Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.002430.6 | |
| Parish: Ascension | |
| Routes: LA 22 | |
| Description: LA 22: JCT LA 75 - JCT LA 44 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $2,376,734.96 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $2,129,777.32 |
| 2 | 00481 | Coastal Bridge Co., L.L.C. | $2,148,240.83 |
| 3 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $2,323,153.93 |
| 4 | 00046 | Barber Bros. Contracting Co., L.L.C | $2,389,679.63 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Coastal Bridge Co., L.L.C. |
- 3 - F.G. Sullivan, Jr. Contractor LLC |
- 4 - Barber Bros. Contracting Co., L.L.C |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-00010 | Removal of (4' CONCRETE JOINTS AT STATION 129+53 LT & RT) | 2 | EACH | 350.00 | 700.00 | 1,000.00 | 2,000.00 | 10.00 | 20.00 | 50.00 | 100.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) (30" CMP STATION 199+14) | 65 | LNFT | 16.00 | 1,040.00 | 10.00 | 650.00 | 10.00 | 650.00 | 15.00 | 975.00 |
| 0003 | 202-02-32180 | Removal of Pipe Headwalls (STATION 129+53 LT & RT) | 2 | EACH | 3,000.00 | 6,000.00 | 1,000.00 | 2,000.00 | 750.00 | 1,500.00 | 750.00 | 1,500.00 |
| 0004 | 203-01-00100 | General Excavation | 220 | CUYD | 15.00 | 3,300.00 | 12.00 | 2,640.00 | 15.00 | 3,300.00 | 16.00 | 3,520.00 |
| 0005 | 203-03-00100 | Embankment | 235 | CUYD | 21.00 | 4,935.00 | 20.00 | 4,700.00 | 15.00 | 3,525.00 | 25.00 | 5,875.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,736 | CUYD | 4.00 | 6,944.00 | 20.00 | 34,720.00 | 15.00 | 26,040.00 | 50.00 | 86,800.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 112 | EACH | 2.00 | 224.00 | 10.00 | 1,120.00 | 10.50 | 1,176.00 | 25.00 | 2,800.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 17,582 | LNFT | 0.01 | 175.82 | 1.50 | 26,373.00 | 1.30 | 22,856.60 | 1.75 | 30,768.50 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 6,175 | CUYD | 7.00 | 43,225.00 | 1.00 | 6,175.00 | 0.50 | 3,087.50 | 35.00 | 216,125.00 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 7.00 | 700.00 | 25.00 | 2,500.00 | 45.00 | 4,500.00 | 60.00 | 6,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 13,833.4 | TON | 90.00 | 1,245,006.00 | 75.00 | 1,037,505.00 | 87.00 | 1,203,505.80 | 85.00 | 1,175,839.00 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,601.3 | TON | 69.00 | 110,489.70 | 1.00 | 1,601.30 | 87.00 | 139,313.10 | 125.00 | 200,162.50 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 55,784 | SQYD | 1.00 | 55,784.00 | 4.50 | 251,028.00 | 4.00 | 223,136.00 | 2.75 | 153,406.00 |
| 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,239 | CUYD | 0.01 | -12.39 | 0.10 | -123.90 | 0.00 | 0.00 | 0.00 | 0.00 |
| 0015 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 3,029 | SQYD | 85.00 | 257,465.00 | 70.00 | 212,030.00 | 91.00 | 275,639.00 | 65.00 | 196,885.00 |
| 0016 | 701-01-01060 | Cross Drain Pipe (42" RCP/PP) (STATION 199+14) | 160 | LNFT | 130.00 | 20,800.00 | 185.00 | 29,600.00 | 200.00 | 32,000.00 | 175.00 | 28,000.00 |
| 0017 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") (STATION 129+53) | 16 | LNFT | 185.00 | 2,960.00 | 75.00 | 1,200.00 | 75.00 | 1,200.00 | 75.00 | 1,200.00 |
| 0018 | 701-15-00100 | Concrete Collar (STATION 129+53) | 2 | EACH | 700.00 | 1,400.00 | 800.00 | 1,600.00 | 900.00 | 1,800.00 | 800.00 | 1,600.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 90,000.00 | 90,000.00 | 100,000.00 | 100,000.00 | 72,000.00 | 72,000.00 | 20,000.00 | 20,000.00 |
| 0020 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 105 | LNFT | 0.05 | 5.25 | 0.25 | 26.25 | 0.15 | 15.75 | 0.30 | 31.50 |
| 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 171 | LNFT | 0.50 | 85.50 | 0.75 | 128.25 | 0.25 | 42.75 | 0.60 | 102.60 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.32 | MILE | 38.00 | 506.16 | 170.00 | 2,264.40 | 500.00 | 6,660.00 | 300.00 | 3,996.00 |
