Bid Tabulations
Letting of
06/13/2012
LA DOTD Headquarters
| Lead Project: H.002000.6 | |
| Parish: West Carroll | |
| Routes: LA 577 | |
| Description: Creek Bridge on LA 577 | |
| Type Const: CLEARING AND GRUBBING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $989,393.20 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49239 | W L Bass Construction Inc. | $668,766.60 |
| 2 | 05789 | D & J Construction Co., Inc. | $685,592.80 |
| 3 | 38936 | Southern Industrial Contractors Llc | $780,962.33 |
| 4 | 36936 | Dirtworks Inc Of Vicksburg | $808,009.60 |
| 5 | 49864 | Terral Construction LLC | $810,128.88 |
| 6 | 18546 | C W & W Contractors, Inc. | $955,645.05 |
| 7 | 00044 | Guinn Construction, LLC | $966,675.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W L Bass Construction Inc. |
- 2 - D & J Construction Co., Inc. |
- 3 - Southern Industrial Contractors Llc |
- 4 - Dirtworks Inc Of Vicksburg |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 16,000.00 | 16,000.00 | 5,000.00 | 5,000.00 | 40,000.00 | 40,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 500.00 | 500.00 | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 |
| 0003 | 202-02-04000 | Removal of Bridge Site 1 Remove 25' x 58' Bridge. Site 2 Remove 20' x 40' Bridge | 2 | EACH | 4,000.00 | 8,000.00 | 8,000.00 | 16,000.00 | 7,500.00 | 15,000.00 | 6,000.00 | 12,000.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 702 | LNFT | 5.00 | 3,510.00 | 5.00 | 3,510.00 | 5.00 | 3,510.00 | 5.00 | 3,510.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 2,954.6 | SQYD | 3.50 | 10,341.10 | 4.00 | 11,818.40 | 4.50 | 13,295.70 | 5.00 | 14,773.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 50,000.00 | 50,000.00 | 68,000.00 | 68,000.00 | 112,500.00 | 112,500.00 | 40,000.00 | 40,000.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 2,480 | LNFT | 0.00 | 0.00 | 3.00 | 7,440.00 | 2.00 | 4,960.00 | 3.00 | 7,440.00 |
| 0008 | 302-02-03121 | Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 3,296.2 | SQYD | 23.00 | 75,812.60 | 16.00 | 52,739.20 | 25.00 | 82,405.00 | 30.00 | 98,886.00 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 34.3 | CUYD | 95.00 | 3,258.50 | 95.00 | 3,258.50 | 65.00 | 2,229.50 | 100.00 | 3,430.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 639.9 | TON | 165.00 | 105,583.50 | 145.00 | 92,785.50 | 175.00 | 111,982.50 | 157.00 | 100,464.30 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 24.6 | TON | 165.00 | 4,059.00 | 145.00 | 3,567.00 | 175.00 | 4,305.00 | 150.00 | 3,690.00 |
| 0012 | 705-01-00100 | Barbed Wire Fence | 925 | LNFT | 10.00 | 9,250.00 | 7.50 | 6,937.50 | 7.00 | 6,475.00 | 5.00 | 4,625.00 |
| 0013 | 708-01-00100 | Right-of-Way Monument | 20 | EACH | 110.00 | 2,200.00 | 200.00 | 4,000.00 | 225.00 | 4,500.00 | 220.00 | 4,400.00 |
| 0014 | 708-02-00100 | Right-of-Way Monument Witness Post | 20 | EACH | 110.00 | 2,200.00 | 110.00 | 2,200.00 | 150.00 | 3,000.00 | 200.00 | 4,000.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,600.00 | 7,600.00 | 11,000.00 | 11,000.00 | 10,000.00 | 10,000.00 | 9,000.00 | 9,000.00 |
| 0016 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 6,000 | LNFT | 0.00 | 0.00 | 0.25 | 1,500.00 | 0.30 | 1,800.00 | 0.30 | 1,800.00 |
| 0017 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,666 | SQYD | 0.00 | 0.00 | 2.00 | 3,332.00 | 1.25 | 2,082.50 | 3.40 | 5,664.40 |
| 0018 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 380 | SQYD | 0.00 | 0.00 | 4.00 | 1,520.00 | 1.45 | 551.00 | 2.70 | 1,026.00 |
| 0019 | 726-01-00100 | Bedding Material | 565 | CUYD | 1.00 | 565.00 | 95.00 | 53,675.00 | 70.00 | 39,550.00 | 100.00 | 56,500.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 46,000.00 | 46,000.00 | 20,000.00 | 20,000.00 | 35,500.00 | 35,500.00 | 40,000.00 | 40,000.00 |
| 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 75.00 | 300.00 | 100.00 | 400.00 | 100.00 | 400.00 | 100.00 | 400.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 28 | EACH | 11.00 | 308.00 | 15.00 | 420.00 | 12.00 | 336.00 | 11.00 | 308.00 |
| 0023 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,140 | LNFT | 2.25 | 4,815.00 | 2.00 | 4,280.00 | 2.40 | 5,136.00 | 2.15 | 4,601.00 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.203 | MILE | 1,300.00 | 263.90 | 1,200.00 | 243.60 | 1,444.00 | 293.13 | 1,300.00 | 263.90 |
| 0025 | 739-01-00100 | Hydro-Seeding | 2 | ACRE | 1,700.00 | 3,400.00 | 1,500.00 | 3,000.00 | 1,500.00 | 3,000.00 | 3,000.00 | 6,000.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,000.00 | 4,000.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 | 6,000.00 | 6,000.00 |
| 0027 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 47.33 | CUYD | 1,150.00 | 54,429.50 | 910.00 | 43,070.30 | 800.00 | 37,864.00 | 1,000.00 | 47,330.00 |
| 0028 | 805-12-02000 | Reinforced Concrete Box Culverts (5' x 5') | 340 | LNFT | 330.00 | 112,200.00 | 350.00 | 119,000.00 | 320.00 | 108,800.00 | 400.00 | 136,000.00 |
| 0029 | 805-12-03000 | Reinforced Concrete Box Culverts (6' x 6') | 348 | LNFT | 400.00 | 139,200.00 | 300.00 | 104,400.00 | 410.00 | 142,680.00 | 425.00 | 147,900.00 |
| 0030 | 806-01-00100 | Deformed Reinforcing Steel | 4,378 | LB | 2.25 | 9,850.50 | 1.10 | 4,815.80 | 1.50 | 6,567.00 | 1.00 | 4,378.00 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,120 | INLF | 1.00 | 1,120.00 | 1.50 | 1,680.00 | 2.00 | 2,240.00 | 1.00 | 1,120.00 |
| CONTRACTOR TOTAL | 668,766.60 | 685,592.80 | 780,962.33 | 808,009.60 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Terral Construction LLC |
- 6 - C W & W Contractors, Inc. |
- 7 - Guinn Construction, LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 34,000.00 | 34,000.00 | 20,000.00 | 20,000.00 | 16,000.00 | 16,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 850.00 | 850.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge Site 1 Remove 25' x 58' Bridge. Site 2 Remove 20' x 40' Bridge | 2 | EACH | 7,500.00 | 15,000.00 | 7,500.00 | 15,000.00 | 10,000.00 | 20,000.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 702 | LNFT | 11.40 | 8,002.80 | 3.00 | 2,106.00 | 6.00 | 4,212.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 2,954.6 | SQYD | 4.25 | 12,557.05 | 5.00 | 14,773.00 | 5.00 | 14,773.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 77,000.00 | 77,000.00 | 105,000.00 | 105,000.00 | 150,000.00 | 150,000.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 2,480 | LNFT | 1.25 | 3,100.00 | 2.00 | 4,960.00 | 2.00 | 4,960.00 |
| 0008 | 302-02-03121 | Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 3,296.2 | SQYD | 17.34 | 57,156.11 | 24.00 | 79,108.80 | 20.50 | 67,572.10 |
| 0009 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 34.3 | CUYD | 117.00 | 4,013.10 | 110.00 | 3,773.00 | 100.00 | 3,430.00 |
| 0010 | 502-01-00100 | Superpave Asphaltic Concrete | 639.9 | TON | 170.00 | 108,783.00 | 160.00 | 102,384.00 | 175.00 | 111,982.50 |
| 0011 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 24.6 | TON | 192.00 | 4,723.20 | 185.00 | 4,551.00 | 250.00 | 6,150.00 |
| 0012 | 705-01-00100 | Barbed Wire Fence | 925 | LNFT | 10.00 | 9,250.00 | 7.00 | 6,475.00 | 12.00 | 11,100.00 |
| 0013 | 708-01-00100 | Right-of-Way Monument | 20 | EACH | 100.00 | 2,000.00 | 150.00 | 3,000.00 | 300.00 | 6,000.00 |
| 0014 | 708-02-00100 | Right-of-Way Monument Witness Post | 20 | EACH | 100.00 | 2,000.00 | 55.00 | 1,100.00 | 100.00 | 2,000.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,800.00 | 8,800.00 | 12,000.00 | 12,000.00 | 15,000.00 | 15,000.00 |
| 0016 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 6,000 | LNFT | 0.33 | 1,980.00 | 1.00 | 6,000.00 | 0.50 | 3,000.00 |
| 0017 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,666 | SQYD | 2.00 | 3,332.00 | 4.00 | 6,664.00 | 1.50 | 2,499.00 |
| 0018 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 380 | SQYD | 2.00 | 760.00 | 4.00 | 1,520.00 | 2.00 | 760.00 |
| 0019 | 726-01-00100 | Bedding Material | 565 | CUYD | 132.56 | 74,896.40 | 100.00 | 56,500.00 | 80.00 | 45,200.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 24,000.00 | 24,000.00 | 68,000.00 | 68,000.00 | 75,000.00 | 75,000.00 |
| 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 87.00 | 348.00 | 100.00 | 400.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 28 | EACH | 13.00 | 364.00 | 7.00 | 196.00 | 15.00 | 420.00 |
| 0023 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,140 | LNFT | 2.60 | 5,564.00 | 3.00 | 6,420.00 | 2.50 | 5,350.00 |
| 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.203 | MILE | 1,803.00 | 366.01 | 750.00 | 152.25 | 1,800.00 | 365.40 |
| 0025 | 739-01-00100 | Hydro-Seeding | 2 | ACRE | 1,500.00 | 3,000.00 | 1,400.00 | 2,800.00 | 2,000.00 | 4,000.00 |
| 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 9,000.00 | 9,000.00 | 12,000.00 | 12,000.00 | 8,000.00 | 8,000.00 |
| 0027 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 47.33 | CUYD | 1,965.00 | 93,003.45 | 1,200.00 | 56,796.00 | 1,200.00 | 56,796.00 |
| 0028 | 805-12-02000 | Reinforced Concrete Box Culverts (5' x 5') | 340 | LNFT | 334.00 | 113,560.00 | 460.00 | 156,400.00 | 395.00 | 134,300.00 |
| 0029 | 805-12-03000 | Reinforced Concrete Box Culverts (6' x 6') | 348 | LNFT | 360.00 | 125,280.00 | 560.00 | 194,880.00 | 515.00 | 179,220.00 |
| 0030 | 806-01-00100 | Deformed Reinforcing Steel | 4,378 | LB | 0.92 | 4,027.76 | 1.00 | 4,378.00 | 2.50 | 10,945.00 |
| 0031 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,120 | INLF | 3.00 | 3,360.00 | 3.00 | 3,360.00 | 2.00 | 2,240.00 |
| CONTRACTOR TOTAL | 810,128.88 | 955,645.05 | 966,675.00 | |||||||