Bid Tabulations
Letting of
03/14/2012
LA DOTD Headquarters
| Lead Project: H.002147.6 | |
| Parish: St. Martin | |
| Routes: LA 92 | |
| Description: LA 92: LA 182 - LA 31 | |
| Type Const: COLD PLANING ASPHALTIC PAVEMENT, SUBGRADE TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALTIC SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $3,018,743.74 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 33663 | Glenn Lege Construction Inc | $2,630,668.67 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,938,927.40 |
| 3 | 00481 | Coastal Bridge Co., L.L.C. | $2,986,438.79 |
| 4 | 08815 | W. E. Mcdonald & Son, LLC. | $3,139,918.79 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Glenn Lege Construction Inc |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Coastal Bridge Co., L.L.C. |
- 4 - W. E. Mcdonald & Son, LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,040.00 | 4,040.00 | 3,600.00 | 3,600.00 | 1,600.00 | 1,600.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 98 | SQYD | 12.99 | 1,273.02 | 6.00 | 588.00 | 10.00 | 980.00 | 40.00 | 3,920.00 |
| 0003 | 203-01-00100 | General Excavation | 90 | CUYD | 7.50 | 675.00 | 48.00 | 4,320.00 | 10.00 | 900.00 | 25.00 | 2,250.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 720 | CUYD | 12.99 | 9,352.80 | 30.00 | 21,600.00 | 15.00 | 10,800.00 | 12.00 | 8,640.00 |
| 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 46 | EACH | 82.06 | 3,774.76 | 130.00 | 5,980.00 | 130.00 | 5,980.00 | 250.00 | 11,500.00 |
| 0006 | 303-01-00200 | In-Place Cement Stabilized Base Course (8 1/2" Thick) | 59,463 | SQYD | 4.09 | 243,203.67 | 6.20 | 368,670.60 | 5.75 | 341,912.25 | 6.00 | 356,778.00 |
| 0007 | 305-01-03020 | Subgrade Layer (10" Thick) (Treated) | 59,417 | SQYD | 7.99 | 474,741.83 | 10.25 | 609,024.25 | 11.00 | 653,587.00 | 9.75 | 579,315.75 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 170 | CUYD | 32.00 | 5,440.00 | 75.00 | 12,750.00 | 25.00 | 4,250.00 | 100.00 | 17,000.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 15,441.6 | TON | 71.35 | 1,101,758.16 | 85.00 | 1,312,536.00 | 75.00 | 1,158,120.00 | 90.00 | 1,389,744.00 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 635 | TON | 104.57 | 66,401.95 | 160.00 | 101,600.00 | 125.00 | 79,375.00 | 185.00 | 117,475.00 |
| 0011 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 40,039 | GAL | 3.77 | 150,947.03 | 3.40 | 136,132.60 | 3.50 | 140,136.50 | 3.50 | 140,136.50 |
| 0012 | 507-02-00200 | Aggregate (S2) | 58,882 | SQYD | 0.99 | 58,293.18 | 0.90 | 52,993.80 | 0.90 | 52,993.80 | 1.00 | 58,882.00 |
| 0013 | 507-02-00300 | Aggregate (S3) | 58,882 | SQYD | 0.76 | 44,750.32 | 0.70 | 41,217.40 | 0.65 | 38,273.30 | 0.75 | 44,161.50 |
| 0014 | 509-01-00100 | Cold Planing Asphaltic Pavement | 66,928 | SQYD | 1.15 | 76,967.20 | 1.90 | 127,163.20 | 1.50 | 100,392.00 | 2.00 | 133,856.00 |
| 0015 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,626 | CUYD | 0.01 | -46.26 | 17.00 | -78,642.00 | 0.10 | -462.60 | 0.01 | -46.26 |
| 0016 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 250 | SQYD | 88.00 | 22,000.00 | 90.00 | 22,500.00 | 75.00 | 18,750.00 | 200.00 | 50,000.00 |
| 0017 | 701-01-02001 | Cross Drain Pipe (24" RCP/PP/CMP) | 68 | LNFT | 69.44 | 4,721.92 | 155.00 | 10,540.00 | 75.00 | 5,100.00 | 120.00 | 8,160.00 |
| 0018 | 701-03-01020 | Storm Drain Pipe (18" RCP/PP) | 8 | LNFT | 83.33 | 666.64 | 65.00 | 520.00 | 65.00 | 520.00 | 100.00 | 800.00 |
| 0019 | 706-01-00100 | Concrete Walk (4" Thick) | 10 | SQYD | 56.00 | 560.00 | 67.00 | 670.00 | 65.00 | 650.00 | 100.00 | 1,000.00 |
| 0020 | 706-02-00200 | Concrete Drive (6" Thick) | 50 | SQYD | 50.50 | 2,525.00 | 75.00 | 3,750.00 | 70.00 | 3,500.00 | 100.00 | 5,000.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 17,769.13 | 17,769.13 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 |
| 0022 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 140 | LNFT | 0.24 | 33.60 | 0.26 | 36.40 | 0.25 | 35.00 | 0.25 | 35.00 |
