 2 | 34567 | James Construction Group LLC | $4,563,233.87 | 370 | $4,933,233.87 |
| 3 | 06276 | Barriere Construction Co., LLC | $4,736,465.41 | 300 | $5,036,465.41 |
| 4 | 48896 | Command Construction Industries LLC | $5,021,387.80 | 270 | $5,291,387.80 |
| 5 | 50078 | Fenton Excavating & Const. Inc. | $5,218,620.98 | 150 | $5,368,620.98 |
| 6 | 38610 | Three C's Properties Inc | $5,320,116.72 | 268 | $5,588,116.72 |
| 7 | 01033 | Wallace C. Drennan, Inc. | $5,661,550.80 | 365 | $6,026,550.80 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - James Construction Group LLC |
- 3 - Barriere Construction Co., LLC |
- 4 - Command Construction Industries LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 27,000.00 | 27,000.00 | 100,000.00 | 100,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 200,000.00 | 200,000.00 | 125,000.00 | 125,000.00 | 242,000.00 | 242,000.00 | 150,000.00 | 150,000.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 7,772.7 | SQYD | 6.00 | 46,636.20 | 8.00 | 62,181.60 | 7.00 | 54,408.90 | 8.00 | 62,181.60 |
| 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 4,761.6 | LNFT | 5.00 | 23,808.00 | 7.00 | 33,331.20 | 5.00 | 23,808.00 | 10.00 | 47,616.00 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | 3,346 | SQYD | 10.00 | 33,460.00 | 17.00 | 56,882.00 | 10.00 | 33,460.00 | 10.00 | 33,460.00 |
| 0006 | 202-02-38220 | Removal of Sign Supports | 9 | EACH | 150.00 | 1,350.00 | 150.00 | 1,350.00 | 160.00 | 1,440.00 | 150.00 | 1,350.00 |
| 0007 | 202-02-38300 | Removal of Sign and U-Channel Post | 14 | EACH | 75.00 | 1,050.00 | 75.00 | 1,050.00 | 80.00 | 1,120.00 | 25.00 | 350.00 |
| 0008 | 202-02-38360 | Removal of Sign Faces | 5 | EACH | 75.00 | 375.00 | 75.00 | 375.00 | 80.00 | 400.00 | 50.00 | 250.00 |
| 0009 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 6,500.00 | 6,500.00 | 6,150.00 | 6,150.00 | 6,500.00 | 6,500.00 | 1,000.00 | 1,000.00 |
| 0010 | 202-03-00010 | Relocation Security Fence and Roller Gate | 1 | EACH | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 |
| 0011 | 202-03-38000 | Relocation of Sign Various Locations | 4 | EACH | 50.00 | 200.00 | 50.00 | 200.00 | 54.00 | 216.00 | 700.00 | 2,800.00 |
| 0012 | 203-01-00100 | General Excavation | 7,262 | CUYD | 12.00 | 87,144.00 | 10.00 | 72,620.00 | 11.00 | 79,882.00 | 15.00 | 108,930.00 |
| 0013 | 203-03-00100 | Embankment | 2,626 | CUYD | 21.00 | 55,146.00 | 35.00 | 91,910.00 | 27.00 | 70,902.00 | 25.00 | 65,650.00 |
| 0014 | 203-04-00100 | Nonplastic Embankment | 3,397 | CUYD | 20.00 | 67,940.00 | 30.00 | 101,910.00 | 22.00 | 74,734.00 | 25.00 | 84,925.00 |
| 0015 | 203-08-00100 | Geotextile Fabric | 10,126 | SQYD | 1.50 | 15,189.00 | 2.50 | 25,315.00 | 1.50 | 15,189.00 | 2.00 | 20,252.00 |
| 0016 | 204-02-00100 | Temporary Hay or Straw Bales | 250 | EACH | 15.00 | 3,750.00 | 17.00 | 4,250.00 | 13.00 | 3,250.00 | 1.00 | 250.00 |
| 0017 | 204-06-00100 | Temporary Silt Fencing | 1,762 | LNFT | 2.00 | 3,524.00 | 2.50 | 4,405.00 | 2.00 | 3,524.00 | 2.00 | 3,524.00 |
| 0018 | 302-02-02000 | Class II Base Course (6" Thick) | 8,667.4 | SQYD | 7.00 | 60,671.80 | 14.00 | 121,343.60 | 12.00 | 104,008.80 | 13.00 | 112,676.20 |
| 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 1,200 | CUYD | 50.00 | 60,000.00 | 75.00 | 90,000.00 | 20.00 | 24,000.00 | 1.00 | 1,200.00 |
| 0020 | 502-01-00100 | Superpave Asphaltic Concrete | 7,333 | TON | 117.00 | 857,961.00 | 111.00 | 813,963.00 | 108.00 | 791,964.00 | 120.00 | 879,960.00 |
| 0021 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 418 | TON | 117.00 | 48,906.00 | 150.00 | 62,700.00 | 108.00 | 45,144.00 | 120.00 | 50,160.00 |
| 0022 | 509-01-00100 | Cold Planing Asphaltic Pavement | 210 | SQYD | 20.00 | 4,200.00 | 10.00 | 2,100.00 | 28.00 | 5,880.00 | 30.00 | 6,300.00 |
| 0023 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -12 | CUYD | 15.00 | -180.00 | 0.01 | -0.12 | 1.00 | -12.00 | 1.00 | -12.00 |
| 0024 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 136 | SQYD | 100.00 | 13,600.00 | 190.00 | 25,840.00 | 200.00 | 27,200.00 | 200.00 | 27,200.00 |
| 0025 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 724 | LNFT | 45.00 | 32,580.00 | 70.00 | 50,680.00 | 65.00 | 47,060.00 | 80.00 | 57,920.00 |
| 0026 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 271 | LNFT | 50.00 | 13,550.00 | 75.00 | 20,325.00 | 65.00 | 17,615.00 | 100.00 | 27,100.00 |
| 0027 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 138 | LNFT | 65.00 | 8,970.00 | 100.00 | 13,800.00 | 105.00 | 14,490.00 | 125.00 | 17,250.00 |
| 0028 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 333 | LNFT | 95.00 | 31,635.00 | 150.00 | 49,950.00 | 110.00 | 36,630.00 | 150.00 | 49,950.00 |
| 0029 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 164 | LNFT | 125.00 | 20,500.00 | 160.00 | 26,240.00 | 140.00 | 22,960.00 | 175.00 | 28,700.00 |
| 0030 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 299 | LNFT | 155.00 | 46,345.00 | 200.00 | 59,800.00 | 150.00 | 44,850.00 | 200.00 | 59,800.00 |
| 0031 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 234 | LNFT | 190.00 | 44,460.00 | 240.00 | 56,160.00 | 180.00 | 42,120.00 | 250.00 | 58,500.00 |
| 0032 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 51 | LNFT | 65.00 | 3,315.00 | 170.00 | 8,670.00 | 120.00 | 6,120.00 | 80.00 | 4,080.00 |
