Bid Tabulations
Letting of
09/12/2012
LA DOTD Headquarters
| Lead Project: H.002104.6 | |
| Parish: St. Landry | |
| Routes: LA 104 | |
| Description: Bayou Plaquemine Bridge | |
| Type Const: GRADING, SUPERPAVE ASPHALTIC CONCRET PAVEMENT, PORTLAND CEMENT CONCRETE SLAB SPAN BRIDGE AND RELATED WORK. | |
| Estimated Construction Cost: $952,222.45 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 56288 | Guinn Services, LLC | $832,409.45 |
| 2 | 08815 | W. E. Mcdonald & Son, LLC. | $846,451.55 |
| 3 | 39462 | Jb James Construction Llc | $870,282.40 |
| 4 | 01012 | Cecil D. Gassiott, LLC | $934,238.95 |
| 5 | 12312 | Gilchrist Construction Co. LLC | $943,426.43 |
| 6 | 00044 | Guinn Construction, LLC | $1,112,273.09 |
| 7 | 40312 | Gray Construction Corp. | $1,146,449.58 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Guinn Services, LLC |
- 2 - W. E. Mcdonald & Son, LLC. |
- 3 - Jb James Construction Llc |
- 4 - Cecil D. Gassiott, LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 6,500.00 | 6,500.00 | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,000.00 | 4,000.00 | 8,000.00 | 8,000.00 | 7,500.00 | 7,500.00 | 25,000.00 | 25,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge (Sta. 110+06.73: 27' X 59" Timber Bridge) | 1 | EACH | 5,500.00 | 5,500.00 | 10,000.00 | 10,000.00 | 6,000.00 | 6,000.00 | 12,700.00 | 12,700.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 50 | LNFT | 5.50 | 275.00 | 1.00 | 50.00 | 7.00 | 350.00 | 6.00 | 300.00 |
| 0005 | 203-01-00100 | General Excavation | 5,166 | CUYD | 6.50 | 33,579.00 | 7.00 | 36,162.00 | 7.00 | 36,162.00 | 5.00 | 25,830.00 |
| 0006 | 203-02-00100 | Drainage Excavation | 244.63 | CUYD | 5.00 | 1,223.15 | 10.00 | 2,446.30 | 10.00 | 2,446.30 | 15.00 | 3,669.45 |
| 0007 | 203-03-00100 | Embankment | 1,386 | CUYD | 14.50 | 20,097.00 | 10.00 | 13,860.00 | 15.50 | 21,483.00 | 17.00 | 23,562.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 100.00 | 1,600.00 | 250.00 | 4,000.00 | 100.00 | 1,600.00 | 100.00 | 1,600.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 1,990 | LNFT | 2.00 | 3,980.00 | 2.00 | 3,980.00 | 2.00 | 3,980.00 | 2.00 | 3,980.00 |
| 0010 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,098.1 | SQYD | 20.00 | 81,962.00 | 26.00 | 106,550.60 | 22.00 | 90,158.20 | 25.00 | 102,452.50 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 16.43 | TON | 300.00 | 4,929.00 | 1,000.00 | 16,430.00 | 200.00 | 3,286.00 | 150.00 | 2,464.50 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 36 | CUYD | 45.00 | 1,620.00 | 100.00 | 3,600.00 | 100.00 | 3,600.00 | 100.00 | 3,600.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 45.00 | 4,500.00 | 1.00 | 100.00 | 75.00 | 7,500.00 | 85.00 | 8,500.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 584.9 | TON | 175.00 | 102,357.50 | 175.00 | 102,357.50 | 125.00 | 73,112.50 | 175.00 | 102,357.50 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 348.3 | TON | 180.00 | 62,694.00 | 175.00 | 60,952.50 | 145.00 | 50,503.50 | 175.00 | 60,952.50 |
| 0016 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 48 | LNFT | 55.00 | 2,640.00 | 60.00 | 2,880.00 | 41.00 | 1,968.00 | 80.00 | 3,840.00 |
| 0017 | 701-05-01100 | Side Drain Pipe (36" RCP/PP/CMP) | 184 | LNFT | 95.00 | 17,480.00 | 115.00 | 21,160.00 | 61.00 | 11,224.00 | 110.00 | 20,240.00 |
