Bid Tabulations
Letting of
02/13/2013
LA DOTD Headquarters
| Lead Project: H.002129.6-R1 | |
| Parish: Jefferson Davis | |
| Routes: LA 101 | |
| Description: LA 101: US 90 - US 165 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $2,691,617.75 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00183 | R. E. Heidt Construction Co., LLC | $2,640,875.23 |
| 2 | 34356 | Prairie Contractors Inc. | $2,705,432.03 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $2,852,922.05 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - R. E. Heidt Construction Co., LLC |
- 2 - Prairie Contractors Inc. |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 117 | SQYD | 12.12 | 1,418.04 | 10.00 | 1,170.00 | 7.00 | 819.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 622 | LNFT | 10.10 | 6,282.20 | 12.00 | 7,464.00 | 8.00 | 4,976.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP | 32 | LNFT | 10.10 | 323.20 | 10.00 | 320.00 | 20.00 | 640.00 |
| 0004 | 202-02-32120 | Removal of Pipe (Side Drain) 18" RCP | 8 | LNFT | 5.05 | 40.40 | 10.00 | 80.00 | 20.00 | 160.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 388.1 | SQYD | 12.12 | 4,703.77 | 1.00 | 388.10 | 7.00 | 2,716.70 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 500 | CUYD | 16.50 | 8,250.00 | 13.00 | 6,500.00 | 19.00 | 9,500.00 |
| 0007 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 350 | CUYD | 18.50 | 6,475.00 | 13.00 | 4,550.00 | 18.00 | 6,300.00 |
| 0008 | 303-02-00100 | Removal of Existing Patches | 655 | SQYD | 8.08 | 5,292.40 | 8.00 | 5,240.00 | 4.75 | 3,111.25 |
| 0009 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 75,996 | SQYD | 7.50 | 569,970.00 | 7.05 | 535,771.80 | 6.20 | 471,175.20 |
| 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,695 | CUYD | 20.00 | 33,900.00 | 15.00 | 25,425.00 | 38.00 | 64,410.00 |
| 0011 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 15.00 | 3,000.00 | 95.00 | 19,000.00 | 19.00 | 3,800.00 |
| 0012 | 502-01-00100 | Superpave Asphaltic Concrete | 18,736.1 | TON | 80.00 | 1,498,888.00 | 79.50 | 1,489,519.95 | 82.50 | 1,545,728.25 |
| 0013 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,533.6 | TON | 79.00 | 121,154.40 | 40.00 | 61,344.00 | 135.00 | 207,036.00 |
| 0014 | 509-01-00100 | Cold Planing Asphaltic Pavement | 57,846 | SQYD | 1.05 | 60,738.30 | 2.10 | 121,476.60 | 0.80 | 46,276.80 |
| 0015 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,577 | CUYD | 1.60 | -7,323.20 | 0.01 | -45.77 | 1.00 | -4,577.00 |
| 0016 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 340 | SQYD | 93.00 | 31,620.00 | 94.00 | 31,960.00 | 78.00 | 26,520.00 |
| 0017 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 40 | SQYD | 195.00 | 7,800.00 | 141.00 | 5,640.00 | 90.00 | 3,600.00 |
| 0018 | 510-02-00100 | Pavement Widening | 183.7 | SQYD | 80.00 | 14,696.00 | 100.00 | 18,370.00 | 145.00 | 26,636.50 |
| 0019 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 3,458 | LNFT | 2.02 | 6,985.16 | 2.45 | 8,472.10 | 2.60 | 8,990.80 |
| 0020 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 4,047 | LNFT | 2.02 | 8,174.94 | 2.75 | 11,129.25 | 2.40 | 9,712.80 |
| 0021 | 602-03-00100 | Cleaning and Sealing Random cracks | 200 | LNFT | 2.28 | 456.00 | 4.00 | 800.00 | 4.60 | 920.00 |
| 0022 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 32 | LNFT | 64.64 | 2,068.48 | 90.00 | 2,880.00 | 125.00 | 4,000.00 |
| 0023 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) 18" RCP Only | 8 | LNFT | 50.50 | 404.00 | 70.00 | 560.00 | 120.00 | 960.00 |
| 0024 | 701-08-00100 | Relaying Pipe | 18 | LNFT | 55.55 | 999.90 | 110.00 | 1,980.00 | 130.00 | 2,340.00 |
| 0025 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 50.50 | 404.00 | 75.00 | 600.00 | 130.00 | 1,040.00 |
| 0026 | 701-15-00100 | Concrete Collar | 9 | EACH | 101.00 | 909.00 | 560.00 | 5,040.00 | 790.00 | 7,110.00 |
| 0027 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 444 | LNFT | 41.41 | 18,386.04 | 42.00 | 18,648.00 | 32.00 | 14,208.00 |
| 0028 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 19.19 | 4,797.50 | 20.00 | 5,000.00 | 18.00 | 4,500.00 |
| 0029 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 60.60 | 6,060.00 | 65.00 | 6,500.00 | 65.00 | 6,500.00 |
| 0030 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,020.00 | 8,080.00 | 2,100.00 | 8,400.00 | 2,400.00 | 9,600.00 |
| 0031 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 52.5 | SQYD | 48.48 | 2,545.20 | 60.00 | 3,150.00 | 90.00 | 4,725.00 |