| 0033 | 701-04-01140 | Storm Drain Pipe Arch (54" Equiv. RCPA) | 271 | LNFT | 220.00 | 59,620.00 | 250.00 | 67,750.00 | 220.00 | 59,620.00 | 350.00 | 94,850.00 |
| 0034 | 701-04-01180 | Storm Drain Pipe Arch (72" Equiv. RCPA) | 788 | LNFT | 335.00 | 263,980.00 | 330.00 | 260,040.00 | 370.00 | 291,560.00 | 450.00 | 354,600.00 |
| 0035 | 702-02-00100 | Manholes (MH-06) | 1 | EACH | 4,000.00 | 4,000.00 | 6,600.00 | 6,600.00 | 8,000.00 | 8,000.00 | 10,000.00 | 10,000.00 |
| 0036 | 702-02-00300 | Manholes (R-CB-11 MOD) | 1 | EACH | 5,500.00 | 5,500.00 | 7,700.00 | 7,700.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0037 | 702-03-00100 | Catch Basins (CB-01) | 10 | EACH | 2,300.00 | 23,000.00 | 2,900.00 | 29,000.00 | 2,800.00 | 28,000.00 | 5,000.00 | 50,000.00 |
| 0038 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 5,000.00 | 5,000.00 | 5,400.00 | 5,400.00 | 4,200.00 | 4,200.00 | 7,500.00 | 7,500.00 |
| 0039 | 702-03-00300 | Catch Basins (CB-04) | 4 | EACH | 1,800.00 | 7,200.00 | 4,100.00 | 16,400.00 | 2,700.00 | 10,800.00 | 5,000.00 | 20,000.00 |
| 0040 | 702-03-00600 | Catch Basins (CB-07) | 11 | EACH | 5,500.00 | 60,500.00 | 6,000.00 | 66,000.00 | 7,500.00 | 82,500.00 | 7,500.00 | 82,500.00 |
| 0041 | 702-03-00700 | Catch Basins (CB-08) | 6 | EACH | 7,500.00 | 45,000.00 | 8,500.00 | 51,000.00 | 10,000.00 | 60,000.00 | 10,000.00 | 60,000.00 |
| 0042 | 702-03-00800 | Catch Basins (CB-09) | 5 | EACH | 6,500.00 | 32,500.00 | 9,000.00 | 45,000.00 | 9,500.00 | 47,500.00 | 10,000.00 | 50,000.00 |
| 0043 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 1,000.00 | 1,000.00 |
| 0044 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 23 | LNFT | 55.00 | 1,265.00 | 20.00 | 460.00 | 30.00 | 690.00 | 100.00 | 2,300.00 |
| 0045 | 705-09-00100 | Rebuilt Fence | 408 | LNFT | 55.00 | 22,440.00 | 20.00 | 8,160.00 | 25.00 | 10,200.00 | 35.00 | 14,280.00 |
| 0046 | 706-01-00100 | Concrete Walk (4" Thick) | 1,022.6 | SQYD | 48.00 | 49,084.80 | 35.00 | 35,791.00 | 63.80 | 65,241.88 | 50.00 | 51,130.00 |
| 0047 | 706-02-00300 | Concrete Drive (8" Thick) | 832.2 | SQYD | 65.00 | 54,093.00 | 50.00 | 41,610.00 | 70.00 | 58,254.00 | 75.00 | 62,415.00 |
| 0048 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 9.9 | SQYD | 60.00 | 594.00 | 60.00 | 594.00 | 72.75 | 720.23 | 60.00 | 594.00 |
| 0049 | 706-04-00100 | Handicapped Curb Ramps | 26 | EACH | 2,200.00 | 57,200.00 | 1,500.00 | 39,000.00 | 1,080.00 | 28,080.00 | 500.00 | 13,000.00 |
| 0050 | 707-03-00100 | Combination Concrete Curb and Gutter (4" High Mountable) | 647.2 | LNFT | 25.00 | 16,180.00 | 22.00 | 14,238.40 | 31.25 | 20,225.00 | 30.00 | 19,416.00 |
| 0051 | 707-03-00100 | Combination Concrete Curb and Gutter (6" High Barrier) | 1,507.3 | LNFT | 25.00 | 37,682.50 | 25.00 | 37,682.50 | 30.00 | 45,219.00 | 30.00 | 45,219.00 |
| 0052 | 708-01-00100 | Right-of-Way Monument | 23 | EACH | 250.00 | 5,750.00 | 200.00 | 4,600.00 | 200.00 | 4,600.00 | 300.00 | 6,900.00 |
| 0053 | 710-01-00100 | Flowable Fill | 212 | CUYD | 200.00 | 42,400.00 | 200.00 | 42,400.00 | 190.00 | 40,280.00 | 150.00 | 31,800.00 |
| 0054 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 | 45,000.00 | 45,000.00 | 120,000.00 | 120,000.00 | 100,000.00 | 100,000.00 |
| 0055 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 7,500 | LNFT | 0.20 | 1,500.00 | 0.16 | 1,200.00 | 0.17 | 1,275.00 | 0.50 | 3,750.00 |
| 0056 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 250 | LNFT | 0.30 | 75.00 | 0.25 | 62.50 | 0.25 | 62.50 | 1.00 | 250.00 |
| 0057 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 640 | LNFT | 0.40 | 256.00 | 0.35 | 224.00 | 0.35 | 224.00 | 1.00 | 640.00 |
| 0058 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 50 | LNFT | 1.10 | 55.00 | 1.00 | 50.00 | 1.00 | 50.00 | 2.00 | 100.00 |
| 0059 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.5 | MILE | 500.00 | 750.00 | 490.00 | 735.00 | 500.00 | 750.00 | 5,000.00 | 7,500.00 |
| 0060 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.59 | MILE | 4,000.00 | 2,360.00 | 3,850.00 | 2,271.50 | 4,000.00 | 2,360.00 | 10,000.00 | 5,900.00 |
| 0061 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.66 | MILE | 12,000.00 | 7,920.00 | 11,500.00 | 7,590.00 | 12,000.00 | 7,920.00 | 20,000.00 | 13,200.00 |
| 0062 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 4 | EACH | 55.00 | 220.00 | 50.00 | 200.00 | 53.00 | 212.00 | 100.00 | 400.00 |
| 0063 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 55.00 | 220.00 | 50.00 | 200.00 | 53.00 | 212.00 | 100.00 | 400.00 |
| 0064 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 137 | EACH | 900.00 | 123,300.00 | 500.00 | 68,500.00 | 320.00 | 43,840.00 | 750.00 | 102,750.00 |
| 0065 | 716-01-00200 | Mulch (Fiber) | 0.5 | TON | 1,100.00 | 550.00 | 2,000.00 | 1,000.00 | 2,100.00 | 1,050.00 | 2,000.00 | 1,000.00 |
| 0066 | 717-01-00100 | Seeding | 98 | LB | 22.00 | 2,156.00 | 9.50 | 931.00 | 10.00 | 980.00 | 1.00 | 98.00 |
| 0067 | 718-01-00100 | Fertilizer | 3,887 | LB | 2.00 | 7,774.00 | 0.60 | 2,332.20 | 0.60 | 2,332.20 | 1.00 | 3,887.00 |
| 0068 | 719-04-00100 | Landscaping | 1 | LUMP | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 10,500.00 | 10,500.00 | 2,500.00 | 2,500.00 |
| 0069 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 30,000.00 | 30,000.00 | 8,000.00 | 8,000.00 | 25,000.00 | 25,000.00 | 1,000.00 | 1,000.00 |
