Bid Tabulations
Letting of
01/25/2012
LA DOTD Headquarters
| Lead Project: H.002267.6 | |
| Parish: Jefferson | |
| Routes: LA 45 | |
| Description: LA 45 Drainage Improvements | |
| Type Const: LA 45 DRAINAGE IMPROVEMENTS | |
| Estimated Construction Cost: $351,367.40 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $358,271.30 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $380,020.98 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 80 | CUYD | 25.00 | 2,000.00 | 20.00 | 1,600.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 319.3 | CUYD | 19.00 | 6,066.70 | 75.00 | 23,947.50 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 2,370.7 | TON | 100.00 | 237,070.00 | 95.00 | 225,216.50 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 26,000.00 | 26,000.00 | 66,500.00 | 66,500.00 |
| 0005 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.914 | MILE | 350.00 | 319.90 | 10.00 | 9.14 |
| 0006 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.492 | MILE | 350.00 | 3,322.20 | 20.00 | 189.84 |
| 0007 | 717-01-00100 | Seeding | 5 | LB | 35.00 | 175.00 | 10.00 | 50.00 |
| 0008 | 718-01-00100 | Fertilizer | 40 | LB | 8.00 | 320.00 | 2.00 | 80.00 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 35,000.00 | 35,000.00 | 38,000.00 | 38,000.00 |
| 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 133 | EACH | 8.00 | 1,064.00 | 6.50 | 864.50 |
| 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.466 | MILE | 3,000.00 | 10,398.00 | 3,800.00 | 13,170.80 |
| 0012 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.357 | MILE | 1,500.00 | 535.50 | 1,100.00 | 392.70 |
| 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 |
| 0014 | NS-500-00280 | Surface Preparation | 1 | LUMP | 30,000.00 | 30,000.00 | 5,000.00 | 5,000.00 |
| CONTRACTOR TOTAL | 358,271.30 | 380,020.98 | ||||||