| 0032 | 707-03-00100 | Combination Concrete Curb and Gutter | 138.1 | LNFT | 35.35 | 4,881.84 | 20.00 | 2,762.00 | 35.00 | 4,833.50 |
| 0033 | 712-02-00100 | Sacked Concrete Revetment | 120 | SQYD | 80.80 | 9,696.00 | 80.00 | 9,600.00 | 90.00 | 10,800.00 |
| 0034 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 4,435.00 | 4,435.00 | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 |
| 0035 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 245 | LNFT | 0.16 | 39.20 | 0.01 | 2.45 | 1.00 | 245.00 |
| 0036 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 443 | LNFT | 0.51 | 225.93 | 0.01 | 4.43 | 1.00 | 443.00 |
| 0037 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 14.209 | MILE | 285.00 | 4,049.57 | 400.00 | 5,683.60 | 350.00 | 4,973.15 |
| 0038 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 10.026 | MILE | 176.75 | 1,772.10 | 0.01 | 0.10 | 100.00 | 1,002.60 |
| 0039 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 23.741 | MILE | 297.95 | 7,073.63 | 0.01 | 0.24 | 100.00 | 2,374.10 |
| 0040 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 10.10 | 20.20 | 0.01 | 0.02 | 12.00 | 24.00 |
| 0041 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 6 | EACH | 20.20 | 121.20 | 0.01 | 0.06 | 22.00 | 132.00 |
| 0042 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 5,000.00 | 5,000.00 |
| 0043 | 726-01-00100 | Bedding Material | 12 | CUYD | 75.75 | 909.00 | 85.00 | 1,020.00 | 110.00 | 1,320.00 |
| 0044 | 727-01-00100 | Mobilization | 1 | LUMP | 55,000.00 | 55,000.00 | 132,000.00 | 132,000.00 | 200,000.00 | 200,000.00 |
| 0045 | 729-16-00200 | Object Marker Assembly (Type 2) | 20 | EACH | 70.70 | 1,414.00 | 70.00 | 1,400.00 | 45.00 | 900.00 |
| 0046 | 729-16-00300 | Object Marker Assembly (Type 3) | 14 | EACH | 80.80 | 1,131.20 | 90.00 | 1,260.00 | 70.00 | 980.00 |
| 0047 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 3,325 | EACH | 6.06 | 20,149.50 | 6.10 | 20,282.50 | 6.50 | 21,612.50 |
| 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,856 | EACH | 4.04 | 7,498.24 | 4.35 | 8,073.60 | 4.50 | 8,352.00 |
| 0049 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 410 | LNFT | 1.01 | 414.10 | 1.25 | 512.50 | 1.10 | 451.00 |
| 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 443 | LNFT | 4.55 | 2,015.65 | 5.00 | 2,215.00 | 5.00 | 2,215.00 |
| 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.681 | MILE | 2,300.00 | 31,466.30 | 2,350.00 | 32,150.35 | 2,400.00 | 32,834.40 |
| 0052 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.05 | MILE | 5,000.00 | 250.00 | 7,500.00 | 375.00 | 5,400.00 | 270.00 |
| 0053 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.77 | MILE | 606.00 | 3,496.62 | 700.00 | 4,039.00 | 660.00 | 3,808.20 |
| 0054 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 176.75 | 353.50 | 200.00 | 400.00 | 190.00 | 380.00 |
| 0055 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 4 | EACH | 378.75 | 1,515.00 | 400.00 | 1,600.00 | 415.00 | 1,660.00 |
| 0056 | 732-04-25020 | Plastic Pavement Legends and Symbols (Yield Line) | 2 | EACH | 454.50 | 909.00 | 500.00 | 1,000.00 | 490.00 | 980.00 |
| 0057 | 732-05-00100 | Removal of Existing Markings | 0.463 | MILE | 2,525.00 | 1,169.08 | 2,600.00 | 1,203.80 | 2,600.00 | 1,203.80 |
| 0058 | 735-01-00100 | Mailboxes | 36 | EACH | 1.01 | 36.36 | 5.00 | 180.00 | 20.00 | 720.00 |
| 0059 | 735-02-00100 | Mailbox Supports (Single) | 23 | EACH | 108.07 | 2,485.61 | 115.00 | 2,645.00 | 110.00 | 2,530.00 |
| 0060 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 136.35 | 681.75 | 150.00 | 750.00 | 140.00 | 700.00 |
| 0061 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 257.55 | 257.55 | 275.00 | 275.00 | 280.00 | 280.00 |
| 0062 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,600.00 | 12,600.00 | 100.00 | 100.00 | 8,000.00 | 8,000.00 |
| 0063 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 2,448 | INLF | 1.01 | 2,472.48 | 1.50 | 3,672.00 | 1.00 | 2,448.00 |
| 0064 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 906 | INLF | 1.25 | 1,132.50 | 1.00 | 906.00 | 2.00 | 1,812.00 |
| 0065 | NS-602-00001 | Milling Concrete Pavement | 196.5 | SQYD | 27.30 | 5,364.45 | 35.00 | 6,877.50 | 11.00 | 2,161.50 |
| 0066 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 5.77 | MILE | 1,348.35 | 7,779.98 | 1,335.00 | 7,702.95 | 1,100.00 | 6,347.00 |
| 0067 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 11.54 | MILE | 1,348.35 | 15,559.96 | 1,335.00 | 15,405.90 | 1,100.00 | 12,694.00 |
| CONTRACTOR TOTAL | 2,640,875.23 | 2,705,432.03 | 2,852,922.05 | |||||||