| 0070 | 726-01-00100 | Bedding Material | 580.3 | CUYD | 85.00 | 49,325.50 | 72.03 | 41,799.01 | 60.00 | 34,818.00 | 125.00 | 72,537.50 |
| 0071 | 727-01-00100 | Mobilization | 1 | LUMP | 247,000.00 | 247,000.00 | 450,000.00 | 450,000.00 | 440,000.00 | 440,000.00 | 500,000.00 | 500,000.00 |
| 0072 | 729-01-00100 | Sign (Type A) | 260 | SQFT | 27.00 | 7,020.00 | 25.00 | 6,500.00 | 25.00 | 6,500.00 | 26.00 | 6,760.00 |
| 0073 | 729-04-00100 | Sign (Type D) | 60 | SQFT | 32.00 | 1,920.00 | 30.00 | 1,800.00 | 30.00 | 1,800.00 | 28.00 | 1,680.00 |
| 0074 | 729-08-00100 | Mounting (2 1/2" Size Post) | 11 | EACH | 1,000.00 | 11,000.00 | 950.00 | 10,450.00 | 1,000.00 | 11,000.00 | 850.00 | 9,350.00 |
| 0075 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 6 | EACH | 1,600.00 | 9,600.00 | 1,500.00 | 9,000.00 | 1,500.00 | 9,000.00 | 1,500.00 | 9,000.00 |
| 0076 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 2 | EACH | 2,000.00 | 4,000.00 | 1,800.00 | 3,600.00 | 1,800.00 | 3,600.00 | 1,600.00 | 3,200.00 |
| 0077 | 729-21-00100 | U-Channel Post | 4 | EACH | 105.00 | 420.00 | 100.00 | 400.00 | 100.00 | 400.00 | 100.00 | 400.00 |
| 0078 | 730-01-00100 | Trenching and Backfilling | 1,463 | LNFT | 5.00 | 7,315.00 | 4.50 | 6,583.50 | 5.00 | 7,315.00 | 5.00 | 7,315.00 |
| 0079 | 730-15-12000 | Relocate Light Poles (40') (Aluminum) | 1 | EACH | 7,800.00 | 7,800.00 | 7,350.00 | 7,350.00 | 7,500.00 | 7,500.00 | 7,500.00 | 7,500.00 |
| 0080 | 731-02-00100 | Reflectorized Raised Pavement Markers | 150 | EACH | 6.50 | 975.00 | 6.00 | 900.00 | 10.00 | 1,500.00 | 10.00 | 1,500.00 |
| 0081 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 4,850 | LNFT | 0.85 | 4,122.50 | 0.60 | 2,910.00 | 0.65 | 3,152.50 | 1.00 | 4,850.00 |
| 0082 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 210 | LNFT | 2.00 | 420.00 | 1.20 | 252.00 | 1.30 | 273.00 | 3.00 | 630.00 |
| 0083 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 42 | LNFT | 5.00 | 210.00 | 4.00 | 168.00 | 4.30 | 180.60 | 10.00 | 420.00 |
| 0084 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 173 | LNFT | 6.00 | 1,038.00 | 5.00 | 865.00 | 5.30 | 916.90 | 10.00 | 1,730.00 |
| 0085 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 1,000.00 | 1,000.00 | 950.00 | 950.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0086 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 225.00 | 900.00 | 200.00 | 800.00 | 200.00 | 800.00 | 300.00 | 1,200.00 |
| 0087 | 732-05-00100 | Removal of Existing Markings | 2 | MILE | 4,000.00 | 8,000.00 | 3,000.00 | 6,000.00 | 3,300.00 | 6,600.00 | 1,000.00 | 2,000.00 |
| 0088 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) | 270 | LNFT | 220.00 | 59,400.00 | 100.00 | 27,000.00 | 120.00 | 32,400.00 | 250.00 | 67,500.00 |
| 0089 | 736-03-00200 | Jacked or Bored Conduit (2" HPDE, Sch 80) | 205 | LNFT | 12.50 | 2,562.50 | 12.00 | 2,460.00 | 12.00 | 2,460.00 | 12.00 | 2,460.00 |
| 0090 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 800 | LNFT | 15.00 | 12,000.00 | 14.00 | 11,200.00 | 15.00 | 12,000.00 | 14.00 | 11,200.00 |
| 0091 | 736-04-04060 | Signal Support (20' Single Mast Arm) | 1 | EACH | 7,500.00 | 7,500.00 | 6,985.00 | 6,985.00 | 7,500.00 | 7,500.00 | 7,000.00 | 7,000.00 |
| 0092 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 2 | EACH | 8,000.00 | 16,000.00 | 7,550.00 | 15,100.00 | 8,000.00 | 16,000.00 | 7,500.00 | 15,000.00 |
| 0093 | 736-04-04100 | Signal Support (30' Single Mast Arm) | 2 | EACH | 8,700.00 | 17,400.00 | 8,100.00 | 16,200.00 | 8,500.00 | 17,000.00 | 8,500.00 | 17,000.00 |
| 0094 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 1 | EACH | 9,700.00 | 9,700.00 | 9,050.00 | 9,050.00 | 9,700.00 | 9,700.00 | 9,500.00 | 9,500.00 |
| 0095 | 736-04-04140 | Signal Support (40' Single Mast Arm) | 1 | EACH | 10,600.00 | 10,600.00 | 9,950.00 | 9,950.00 | 11,000.00 | 11,000.00 | 10,500.00 | 10,500.00 |
| 0096 | 736-04-05005 | Signal Support (35'span, 25' span add-on arm) | 1 | EACH | 13,200.00 | 13,200.00 | 12,350.00 | 12,350.00 | 13,000.00 | 13,000.00 | 12,000.00 | 12,000.00 |
| 0097 | 736-04-05008 | Signal Support (40'span, 35' span add-on arm) | 1 | EACH | 15,400.00 | 15,400.00 | 14,450.00 | 14,450.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0098 | 736-04-05010 | Signal Support (45'span, 30' span add-on arm) | 1 | EACH | 15,700.00 | 15,700.00 | 14,750.00 | 14,750.00 | 16,000.00 | 16,000.00 | 15,500.00 | 15,500.00 |
| 0099 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 25 | EACH | 900.00 | 22,500.00 | 845.00 | 21,125.00 | 900.00 | 22,500.00 | 850.00 | 21,250.00 |
| 0100 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 2 | EACH | 950.00 | 1,900.00 | 885.00 | 1,770.00 | 950.00 | 1,900.00 | 1,000.00 | 2,000.00 |
| 0101 | 736-05-03000 | Signal Heads (4 Section, 12" Led Lens, R, Y, LT. G, G) | 1 | EACH | 1,300.00 | 1,300.00 | 1,220.00 | 1,220.00 | 1,300.00 | 1,300.00 | 1,500.00 | 1,500.00 |
| 0102 | 736-05-04000 | Signal Heads (5 Section, 12" Led Lens, R, LT. Y, Y, LT. G, G) | 2 | EACH | 1,400.00 | 2,800.00 | 1,325.00 | 2,650.00 | 1,400.00 | 2,800.00 | 1,500.00 | 3,000.00 |
| 0103 | 736-06-00200 | Signal Service (Pedestal Required) | 2 | EACH | 2,200.00 | 4,400.00 | 2,050.00 | 4,100.00 | 2,100.00 | 4,200.00 | 2,500.00 | 5,000.00 |
| 0104 | 736-08-00111 | Sig Cntrlr (TS-2, Type 2)(Type 6E Cabinet)(Furnish & Install) | 2 | EACH | 30,000.00 | 60,000.00 | 27,650.00 | 55,300.00 | 30,000.00 | 60,000.00 | 30,000.00 | 60,000.00 |
| 0105 | 736-09-00100 | Loop Detector | 545 | LNFT | 14.00 | 7,630.00 | 13.00 | 7,085.00 | 14.00 | 7,630.00 | 20.00 | 10,900.00 |
| 0106 | 736-10-00200 | Underground Junction Box (Type E) | 4 | EACH | 425.00 | 1,700.00 | 400.00 | 1,600.00 | 400.00 | 1,600.00 | 500.00 | 2,000.00 |
| 0107 | 736-10-00300 | Underground Junction Box (Type F) | 17 | EACH | 500.00 | 8,500.00 | 460.00 | 7,820.00 | 500.00 | 8,500.00 | 500.00 | 8,500.00 |
| 0108 | 736-10-00500 | Underground Junction Box (Type H) | 2 | EACH | 875.00 | 1,750.00 | 825.00 | 1,650.00 | 900.00 | 1,800.00 | 900.00 | 1,800.00 |
| 0109 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 925 | LNFT | 2.00 | 1,850.00 | 1.80 | 1,665.00 | 2.00 | 1,850.00 | 2.00 | 1,850.00 |
| 0110 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 539 | LNFT | 3.50 | 1,886.50 | 3.10 | 1,670.90 | 3.30 | 1,778.70 | 3.00 | 1,617.00 |
| 0111 | 736-12-01001 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 4,810 | LNFT | 1.25 | 6,012.50 | 1.10 | 5,291.00 | 1.10 | 5,291.00 | 1.00 | 4,810.00 |
| 0112 | 736-12-02020 | Conductor (3c, #14 awg) | 251 | LNFT | 3.30 | 828.30 | 3.10 | 778.10 | 3.30 | 828.30 | 3.00 | 753.00 |
| 0113 | 736-13-00400 | Cable (6C Signal) | 1,625 | LNFT | 2.00 | 3,250.00 | 1.70 | 2,762.50 | 1.80 | 2,925.00 | 2.00 | 3,250.00 |
| 0114 | 736-13-00500 | Cable (10C Signal) | 2,710 | LNFT | 2.25 | 6,097.50 | 2.00 | 5,420.00 | 2.00 | 5,420.00 | 2.00 | 5,420.00 |
| 0115 | 740-01-00100 | Construction Layout | 1 | LUMP | 125,000.00 | 125,000.00 | 78,538.08 | 78,538.08 | 80,000.00 | 80,000.00 | 100,000.00 | 100,000.00 |
| 0116 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 25,000.00 | 25,000.00 |
| 0117 | 741-01-02040 | Water Main (8" Ductile Iron) | 120 | LNFT | 150.00 | 18,000.00 | 140.00 | 16,800.00 | 150.00 | 18,000.00 | 200.00 | 24,000.00 |
| 0118 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 32,000.00 | 32,000.00 | 40,000.00 | 40,000.00 | 25,000.00 | 25,000.00 | 1,000.00 | 1,000.00 |
| 0119 | 804-01-00100 | Precast Concrete Piles (12") | 160 | LNFT | 80.85 | 12,936.00 | 110.00 | 17,600.00 | 200.00 | 32,000.00 | 200.00 | 32,000.00 |
| 0120 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 1,880 | LNFT | 12.55 | 23,594.00 | 22.00 | 41,360.00 | 13.00 | 24,440.00 | 25.00 | 47,000.00 |
| 0121 | 805-01-00700 | Class A Concrete (Bents) | 5 | CUYD | 4,500.00 | 22,500.00 | 1,200.00 | 6,000.00 | 3,000.00 | 15,000.00 | 500.00 | 2,500.00 |
| 0122 | 805-02-00100 | Class A(M) Concrete | 148.12 | CUYD | 855.00 | 126,642.60 | 820.00 | 121,458.40 | 1,300.00 | 192,556.00 | 250.00 | 37,030.00 |
| 0123 | 806-01-00100 | Deformed Reinforcing Steel | 21,570 | LB | 1.25 | 26,962.50 | 1.00 | 21,570.00 | 0.80 | 17,256.00 | 0.10 | 2,157.00 |
| 0124 | NS-203-00006 | Exploratory Excavation | 100 | CUYD | 40.00 | 4,000.00 | 300.00 | 30,000.00 | 200.00 | 20,000.00 | 100.00 | 10,000.00 |
| 0125 | NS-203-00007 | Temporary Sheeting and Bracing | 1 | LUMP | 4,000.00 | 4,000.00 | 1,000.00 | 1,000.00 | 1.00 | 1.00 | 25,000.00 | 25,000.00 |
| 0126 | NS-203-00008 | Control of Groundwater | 1 | LUMP | 3,000.00 | 3,000.00 | 1,000.00 | 1,000.00 | 1.00 | 1.00 | 1,000.00 | 1,000.00 |
| 0127 | NS-300-00060 | Geogrid | 8,668 | SQYD | 3.50 | 30,338.00 | 3.00 | 26,004.00 | 1.80 | 15,602.40 | 3.00 | 26,004.00 |
| 0128 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement (Full Depth) | 11,410 | INLF | 1.00 | 11,410.00 | 1.00 | 11,410.00 | 0.85 | 9,698.50 | 1.00 | 11,410.00 |
| 0129 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement (Full Depth) | 5,289 | INLF | 1.00 | 5,289.00 | 1.00 | 5,289.00 | 1.00 | 5,289.00 | 1.00 | 5,289.00 |
| 0130 | NS-700-00220 | Impact Attenuator (Kinetic) | 3 | EACH | 14,000.00 | 42,000.00 | 22,000.00 | 66,000.00 | 13,500.00 | 40,500.00 | 12,850.00 | 38,550.00 |
| 0131 | NS-736-00005 | Video Detection Cabinet Components | 2 | EACH | 8,500.00 | 17,000.00 | 8,020.00 | 16,040.00 | 8,000.00 | 16,000.00 | 9,000.00 | 18,000.00 |
| 0132 | NS-736-00006 | Video Detection Camera | 8 | EACH | 2,000.00 | 16,000.00 | 1,890.00 | 15,120.00 | 2,000.00 | 16,000.00 | 2,000.00 | 16,000.00 |
| 0133 | NS-736-00007 | Video Detection Training | 1 | LUMP | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 |
| 0134 | NS-736-00014 | Tubular Marker | 125 | EACH | 48.00 | 6,000.00 | 50.00 | 6,250.00 | 50.00 | 6,250.00 | 0.50 | 62.50 |
| 0135 | NS-804-00006 | Vibration Monitoring | 50 | DALY | 450.00 | 22,500.00 | 500.00 | 25,000.00 | 300.00 | 15,000.00 | 100.00 | 5,000.00 |
| 0136 | NS-MSC-00120 | Drainage Structure MH-14x9 | 6 | EACH | 10,000.00 | 60,000.00 | 9,400.00 | 56,400.00 | 25,000.00 | 150,000.00 | 15,000.00 | 90,000.00 |
| 0137 | NS-P26-06000 | Fire Hydrants (Jefferson Parish) | 4 | EACH | 3,800.00 | 15,200.00 | 3,900.00 | 15,600.00 | 4,000.00 | 16,000.00 | 5,000.00 | 20,000.00 |
| 0138 | NS-P26-06020 | Fittings for Waterlines (DI) (Jefferson Parish) | 1,000 | LB | 10.00 | 10,000.00 | 5.25 | 5,250.00 | 6.00 | 6,000.00 | 10.00 | 10,000.00 |
| 0139 | NS-P26-07000 | Gate Valve and Valve Box (8") (Jefferson Parish) | 4 | EACH | 2,000.00 | 8,000.00 | 1,450.00 | 5,800.00 | 3,000.00 | 12,000.00 | 2,000.00 | 8,000.00 |
| 0140 | NS-P26-12000 | Long Body Transitional Coupling (4") (Jefferson Parish) | 1 | EACH | 1,000.00 | 1,000.00 | 350.00 | 350.00 | 150.00 | 150.00 | 1,250.00 | 1,250.00 |