| 0023 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.844 | MILE | 38.00 | 450.07 | 225.00 | 2,664.90 | 100.00 | 1,184.40 | 300.00 | 3,553.20 |
| 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 34.221 | MILE | 38.00 | 1,300.40 | 275.00 | 9,410.78 | 100.00 | 3,422.10 | 325.00 | 11,121.83 |
| 0025 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 4.00 | 8.00 | 50.00 | 100.00 | 10.00 | 20.00 | 25.00 | 50.00 |
| 0026 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 1 | EACH | 5.00 | 5.00 | 50.00 | 50.00 | 20.00 | 20.00 | 30.00 | 30.00 |
| 0027 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 10.00 | 20.00 | 85.00 | 170.00 | 25.00 | 50.00 | 60.00 | 120.00 |
| 0028 | 726-01-00100 | Bedding Material | 96.3 | CUYD | 90.00 | 8,667.00 | 10.00 | 963.00 | 10.00 | 963.00 | 10.00 | 963.00 |
| 0029 | 727-01-00100 | Mobilization | 1 | LUMP | 190,000.00 | 190,000.00 | 200,000.00 | 200,000.00 | 100,000.00 | 100,000.00 | 75,000.00 | 75,000.00 |
| 0030 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 65.00 | 780.00 | 50.00 | 600.00 | 45.00 | 540.00 | 75.00 | 900.00 |
| 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 971 | EACH | 4.50 | 4,369.50 | 5.50 | 5,340.50 | 4.00 | 3,884.00 | 5.00 | 4,855.00 |
| 0032 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 105 | LNFT | 1.45 | 152.25 | 1.50 | 157.50 | 1.25 | 131.25 | 1.50 | 157.50 |
| 0033 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 105 | LNFT | 5.00 | 525.00 | 4.75 | 498.75 | 5.25 | 551.25 | 6.00 | 630.00 |
| 0034 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 66 | LNFT | 5.25 | 346.50 | 5.50 | 363.00 | 5.25 | 346.50 | 6.00 | 396.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.407 | MILE | 2,700.00 | 30,798.90 | 2,700.00 | 30,798.90 | 2,575.00 | 29,373.03 | 3,000.00 | 34,221.00 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.948 | MILE | 875.00 | 3,454.50 | 900.00 | 3,553.20 | 675.00 | 2,664.90 | 800.00 | 3,158.40 |
| 0037 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 215.00 | 430.00 | 250.00 | 500.00 | 175.00 | 350.00 | 200.00 | 400.00 |
| 0038 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 250.00 | 250.00 | 250.00 | 250.00 | 275.00 | 275.00 | 350.00 | 350.00 |
| 0039 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 455.00 | 910.00 | 425.00 | 850.00 | 400.00 | 800.00 | 500.00 | 1,000.00 |
| 0040 | 735-01-00100 | Mailboxes | 33 | EACH | 6.00 | 198.00 | 1.00 | 33.00 | 1.00 | 33.00 | 8.00 | 264.00 |
| 0041 | 735-02-00100 | Mailbox Supports (Single) | 18 | EACH | 115.00 | 2,070.00 | 125.00 | 2,250.00 | 115.00 | 2,070.00 | 150.00 | 2,700.00 |
| 0042 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 250.00 | 250.00 | 225.00 | 225.00 | 210.00 | 210.00 | 260.00 | 260.00 |
| 0043 | 735-04-00100 | Mailbox Supports (Multiple) | 3 | EACH | 275.00 | 825.00 | 375.00 | 1,125.00 | 350.00 | 1,050.00 | 400.00 | 1,200.00 |
| 0044 | 739-01-00100 | Hydro-Seeding | 12.1 | ACRE | 500.00 | 6,050.00 | 1,200.00 | 14,520.00 | 1,200.00 | 14,520.00 | 1,500.00 | 18,150.00 |
| 0045 | 740-01-00100 | Construction Layout | 1 | LUMP | 13,800.00 | 13,800.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 |
| 0046 | NS-200-00020 | Cleaning Existing Ditches | 400 | LNFT | 21.00 | 8,400.00 | 10.00 | 4,000.00 | 10.00 | 4,000.00 | 10.00 | 4,000.00 |
| 0047 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 20 | TON | 65.00 | 1,300.00 | 100.00 | 2,000.00 | 100.00 | 2,000.00 | 150.00 | 3,000.00 |
| 0048 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 162,816 | INLF | 0.01 | 1,628.16 | 0.75 | 122,112.00 | 0.50 | 81,408.00 | 0.35 | 56,985.60 |
| 0049 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 0.88 | MILE | 1,200.00 | 1,056.00 | 1,100.00 | 968.00 | 1,500.00 | 1,320.00 | 600.00 | 528.00 |
| CONTRACTOR TOTAL | 2,129,777.32 | 2,148,240.83 | 2,323,153.93 | 2,389,679.63 | ||||||||