| 0018 | 702-06-01020 | Side Drain End Treatment (1 Barrel, 24" RCP/PP or 30" CMP) | 2 | EACH | 2,000.00 | 4,000.00 | 2,500.00 | 5,000.00 | 1,800.00 | 3,600.00 | 2,200.00 | 4,400.00 |
| 0019 | 702-06-01060 | Side Drain End Treatment (1 Barrel, 36" RCP/PP or 42" CMP) | 6 | EACH | 3,750.00 | 22,500.00 | 5,000.00 | 30,000.00 | 3,000.00 | 18,000.00 | 2,500.00 | 15,000.00 |
| 0020 | 704-03-00100 | Blocked Out Guard Rail | 525 | LNFT | 22.00 | 11,550.00 | 20.00 | 10,500.00 | 20.00 | 10,500.00 | 20.00 | 10,500.00 |
| 0021 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 68.00 | 6,800.00 | 65.00 | 6,500.00 | 65.00 | 6,500.00 | 68.00 | 6,800.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 2,100.00 | 8,400.00 | 2,100.00 | 8,400.00 | 2,200.00 | 8,800.00 |
| 0023 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 250.00 | 2,000.00 | 250.00 | 2,000.00 | 125.00 | 1,000.00 | 200.00 | 1,600.00 |
| 0024 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 250.00 | 2,000.00 | 250.00 | 2,000.00 | 125.00 | 1,000.00 | 100.00 | 800.00 |
| 0025 | 712-04-00100 | Flexible Revetment | 310 | SQYD | 55.00 | 17,050.00 | 60.00 | 18,600.00 | 50.00 | 15,500.00 | 76.00 | 23,560.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 14,000.00 | 14,000.00 | 22,000.00 | 22,000.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 |
| 0027 | 716-01-00100 | Mulch (Vegetative) | 3 | TON | 1,000.00 | 3,000.00 | 650.00 | 1,950.00 | 950.00 | 2,850.00 | 750.00 | 2,250.00 |
| 0028 | 717-01-00100 | Seeding | 80 | LB | 10.00 | 800.00 | 10.00 | 800.00 | 10.00 | 800.00 | 10.00 | 800.00 |
| 0029 | 718-01-00100 | Fertilizer | 2,000 | LB | 1.00 | 2,000.00 | 0.50 | 1,000.00 | 0.60 | 1,200.00 | 0.60 | 1,200.00 |
| 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 5,234 | SQYD | 1.75 | 9,159.50 | 1.50 | 7,851.00 | 1.15 | 6,019.10 | 1.30 | 6,804.20 |
| 0031 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 8,500.00 | 8,500.00 | 3,000.00 | 3,000.00 | 7,500.00 | 7,500.00 | 20,000.00 | 20,000.00 |
| 0032 | 726-01-00100 | Bedding Material | 57.3 | CUYD | 100.00 | 5,730.00 | 100.00 | 5,730.00 | 80.00 | 4,584.00 | 100.00 | 5,730.00 |
| 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 42,500.00 | 42,500.00 | 35,000.00 | 35,000.00 | 90,000.00 | 90,000.00 | 80,000.00 | 80,000.00 |
| 0034 | 731-02-00100 | Reflectorized Raised Pavement Markers | 22 | EACH | 45.00 | 990.00 | 25.00 | 550.00 | 25.00 | 550.00 | 12.00 | 264.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.491 | MILE | 5,500.00 | 2,700.50 | 5,000.00 | 2,455.00 | 5,000.00 | 2,455.00 | 7,500.00 | 3,682.50 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.145 | MILE | 4,000.00 | 580.00 | 5,000.00 | 725.00 | 2,000.00 | 290.00 | 4,000.00 | 580.00 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,500.00 | 8,500.00 | 8,500.00 | 8,500.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0038 | 804-01-00300 | Precast Concrete Piles (16") | 1,240 | LNFT | 62.00 | 76,880.00 | 67.00 | 83,080.00 | 70.00 | 86,800.00 | 65.00 | 80,600.00 |
| 0039 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1.00 | 1.00 | 1.00 | 1.00 | 100.00 | 100.00 | 1,500.00 | 1,500.00 |
| 0040 | 805-01-00700 | Class A Concrete (Bents) | 28.89 | CUYD | 1,000.00 | 28,890.00 | 800.00 | 23,112.00 | 1,000.00 | 28,890.00 | 1,500.00 | 43,335.00 |
| 0041 | 805-03-00100 | Class AA Concrete | 108.76 | CUYD | 810.00 | 88,095.60 | 600.00 | 65,256.00 | 600.00 | 65,256.00 | 750.00 | 81,570.00 |
| 0042 | 806-01-00100 | Deformed Reinforcing Steel | 26,712 | LB | 1.00 | 26,712.00 | 1.00 | 26,712.00 | 0.90 | 24,040.80 | 0.90 | 24,040.80 |
| 0043 | 810-01-00100 | Concrete Railing (Standard Barrier) | 80 | LNFT | 85.00 | 6,800.00 | 60.00 | 4,800.00 | 62.00 | 4,960.00 | 63.00 | 5,040.00 |
| 0044 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 80 | LNFT | 85.00 | 6,800.00 | 60.00 | 4,800.00 | 64.00 | 5,120.00 | 65.00 | 5,200.00 |
| 0045 | 813-01-00100 | Concrete Approach Slabs | 266.67 | SQYD | 260.00 | 69,334.20 | 195.00 | 52,000.65 | 200.00 | 53,334.00 | 200.00 | 53,334.00 |
| 0046 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 160 | INLF | 5.00 | 800.00 | 10.00 | 1,600.00 | 1.00 | 160.00 | 5.00 | 800.00 |
| CONTRACTOR TOTAL | 832,409.45 | 846,451.55 | 870,282.40 | 934,238.95 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Gilchrist Construction Co. LLC |
- 6 - Guinn Construction, LLC |
- 7 - Gray Construction Corp. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 20,000.00 | 20,000.00 | 6,000.00 | 6,000.00 | 30,000.00 | 30,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,500.00 | 4,500.00 | 5,000.00 | 5,000.00 | 47,000.00 | 47,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge (Sta. 110+06.73: 27' X 59" Timber Bridge) | 1 | EACH | 40,000.00 | 40,000.00 | 6,500.00 | 6,500.00 | 19,900.00 | 19,900.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 50 | LNFT | 20.00 | 1,000.00 | 20.00 | 1,000.00 | 30.00 | 1,500.00 |
| 0005 | 203-01-00100 | General Excavation | 5,166 | CUYD | 7.00 | 36,162.00 | 10.00 | 51,660.00 | 7.00 | 36,162.00 |
| 0006 | 203-02-00100 | Drainage Excavation | 244.63 | CUYD | 13.00 | 3,180.19 | 13.00 | 3,180.19 | 34.00 | 8,317.42 |
| 0007 | 203-03-00100 | Embankment | 1,386 | CUYD | 24.00 | 33,264.00 | 20.00 | 27,720.00 | 31.00 | 42,966.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 150.00 | 2,400.00 | 100.00 | 1,600.00 | 122.00 | 1,952.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 1,990 | LNFT | 2.00 | 3,980.00 | 2.00 | 3,980.00 | 3.15 | 6,268.50 |
| 0010 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,098.1 | SQYD | 24.00 | 98,354.40 | 22.00 | 90,158.20 | 30.40 | 124,582.24 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 16.43 | TON | 400.00 | 6,572.00 | 750.00 | 12,322.50 | 850.00 | 13,965.50 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 36 | CUYD | 150.00 | 5,400.00 | 100.00 | 3,600.00 | 90.00 | 3,240.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 50.00 | 5,000.00 | 50.00 | 5,000.00 | 83.00 | 8,300.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 584.9 | TON | 105.00 | 61,414.50 | 200.00 | 116,980.00 | 162.00 | 94,753.80 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 348.3 | TON | 120.00 | 41,796.00 | 220.00 | 76,626.00 | 163.00 | 56,772.90 |
| 0016 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 48 | LNFT | 70.00 | 3,360.00 | 100.00 | 4,800.00 | 86.00 | 4,128.00 |
| 0017 | 701-05-01100 | Side Drain Pipe (36" RCP/PP/CMP) | 184 | LNFT | 90.00 | 16,560.00 | 135.00 | 24,840.00 | 115.00 | 21,160.00 |
| 0018 | 702-06-01020 | Side Drain End Treatment (1 Barrel, 24" RCP/PP or 30" CMP) | 2 | EACH | 2,000.00 | 4,000.00 | 2,500.00 | 5,000.00 | 2,600.00 | 5,200.00 |
| 0019 | 702-06-01060 | Side Drain End Treatment (1 Barrel, 36" RCP/PP or 42" CMP) | 6 | EACH | 3,500.00 | 21,000.00 | 4,600.00 | 27,600.00 | 4,850.00 | 29,100.00 |
| 0020 | 704-03-00100 | Blocked Out Guard Rail | 525 | LNFT | 22.00 | 11,550.00 | 28.00 | 14,700.00 | 23.00 | 12,075.00 |
| 0021 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 75.00 | 7,500.00 | 75.00 | 7,500.00 | 65.00 | 6,500.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,500.00 | 10,000.00 | 2,100.00 | 8,400.00 |
| 0023 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 200.00 | 1,600.00 | 300.00 | 2,400.00 | 460.00 | 3,680.00 |
| 0024 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 200.00 | 1,600.00 | 300.00 | 2,400.00 | 165.00 | 1,320.00 |
| 0025 | 712-04-00100 | Flexible Revetment | 310 | SQYD | 60.00 | 18,600.00 | 85.00 | 26,350.00 | 77.00 | 23,870.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,000.00 | 35,000.00 | 15,000.00 | 15,000.00 | 7,300.00 | 7,300.00 |
| 0027 | 716-01-00100 | Mulch (Vegetative) | 3 | TON | 1,200.00 | 3,600.00 | 1,000.00 | 3,000.00 | 1,000.00 | 3,000.00 |
| 0028 | 717-01-00100 | Seeding | 80 | LB | 12.00 | 960.00 | 20.00 | 1,600.00 | 8.00 | 640.00 |
| 0029 | 718-01-00100 | Fertilizer | 2,000 | LB | 0.70 | 1,400.00 | 1.00 | 2,000.00 | 1.25 | 2,500.00 |
| 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 5,234 | SQYD | 1.35 | 7,065.90 | 2.00 | 10,468.00 | 1.25 | 6,542.50 |
| 0031 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 2,000.00 | 2,000.00 | 12,500.00 | 12,500.00 | 16,300.00 | 16,300.00 |
| 0032 | 726-01-00100 | Bedding Material | 57.3 | CUYD | 138.00 | 7,907.40 | 100.00 | 5,730.00 | 151.00 | 8,652.30 |
| 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 90,000.00 | 90,000.00 | 175,000.00 | 175,000.00 | 65,400.00 | 65,400.00 |
| 0034 | 731-02-00100 | Reflectorized Raised Pavement Markers | 22 | EACH | 6.17 | 135.74 | 35.00 | 770.00 | 25.00 | 550.00 |
| 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.491 | MILE | 3,500.00 | 1,718.50 | 7,500.00 | 3,682.50 | 5,000.00 | 2,455.00 |
| 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.145 | MILE | 1,000.00 | 145.00 | 4,000.00 | 580.00 | 2,000.00 | 290.00 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 4,900.00 | 4,900.00 |
| 0038 | 804-01-00300 | Precast Concrete Piles (16") | 1,240 | LNFT | 55.00 | 68,200.00 | 75.00 | 93,000.00 | 94.00 | 116,560.00 |
| 0039 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 2,000.00 | 2,000.00 | 1.00 | 1.00 | 200.00 | 200.00 |
| 0040 | 805-01-00700 | Class A Concrete (Bents) | 28.89 | CUYD | 1,500.00 | 43,335.00 | 1,000.00 | 28,890.00 | 1,750.00 | 50,557.50 |
| 0041 | 805-03-00100 | Class AA Concrete | 108.76 | CUYD | 900.00 | 97,884.00 | 900.00 | 97,884.00 | 1,285.00 | 139,756.60 |
| 0042 | 806-01-00100 | Deformed Reinforcing Steel | 26,712 | LB | 1.20 | 32,054.40 | 1.10 | 29,383.20 | 0.90 | 24,040.80 |
| 0043 | 810-01-00100 | Concrete Railing (Standard Barrier) | 80 | LNFT | 61.00 | 4,880.00 | 100.00 | 8,000.00 | 107.00 | 8,560.00 |
| 0044 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 80 | LNFT | 70.00 | 5,600.00 | 100.00 | 8,000.00 | 107.00 | 8,560.00 |
| 0045 | 813-01-00100 | Concrete Approach Slabs | 266.67 | SQYD | 220.00 | 58,667.40 | 250.00 | 66,667.50 | 256.00 | 68,267.52 |
| 0046 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 160 | INLF | 13.00 | 2,080.00 | 20.00 | 3,200.00 | 1.90 | 304.00 |
| CONTRACTOR TOTAL | 943,426.43 | 1,112,273.09 | 1,146,449.58 | |||||||