Bid Tabulations
Letting of
02/08/2012
LA DOTD Headquarters
| Lead Project: H.001978.6 | |
| Parish: Morehouse | |
| Routes: LA 833 | |
| Description: LA 833: LA 140 TO 88 FT. WEST OF US 165 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $1,723,132.74 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05789 | D & J Construction Co., Inc. | $1,875,252.05 |
| 2 | 27948 | Diamond B Testing, Inc. | $2,061,737.15 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - D & J Construction Co., Inc. |
- 2 - Diamond B Testing, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 5,365.64 | 5,365.64 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,020 | CUYD | 24.00 | 24,480.00 | 47.55 | 48,501.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,337 | CUYD | 60.00 | 80,220.00 | 73.11 | 97,748.07 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 12,538.1 | TON | 98.00 | 1,228,733.80 | 109.91 | 1,378,062.57 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 254.3 | TON | 98.00 | 24,921.40 | 209.86 | 53,367.40 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 575 | SQYD | 20.00 | 11,500.00 | 48.59 | 27,939.25 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -28 | CUYD | 0.10 | -2.80 | 0.10 | -2.80 |
| 0008 | 510-01-00102 | Pavement Patching (8" Minimum Thickness) | 3,000 | SQYD | 80.00 | 240,000.00 | 77.75 | 233,250.00 |
| 0009 | 701-13-01180 | