Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.002017.6 | |
| Parish: Beauregard | |
| Routes: LA 110 | |
| Description: LA 110: WUNCH RD - US 171 | |
| Type Const: PAVEMENT PATCHING, COLD PLANE ASPHALTIC CONCRETE, ASPHALT SURFACE TREATMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $6,524,602.60 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34356 | Prairie Contractors Inc. | $6,780,517.85 |
| 2 | 14096 | Bessette Development Corp. | $7,341,054.00 |
| 3 | 00183 | R. E. Heidt Construction Co., LLC | $7,975,871.34 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Prairie Contractors Inc. |
- 2 - Bessette Development Corp. |
- 3 - R. E. Heidt Construction Co., LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 2,446 | LNFT | 10.00 | 24,460.00 | 5.00 | 12,230.00 | 2.25 | 5,503.50 |
| 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 50,000.00 | 50,000.00 | 54,750.00 | 54,750.00 | 6,710.00 | 6,710.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9,777 | CUYD | 57.00 | 557,289.00 | 68.50 | 669,724.50 | 70.00 | 684,390.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 58,264.7 | TON | 80.75 | 4,704,874.53 | 90.00 | 5,243,823.00 | 99.00 | 5,768,205.30 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,806.7 | TON | 50.00 | 90,335.00 | 97.00 | 175,249.90 | 157.00 | 283,651.90 |
| 0006 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 79,370 | GAL | 2.75 | 218,267.50 | 3.43 | 272,239.10 | 3.47 | 275,413.90 |
| 0007 | 507-02-00200 | Aggregate (S2) | 193,590 | SQYD | 1.10 | 212,949.00 | 0.73 | 141,320.70 | 0.73 | 141,320.70 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 28,847 | SQYD | 4.50 | 129,811.50 | 1.90 | 54,809.30 | 1.17 | 33,750.99 |
| 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -995 | CUYD | 0.01 | -9.95 | 2.00 | -1,990.00 | 1.00 | -995.00 |
| 0010 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 350 | SQYD | 175.00 | 61,250.00 | 69.00 | 24,150.00 | 110.00 | 38,500.00 |
| 0011 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 1,950 | LNFT | 30.00 | 58,500.00 | 29.15 | 56,842.50 | 30.30 | 59,085.00 |
| 0012 | 704-03-00100 | Blocked Out Guard Rail | 1,187.5 | LNFT | 20.00 | 23,750.00 | 17.50 | 20,781.25 | 17.68 | 20,995.00 |
| 0013 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 800 | LNFT | 57.00 | 45,600.00 | 55.00 | 44,000.00 | 55.55 | 44,440.00 |
| 0014 | 704-11-00100 | Guard Rail End Treatment (Flared) | 32 | EACH | 2,000.00 | 64,000.00 | 1,940.00 | 62,080.00 | 1,959.40 | 62,700.80 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 17,485.00 | 17,485.00 | 16,155.00 | 16,155.00 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 230 | LNFT | 0.01 | 2.30 | 0.20 | 46.00 | 0.61 | 140.30 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 35.88 | MILE | 400.00 | 14,352.00 | 111.50 | 4,000.62 | 157.00 | 5,633.16 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 29.544 | MILE | 0.01 | 0.30 | 175.00 | 5,170.20 | 252.50 | 7,459.86 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 80.755 | MILE | 0.01 | 0.81 | 285.00 | 23,015.18 | 505.00 | 40,781.28 |
| 0020 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 0.01 | 0.04 | 25.00 | 100.00 | 101.00 | 404.00 |
| 0021 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 6,059 | EACH | 0.01 | 60.59 | 1.25 | 7,573.75 | 0.36 | 2,181.24 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 261,664.83 | 261,664.83 | 200,000.00 | 200,000.00 |
| 0023 | 729-16-00300 | Object Marker Assembly (Type 3) | 32 | EACH | 75.00 | 2,400.00 | 75.00 | 2,400.00 | 75.75 | 2,424.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,031 | EACH | 4.25 | 12,881.75 | 4.00 | 12,124.00 | 4.55 | 13,791.05 |
| 0025 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 115 | LNFT | 9.00 | 1,035.00 | 8.00 | 920.00 | 5.05 | 580.75 |
| 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 52.383 | MILE | 2,525.00 | 132,267.08 | 2,500.00 | 130,957.50 | 2,600.75 | 136,235.09 |
| 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 19.792 | MILE | 700.00 | 13,854.40 | 675.00 | 13,359.60 | 757.50 | 14,992.44 |
| 0028 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 500.00 | 1,000.00 | 450.00 | 900.00 | 378.75 | 757.50 |
| 0029 | 735-01-00100 | Mailboxes | 26 | EACH | 1.00 | 26.00 | 12.00 | 312.00 | 12.12 | 315.12 |
| 0030 | 735-02-00100 | Mailbox Supports (Single) | 25 | EACH | 125.00 | 3,125.00 | 59.00 | 1,475.00 | 95.95 | 2,398.75 |
| 0031 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 200.00 | 200.00 | 72.80 | 72.80 | 136.35 | 136.35 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 22,000.00 | 22,000.00 | 100,000.00 | 100,000.00 |
| 0033 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 100 | LNFT | 70.00 | 7,000.00 | 66.00 | 6,600.00 | 66.66 | 6,666.00 |
| 0034 | 732-05-00100 | Removal of Existing Markings | 0.284 | MILE | 4,000.00 | 1,136.00 | 3,053.76 | 867.27 | 4,040.00 | 1,147.36 |
| CONTRACTOR TOTAL | 6,780,517.85 | 7,341,054.00 | 7,975,871.34 | |||||||