| 0141 | NS-P26-12020 | Long Body Transitional Coupling (6") (Jefferson Parish) | 3 | EACH | 1,000.00 | 3,000.00 | 350.00 | 1,050.00 | 200.00 | 600.00 | 1,250.00 | 3,750.00 |
| 0142 | NS-P26-12040 | Long Body Transitional Coupling (8") (Jefferson Parish) | 2 | EACH | 1,000.00 | 2,000.00 | 450.00 | 900.00 | 210.00 | 420.00 | 1,250.00 | 2,500.00 |
| 0143 | NS-P26-18000 | Removal and Disposal of Existing AC Waterline (Jefferson Parish) | 1,090 | LNFT | 25.00 | 27,250.00 | 15.00 | 16,350.00 | 20.00 | 21,800.00 | 20.00 | 21,800.00 |
| 0144 | NS-P26-23000 | Water Service Connections (Jefferson Parish) | 15 | EACH | 500.00 | 7,500.00 | 500.00 | 7,500.00 | 500.00 | 7,500.00 | 500.00 | 7,500.00 |
| 0145 | NS-P26-23060 | Waterline (8" PVC) (Jefferson Parish) | 2,180 | LNFT | 50.00 | 109,000.00 | 38.00 | 82,840.00 | 48.00 | 104,640.00 | 50.00 | 109,000.00 |
| 0146 | NS-P26-23120 | Waterline (6" PVC) (Restrained) (Jefferson Parish) | 60 | LNFT | 40.00 | 2,400.00 | 34.00 | 2,040.00 | 65.00 | 3,900.00 | 75.00 | 4,500.00 |
| 0147 | NS-P26-23140 | Waterline (8" PVC) (Restrained) (Jefferson Parish) | 60 | LNFT | 55.00 | 3,300.00 | 46.00 | 2,760.00 | 80.00 | 4,800.00 | 75.00 | 4,500.00 |
| 0148 | NS-P26-30000 | Sewer Force Main Relocation (10") | 1 | LUMP | 30,000.00 | 30,000.00 | 35,000.00 | 35,000.00 | 60,000.00 | 60,000.00 | 50,000.00 | 50,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 4,385,467.70 | 4,563,233.87 | 4,736,465.41 | 5,021,387.80 | ||||||||
| NUMBER OF DAYS BID AT $1000 PER DAY. | 210,000.00 | 370,000.00 | 300,000.00 | 270,000.00 | ||||||||
| TOTAL BID | 4,595,467.70 | 4,933,233.87 | 5,036,465.41 | 5,291,387.80 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Fenton Excavating & Const. Inc. |
- 6 - Three C's Properties Inc |
- 7 - Wallace C. Drennan, Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 72,737.50 | 72,737.50 | 14,112.53 | 14,112.53 | 100,000.00 | 100,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 73,600.00 | 73,600.00 | 264,127.78 | 264,127.78 | 100,000.00 | 100,000.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 7,772.7 | SQYD | 11.98 | 93,116.95 | 9.11 | 70,809.30 | 2.00 | 15,545.40 |
| 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 4,761.6 | LNFT | 6.11 | 29,093.38 | 6.46 | 30,759.94 | 0.00 | 0.00 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | 3,346 | SQYD | 10.92 | 36,538.32 | 9.49 | 31,753.54 | 15.00 | 50,190.00 |
| 0006 | 202-02-38220 | Removal of Sign Supports | 9 | EACH | 221.38 | 1,992.42 | 168.00 | 1,512.00 | 10.00 | 90.00 |
| 0007 | 202-02-38300 | Removal of Sign and U-Channel Post | 14 | EACH | 81.94 | 1,147.16 | 84.00 | 1,176.00 | 10.00 | 140.00 |
| 0008 | 202-02-38360 | Removal of Sign Faces | 5 | EACH | 139.44 | 697.20 | 84.00 | 420.00 | 10.00 | 50.00 |
| 0009 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 8,740.00 | 8,740.00 | 45,920.00 | 45,920.00 | 50,000.00 | 50,000.00 |
| 0010 | 202-03-00010 | Relocation Security Fence and Roller Gate | 1 | EACH | 10,925.00 | 10,925.00 | 15,120.00 | 15,120.00 | 10,000.00 | 10,000.00 |
| 0011 | 202-03-38000 | Relocation of Sign Various Locations | 4 | EACH | 54.63 | 218.52 | 56.00 | 224.00 | 10,000.00 | 40,000.00 |
| 0012 | 203-01-00100 | General Excavation | 7,262 | CUYD | 21.28 | 154,535.36 | 19.81 | 143,860.22 | 30.00 | 217,860.00 |
| 0013 | 203-03-00100 | Embankment | 2,626 | CUYD | 8.13 | 21,349.38 | 27.97 | 73,449.22 | 30.00 | 78,780.00 |
| 0014 | 203-04-00100 | Nonplastic Embankment | 3,397 | CUYD | 24.07 | 81,765.79 | 22.13 | 75,175.61 | 30.00 | 101,910.00 |
| 0015 | 203-08-00100 | Geotextile Fabric | 10,126 | SQYD | 4.08 | 41,314.08 | 1.42 | 14,378.92 | 2.00 | 20,252.00 |
| 0016 | 204-02-00100 | Temporary Hay or Straw Bales | 250 | EACH | 17.54 | 4,385.00 | 21.15 | 5,287.50 | 25.00 | 6,250.00 |
| 0017 | 204-06-00100 | Temporary Silt Fencing | 1,762 | LNFT | 1.64 | 2,889.68 | 1.98 | 3,488.76 | 10.00 | 17,620.00 |
| 0018 | 302-02-02000 | Class II Base Course (6" Thick) | 8,667.4 | SQYD | 8.26 | 71,592.72 | 8.06 | 69,859.24 | 30.00 | 260,022.00 |
| 0019 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 1,200 | CUYD | 52.04 | 62,448.00 | 41.14 | 49,368.00 | 15.00 | 18,000.00 |
| 0020 | 502-01-00100 | Superpave Asphaltic Concrete | 7,333 | TON | 127.82 | 937,304.06 | 120.21 | 881,499.93 | 125.00 | 916,625.00 |
| 0021 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 418 | TON | 127.82 | 53,428.76 | 147.54 | 61,671.72 | 165.00 | 68,970.00 |
| 0022 | 509-01-00100 | Cold Planing Asphaltic Pavement | 210 | SQYD | 21.85 | 4,588.50 | 34.73 | 7,293.30 | 30.00 | 6,300.00 |
| 0023 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -12 | CUYD | 16.39 | -196.68 | 0.47 | -5.64 | 5.00 | -60.00 |
| 0024 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 136 | SQYD | 109.25 | 14,858.00 | 120.77 | 16,424.72 | 150.00 | 20,400.00 |
| 0025 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 724 | LNFT | 45.24 | 32,753.76 | 79.56 | 57,601.44 | 90.00 | 65,160.00 |
| 0026 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 271 | LNFT | 48.14 | 13,045.94 | 68.44 | 18,547.24 | 70.00 | 18,970.00 |
| 0027 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 138 | LNFT | 58.99 | 8,140.62 | 167.19 | 23,072.22 | 88.00 | 12,144.00 |
| 0028 | 701-03-01060 | Storm Drain Pipe (30" RCP/PP) | 333 | LNFT | 79.29 | 26,403.57 | 128.01 | 42,627.33 | 108.00 | 35,964.00 |