| 0023 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 400 | LNFT | 0.82 | 328.00 | 0.52 | 208.00 | 1.00 | 400.00 | 0.50 | 200.00 |
| 0024 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.062 | MILE | 650.19 | 5,892.02 | 170.00 | 1,540.54 | 175.00 | 1,585.85 | 400.00 | 3,624.80 |
| 0025 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.419 | MILE | 436.32 | 3,237.06 | 200.00 | 1,483.80 | 410.00 | 3,041.79 | 200.00 | 1,483.80 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 22.995 | MILE | 490.86 | 11,287.33 | 350.00 | 8,048.25 | 465.00 | 10,692.68 | 350.00 | 8,048.25 |
| 0027 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 49.09 | 98.18 | 25.00 | 50.00 | 50.00 | 100.00 | 25.00 | 50.00 |
| 0028 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 2 | EACH | 49.09 | 98.18 | 25.00 | 50.00 | 50.00 | 100.00 | 25.00 | 50.00 |
| 0029 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 953 | EACH | 1.20 | 1,143.60 | 1.15 | 1,095.95 | 1.20 | 1,143.60 | 2.00 | 1,906.00 |
| 0030 | 717-01-00100 | Seeding | 2.43 | LB | 109.08 | 265.06 | 11.00 | 26.73 | 11.00 | 26.73 | 100.00 | 243.00 |
| 0031 | 718-01-00100 | Fertilizer | 4.94 | LB | 109.08 | 538.86 | 1.25 | 6.18 | 1.00 | 4.94 | 100.00 | 494.00 |
| 0032 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 5,176.25 | 5,176.25 | 4,000.00 | 4,000.00 | 5,000.00 | 5,000.00 | 3,000.00 | 3,000.00 |
| 0033 | 726-01-00100 | Bedding Material | 10 | CUYD | 75.00 | 750.00 | 87.00 | 870.00 | 90.00 | 900.00 | 100.00 | 1,000.00 |
| 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 247,847.69 | 247,847.69 | 91,000.00 | 91,000.00 | 265,000.00 | 265,000.00 | 88,500.00 | 88,500.00 |
| 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 163.62 | 327.24 | 80.00 | 160.00 | 95.00 | 190.00 | 125.00 | 250.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 600 | EACH | 5.73 | 3,438.00 | 6.00 | 3,600.00 | 5.50 | 3,300.00 | 5.75 | 3,450.00 |
| 0037 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 70 | LNFT | 1.47 | 102.90 | 4.25 | 297.50 | 1.50 | 105.00 | 4.00 | 280.00 |
| 0038 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 188 | LNFT | 4.91 | 923.08 | 4.25 | 799.00 | 4.75 | 893.00 | 4.00 | 752.00 |
| 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 5.45 | 65.40 | 4.25 | 51.00 | 5.25 | 63.00 | 4.00 | 48.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.498 | MILE | 2,836.08 | 32,609.25 | 2,700.00 | 31,044.60 | 2,700.00 | 31,044.60 | 2,600.00 | 29,894.80 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.709 | MILE | 927.18 | 3,438.91 | 900.00 | 3,338.10 | 900.00 | 3,338.10 | 850.00 | 3,152.65 |
| 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 234.52 | 234.52 | 325.00 | 325.00 | 225.00 | 225.00 | 300.00 | 300.00 |
| 0043 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 1 | EACH | 245.43 | 245.43 | 425.00 | 425.00 | 250.00 | 250.00 | 400.00 | 400.00 |
| 0044 | 732-05-00100 | Removal of Existing Markings | 0.023 | MILE | 5,454.00 | 125.44 | 25,000.00 | 575.00 | 5,000.00 | 115.00 | 25,000.00 | 575.00 |
| 0045 | 735-01-00100 | Mailboxes | 36 | EACH | 16.36 | 588.96 | 1.00 | 36.00 | 6.00 | 216.00 | 1.00 | 36.00 |
| 0046 | 735-02-00100 | Mailbox Supports (Single) | 27 | EACH | 103.63 | 2,798.01 | 104.00 | 2,808.00 | 130.00 | 3,510.00 | 104.00 | 2,808.00 |
| 0047 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 136.35 | 681.75 | 125.00 | 625.00 | 200.00 | 1,000.00 | 125.00 | 625.00 |
| 0048 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 201.80 | 403.60 | 180.00 | 360.00 | 315.00 | 630.00 | 180.00 | 360.00 |
| 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 13,508.75 | 13,508.75 | 9,000.00 | 9,000.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0050 | NS-200-00020 | Cleaning Existing Ditches | 215 | LNFT | 9.00 | 1,935.00 | 10.00 | 2,150.00 | 16.00 | 3,440.00 | 15.00 | 3,225.00 |
| 0051 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,185 | INLF | 1.25 | 2,731.25 | 1.10 | 2,403.50 | 1.25 | 2,731.25 | 3.00 | 6,555.00 |
| CONTRACTOR TOTAL | 2,630,668.67 | 2,938,927.40 | 2,986,438.79 | 3,139,918.79 | ||||||||