| 0029 | 701-03-01080 | Storm Drain Pipe (36" RCP/PP) | 164 | LNFT | 94.04 | 15,422.56 | 174.28 | 28,581.92 | 150.00 | 24,600.00 |
| 0030 | 701-03-01090 | Storm Drain Pipe (42" RCP/PP) | 299 | LNFT | 114.18 | 34,139.82 | 169.00 | 50,531.00 | 210.00 | 62,790.00 |
| 0031 | 701-03-01100 | Storm Drain Pipe (48" RCP/PP) | 234 | LNFT | 138.17 | 32,331.78 | 190.76 | 44,637.84 | 235.00 | 54,990.00 |
| 0032 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 51 | LNFT | 55.15 | 2,812.65 | 149.83 | 7,641.33 | 250.00 | 12,750.00 |
| 0033 | 701-04-01140 | Storm Drain Pipe Arch (54" Equiv. RCPA) | 271 | LNFT | 158.66 | 42,996.86 | 268.94 | 72,882.74 | 288.00 | 78,048.00 |
| 0034 | 701-04-01180 | Storm Drain Pipe Arch (72" Equiv. RCPA) | 788 | LNFT | 232.48 | 183,194.24 | 414.08 | 326,295.04 | 400.00 | 315,200.00 |
| 0035 | 702-02-00100 | Manholes (MH-06) | 1 | EACH | 11,247.00 | 11,247.00 | 5,959.34 | 5,959.34 | 10,000.00 | 10,000.00 |
| 0036 | 702-02-00300 | Manholes (R-CB-11 MOD) | 1 | EACH | 10,942.25 | 10,942.25 | 6,294.88 | 6,294.88 | 10,000.00 | 10,000.00 |
| 0037 | 702-03-00100 | Catch Basins (CB-01) | 10 | EACH | 6,665.40 | 66,654.00 | 3,712.98 | 37,129.80 | 2,700.00 | 27,000.00 |
| 0038 | 702-03-00200 | Catch Basins (CB-02) | 1 | EACH | 11,856.50 | 11,856.50 | 7,506.86 | 7,506.86 | 10,000.00 | 10,000.00 |
| 0039 | 702-03-00300 | Catch Basins (CB-04) | 4 | EACH | 5,060.00 | 20,240.00 | 3,219.75 | 12,879.00 | 2,200.00 | 8,800.00 |
| 0040 | 702-03-00600 | Catch Basins (CB-07) | 11 | EACH | 12,983.50 | 142,818.50 | 4,676.28 | 51,439.08 | 4,400.00 | 48,400.00 |
| 0041 | 702-03-00700 | Catch Basins (CB-08) | 6 | EACH | 13,256.05 | 79,536.30 | 7,188.25 | 43,129.50 | 6,600.00 | 39,600.00 |
| 0042 | 702-03-00800 | Catch Basins (CB-09) | 5 | EACH | 11,442.50 | 57,212.50 | 6,879.03 | 34,395.15 | 5,300.00 | 26,500.00 |
| 0043 | 702-04-00100 | Adjusting Manholes | 1 | EACH | 632.50 | 632.50 | 560.00 | 560.00 | 2,500.00 | 2,500.00 |
| 0044 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 23 | LNFT | 16.39 | 376.97 | 95.20 | 2,189.60 | 100.00 | 2,300.00 |
| 0045 | 705-09-00100 | Rebuilt Fence | 408 | LNFT | 21.85 | 8,914.80 | 76.59 | 31,248.72 | 25.00 | 10,200.00 |
| 0046 | 706-01-00100 | Concrete Walk (4" Thick) | 1,022.6 | SQYD | 50.20 | 51,334.52 | 45.00 | 46,017.00 | 70.00 | 71,582.00 |
| 0047 | 706-02-00300 | Concrete Drive (8" Thick) | 832.2 | SQYD | 68.89 | 57,330.26 | 72.92 | 60,684.02 | 75.00 | 62,415.00 |
| 0048 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 9.9 | SQYD | 53.48 | 529.45 | 358.11 | 3,545.29 | 250.00 | 2,475.00 |
| 0049 | 706-04-00100 | Handicapped Curb Ramps | 26 | EACH | 1,371.38 | 35,655.88 | 1,512.25 | 39,318.50 | 1,500.00 | 39,000.00 |
| 0050 | 707-03-00100 | Combination Concrete Curb and Gutter (4" High Mountable) | 647.2 | LNFT | 32.24 | 20,865.73 | 28.54 | 18,471.09 | 39.00 | 25,240.80 |
| 0051 | 707-03-00100 | Combination Concrete Curb and Gutter (6" High Barrier) | 1,507.3 | LNFT | 32.24 | 48,595.35 | 33.10 | 49,891.63 | 37.00 | 55,770.10 |
| 0052 | 708-01-00100 | Right-of-Way Monument | 23 | EACH | 163.88 | 3,769.24 | 60.90 | 1,400.70 | 200.00 | 4,600.00 |
| 0053 | 710-01-00100 | Flowable Fill | 212 | CUYD | 133.11 | 28,219.32 | 156.77 | 33,235.24 | 250.00 | 53,000.00 |
| 0054 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 66,412.50 | 66,412.50 | 173,430.61 | 173,430.61 | 100,000.00 | 100,000.00 |
| 0055 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 7,500 | LNFT | 0.17 | 1,275.00 | 0.18 | 1,350.00 | 0.25 | 1,875.00 |
| 0056 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 250 | LNFT | 0.27 | 67.50 | 0.28 | 70.00 | 0.50 | 125.00 |
| 0057 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 640 | LNFT | 0.38 | 243.20 | 0.39 | 249.60 | 1.00 | 640.00 |
| 0058 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 50 | LNFT | 1.09 | 54.50 | 1.12 | 56.00 | 1.50 | 75.00 |
| 0059 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.5 | MILE | 535.33 | 803.00 | 548.80 | 823.20 | 500.00 | 750.00 |
| 0060 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.59 | MILE | 4,206.13 | 2,481.62 | 4,312.00 | 2,544.08 | 400.00 | 236.00 |
| 0061 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.66 | MILE | 12,563.75 | 8,292.08 | 12,880.00 | 8,500.80 | 12,000.00 | 7,920.00 |
| 0062 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 4 | EACH | 54.63 | 218.52 | 56.00 | 224.00 | 100.00 | 400.00 |
| 0063 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 54.63 | 218.52 | 56.00 | 224.00 | 100.00 | 400.00 |
| 0064 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 137 | EACH | 857.10 | 117,422.70 | 647.19 | 88,665.03 | 1,500.00 | 205,500.00 |
| 0065 | 716-01-00200 | Mulch (Fiber) | 0.5 | TON | 1,150.00 | 575.00 | 1,120.00 | 560.00 | 5,000.00 | 2,500.00 |
| 0066 | 717-01-00100 | Seeding | 98 | LB | 23.00 | 2,254.00 | 22.40 | 2,195.20 | 100.00 | 9,800.00 |
| 0067 | 718-01-00100 | Fertilizer | 3,887 | LB | 2.01 | 7,812.87 | 1.97 | 7,657.39 | 5.00 | 19,435.00 |
| 0068 | 719-04-00100 | Landscaping | 1 | LUMP | 15,295.00 | 15,295.00 | 17,931.20 | 17,931.20 | 10,000.00 | 10,000.00 |
| 0069 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 27,312.50 | 27,312.50 | 18,270.00 | 18,270.00 | 10,000.00 | 10,000.00 |
| 0070 | 726-01-00100 | Bedding Material | 580.3 | CUYD | 36.97 | 21,453.69 | 47.21 | 27,395.96 | 100.00 | 58,030.00 |
| 0071 | 727-01-00100 | Mobilization | 1 | LUMP | 735,000.00 | 735,000.00 | 413,000.00 | 413,000.00 | 500,000.00 | 500,000.00 |
| 0072 | 729-01-00100 | Sign (Type A) | 260 | SQFT | 84.81 | 22,050.60 | 28.00 | 7,280.00 | 25.00 | 6,500.00 |
| 0073 | 729-04-00100 | Sign (Type D) | 60 | SQFT | 32.78 | 1,966.80 | 33.60 | 2,016.00 | 50.00 | 3,000.00 |
| 0074 | 729-08-00100 | Mounting (2 1/2" Size Post) | 11 | EACH | 1,037.88 | 11,416.68 | 1,064.00 | 11,704.00 | 1,000.00 | 11,000.00 |
| 0075 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 6 | EACH | 1,638.75 | 9,832.50 | 1,680.00 | 10,080.00 | 1,600.00 | 9,600.00 |
| 0076 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 2 | EACH | 1,966.50 | 3,933.00 | 2,016.00 | 4,032.00 | 2,000.00 | 4,000.00 |
| 0077 | 729-21-00100 | U-Channel Post | 4 | EACH | 109.25 | 437.00 | 112.00 | 448.00 | 200.00 | 800.00 |
| 0078 | 730-01-00100 | Trenching and Backfilling | 1,463 | LNFT | 5.46 | 7,987.98 | 6.72 | 9,831.36 | 7.00 | 10,241.00 |
| 0079 | 730-15-12000 | Relocate Light Poles (40') (Aluminum) | 1 | EACH | 9,286.25 | 9,286.25 | 3,808.00 | 3,808.00 | 10,000.00 | 10,000.00 |
| 0080 | 731-02-00100 | Reflectorized Raised Pavement Markers | 150 | EACH | 6.56 | 984.00 | 6.72 | 1,008.00 | 15.00 | 2,250.00 |
| 0081 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 4,850 | LNFT | 0.66 | 3,201.00 | 0.67 | 3,249.50 | 0.65 | 3,152.50 |
| 0082 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 210 | LNFT | 1.31 | 275.10 | 1.34 | 281.40 | 1.30 | 273.00 |
| 0083 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 42 | LNFT | 4.37 | 183.54 | 4.48 | 188.16 | 5.00 | 210.00 |
| 0084 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 173 | LNFT | 5.46 | 944.58 | 5.60 | 968.80 | 10.00 | 1,730.00 |
| 0085 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1 | MILE | 1,037.88 | 1,037.88 | 1,064.00 | 1,064.00 | 1,000.00 | 1,000.00 |
| 0086 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 218.50 | 874.00 | 224.00 | 896.00 | 750.00 | 3,000.00 |
| 0087 | 732-05-00100 | Removal of Existing Markings | 2 | MILE | 3,277.50 | 6,555.00 | 3,360.00 | 6,720.00 | 3,000.00 | 6,000.00 |
| 0088 | 733-01-00100 | Concrete Roadway Barrier (Single Faced) | 270 | LNFT | 250.41 | 67,610.70 | 272.20 | 73,494.00 | 300.00 | 81,000.00 |
| 0089 | 736-03-00200 | Jacked or Bored Conduit (2" HPDE, Sch 80) | 205 | LNFT | 13.11 | 2,687.55 | 24.64 | 5,051.20 | 30.00 | 6,150.00 |
| 0090 | 736-03-00300 | Jacked or Bored Conduit (3" HPDE, Sch 80) | 800 | LNFT | 16.39 | 13,112.00 | 32.48 | 25,984.00 | 40.00 | 32,000.00 |
| 0091 | 736-04-04060 | Signal Support (20' Single Mast Arm) | 1 | EACH | 7,631.11 | 7,631.11 | 6,475.84 | 6,475.84 | 6,600.00 | 6,600.00 |
| 0092 | 736-04-04080 | Signal Support (25' Single Mast Arm) | 2 | EACH | 8,248.38 | 16,496.76 | 7,091.84 | 14,183.68 | 7,000.00 | 14,000.00 |
| 0093 | 736-04-04100 | Signal Support (30' Single Mast Arm) | 2 | EACH | 8,849.25 | 17,698.50 | 7,698.88 | 15,397.76 | 7,500.00 | 15,000.00 |
| 0094 | 736-04-04120 | Signal Support (35' Single Mast Arm) | 1 | EACH | 9,887.13 | 9,887.13 | 8,753.92 | 8,753.92 | 8,500.00 | 8,500.00 |
| 0095 | 736-04-04140 | Signal Support (40' Single Mast Arm) | 1 | EACH | 10,870.38 | 10,870.38 | 9,730.56 | 9,730.56 | 10,000.00 | 10,000.00 |
| 0096 | 736-04-05005 | Signal Support (35'span, 25' span add-on arm) | 1 | EACH | 13,492.38 | 13,492.38 | 9,856.00 | 9,856.00 | 10,000.00 | 10,000.00 |
| 0097 | 736-04-05008 | Signal Support (40'span, 35' span add-on arm) | 1 | EACH | 16,114.38 | 16,114.38 | 12,156.48 | 12,156.48 | 12,000.00 | 12,000.00 |
| 0098 | 736-04-05010 | Signal Support (45'span, 30' span add-on arm) | 1 | EACH | 16,387.50 | 16,387.50 | 12,544.00 | 12,544.00 | 12,000.00 | 12,000.00 |
| 0099 | 736-05-02000 | Signal Heads (3 Section, 12" Led Lens, R, Y, G) | 25 | EACH | 914.38 | 22,859.50 | 1,368.64 | 34,216.00 | 1,500.00 | 37,500.00 |
| 0100 | 736-05-02020 | Signal Heads (3 Section, 12" Led Lens, R, LT. Y, LT. G) | 2 | EACH | 924.83 | 1,849.66 | 1,402.24 | 2,804.48 | 1,500.00 | 3,000.00 |
| 0101 | 736-05-03000 | Signal Heads (4 Section, 12" Led Lens, R, Y, LT. G, G) | 1 | EACH | 1,274.90 | 1,274.90 | 1,694.56 | 1,694.56 | 1,600.00 | 1,600.00 |
| 0102 | 736-05-04000 | Signal Heads (5 Section, 12" Led Lens, R, LT. Y, Y, LT. G, G) | 2 | EACH | 1,384.63 | 2,769.26 | 1,993.60 | 3,987.20 | 2,000.00 | 4,000.00 |
| 0103 | 736-06-00200 | Signal Service (Pedestal Required) | 2 | EACH | 2,142.25 | 4,284.50 | 2,424.80 | 4,849.60 | 2,300.00 | 4,600.00 |
| 0104 | 736-08-00111 | Sig Cntrlr (TS-2, Type 2)(Type 6E Cabinet)(Furnish & Install) | 2 | EACH | 28,894.25 | 57,788.50 | 29,002.40 | 58,004.80 | 28,000.00 | 56,000.00 |
| 0105 | 736-09-00100 | Loop Detector | 545 | LNFT | 13.59 | 7,406.55 | 19.04 | 10,376.80 | 25.00 | 13,625.00 |
| 0106 | 736-10-00200 | Underground Junction Box (Type E) | 4 | EACH | 418.00 | 1,672.00 | 528.64 | 2,114.56 | 1,000.00 | 4,000.00 |
| 0107 | 736-10-00300 | Underground Junction Box (Type F) | 17 | EACH | 480.70 | 8,171.90 | 694.40 | 11,804.80 | 1,000.00 | 17,000.00 |
| 0108 | 736-10-00500 | Underground Junction Box (Type H) | 2 | EACH | 862.13 | 1,724.26 | 1,260.00 | 2,520.00 | 1,500.00 | 3,000.00 |
| 0109 | 736-11-00300 | Conduit (2" HDPE, Schedule 80) | 925 | LNFT | 1.88 | 1,739.00 | 2.24 | 2,072.00 | 3.00 | 2,775.00 |
| 0110 | 736-11-00400 | Conduit (3" HDPE, Schedule 80) | 539 | LNFT | 3.24 | 1,746.36 | 3.36 | 1,811.04 | 4.00 | 2,156.00 |
| 0111 | 736-12-01001 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 4,810 | LNFT | 1.15 | 5,531.50 | 2.24 | 10,774.40 | 3.00 | 14,430.00 |
| 0112 | 736-12-02020 | Conductor (3c, #14 awg) | 251 | LNFT | 3.24 | 813.24 | 4.48 | 1,124.48 | 5.00 | 1,255.00 |
| 0113 | 736-13-00400 | Cable (6C Signal) | 1,625 | LNFT | 1.78 | 2,892.50 | 2.24 | 3,640.00 | 3.00 | 4,875.00 |
| 0114 | 736-13-00500 | Cable (10C Signal) | 2,710 | LNFT | 2.61 | 7,073.10 | 2.80 | 7,588.00 | 3.00 | 8,130.00 |
| 0115 | 740-01-00100 | Construction Layout | 1 | LUMP | 39,187.50 | 39,187.50 | 112,784.00 | 112,784.00 | 111,000.00 | 111,000.00 |
| 0116 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 27,500.00 | 27,500.00 | 13,440.00 | 13,440.00 | 66,000.00 | 66,000.00 |
| 0117 | 741-01-02040 | Water Main (8" Ductile Iron) | 120 | LNFT | 109.44 | 13,132.80 | 62.80 | 7,536.00 | 200.00 | 24,000.00 |
| 0118 | 803-05-00100 | Temporary Sheeting | 1 | LUMP | 150,000.00 | 150,000.00 | 107,520.00 | 107,520.00 | 10,000.00 | 10,000.00 |
| 0119 | 804-01-00100 | Precast Concrete Piles (12") | 160 | LNFT | 104.50 | 16,720.00 | 56.00 | 8,960.00 | 600.00 | 96,000.00 |
| 0120 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 1,880 | LNFT | 18.81 | 35,362.80 | 28.00 | 52,640.00 | 25.00 | 47,000.00 |
| 0121 | 805-01-00700 | Class A Concrete (Bents) | 5 | CUYD | 888.25 | 4,441.25 | 5,600.00 | 28,000.00 | 4,000.00 | 20,000.00 |
| 0122 | 805-02-00100 | Class A(M) Concrete | 148.12 | CUYD | 750.48 | 111,161.10 | 779.32 | 115,432.88 | 700.00 | 103,684.00 |
| 0123 | 806-01-00100 | Deformed Reinforcing Steel | 21,570 | LB | 1.36 | 29,335.20 | 0.58 | 12,510.60 | 1.00 | 21,570.00 |
| 0124 | NS-203-00006 | Exploratory Excavation | 100 | CUYD | 11.00 | 1,100.00 | 132.92 | 13,292.00 | 150.00 | 15,000.00 |
| 0125 | NS-203-00007 | Temporary Sheeting and Bracing | 1 | LUMP | 49,500.00 | 49,500.00 | 26,880.00 | 26,880.00 | 1,000.00 | 1,000.00 |
| 0126 | NS-203-00008 | Control of Groundwater | 1 | LUMP | 31,350.00 | 31,350.00 | 15,680.00 | 15,680.00 | 0.00 | 0.00 |
| 0127 | NS-300-00060 | Geogrid | 8,668 | SQYD | 2.68 | 23,230.24 | 1.97 | 17,075.96 | 2.00 | 17,336.00 |
| 0128 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement (Full Depth) | 11,410 | INLF | 0.68 | 7,758.80 | 9.41 | 107,368.10 | 1.00 | 11,410.00 |
| 0129 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement (Full Depth) | 5,289 | INLF | 2.09 | 11,054.01 | 9.52 | 50,351.28 | 1.00 | 5,289.00 |
| 0130 | NS-700-00220 | Impact Attenuator (Kinetic) | 3 | EACH | 13,872.38 | 41,617.14 | 14,868.00 | 44,604.00 | 14,000.00 | 42,000.00 |
| 0131 | NS-736-00005 | Video Detection Cabinet Components | 2 | EACH | 8,882.50 | 17,765.00 | 9,200.80 | 18,401.60 | 8,800.00 | 17,600.00 |
| 0132 | NS-736-00006 | Video Detection Camera | 8 | EACH | 2,090.00 | 16,720.00 | 1,937.60 | 15,500.80 | 1,800.00 | 14,400.00 |
| 0133 | NS-736-00007 | Video Detection Training | 1 | LUMP | 1.05 | 1.05 | 319.20 | 319.20 | 300.00 | 300.00 |
| 0134 | NS-736-00014 | Tubular Marker | 125 | EACH | 78.38 | 9,797.50 | 50.40 | 6,300.00 | 50.00 | 6,250.00 |
| 0135 | NS-804-00006 | Vibration Monitoring | 50 | DALY | 52.25 | 2,612.50 | 560.00 | 28,000.00 | 250.00 | 12,500.00 |
| 0136 | NS-MSC-00120 | Drainage Structure MH-14x9 | 6 | EACH | 22,187.00 | 133,122.00 | 10,369.16 | 62,214.96 | 12,000.00 | 72,000.00 |
| 0137 | NS-P26-06000 | Fire Hydrants (Jefferson Parish) | 4 | EACH | 3,696.00 | 14,784.00 | 4,797.87 | 19,191.48 | 6,000.00 | 24,000.00 |
| 0138 | NS-P26-06020 | Fittings for Waterlines (DI) (Jefferson Parish) | 1,000 | LB | 6.05 | 6,050.00 | 4.23 | 4,230.00 | 15.00 | 15,000.00 |
| 0139 | NS-P26-07000 | Gate Valve and Valve Box (8") (Jefferson Parish) | 4 | EACH | 1,818.30 | 7,273.20 | 2,176.00 | 8,704.00 | 1,200.00 | 4,800.00 |
| 0140 | NS-P26-12000 | Long Body Transitional Coupling (4") (Jefferson Parish) | 1 | EACH | 492.80 | 492.80 | 165.64 | 165.64 | 275.00 | 275.00 |
| 0141 | NS-P26-12020 | Long Body Transitional Coupling (6") (Jefferson Parish) | 3 | EACH | 544.50 | 1,633.50 | 218.02 | 654.06 | 275.00 | 825.00 |
| 0142 | NS-P26-12040 | Long Body Transitional Coupling (8") (Jefferson Parish) | 2 | EACH | 797.50 | 1,595.00 | 227.36 | 454.72 | 375.00 | 750.00 |
| 0143 | NS-P26-18000 | Removal and Disposal of Existing AC Waterline (Jefferson Parish) | 1,090 | LNFT | 16.50 | 17,985.00 | 27.56 | 30,040.40 | 15.00 | 16,350.00 |
| 0144 | NS-P26-23000 | Water Service Connections (Jefferson Parish) | 15 | EACH | 770.00 | 11,550.00 | 1,749.26 | 26,238.90 | 250.00 | 3,750.00 |
| 0145 | NS-P26-23060 | Waterline (8" PVC) (Jefferson Parish) | 2,180 | LNFT | 41.84 | 91,211.20 | 47.83 | 104,269.40 | 66.00 | 143,880.00 |
| 0146 | NS-P26-23120 | Waterline (6" PVC) (Restrained) (Jefferson Parish) | 60 | LNFT | 41.46 | 2,487.60 | 146.64 | 8,798.40 | 250.00 | 15,000.00 |
| 0147 | NS-P26-23140 | Waterline (8" PVC) (Restrained) (Jefferson Parish) | 60 | LNFT | 49.73 | 2,983.80 | 139.21 | 8,352.60 | 250.00 | 15,000.00 |
| 0148 | NS-P26-30000 | Sewer Force Main Relocation (10") | 1 | LUMP | 51,320.79 | 51,320.79 | 29,073.20 | 29,073.20 | 33,000.00 | 33,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 5,218,620.98 | 5,320,116.72 | 5,661,550.80 | |||||||
| NUMBER OF DAYS BID AT $1000 PER DAY. | 150,000.00 | 268,000.00 | 365,000.00 | |||||||
| TOTAL BID | 5,368,620.98 | 5,588,116.72 | 6,026,550.80 | |||||||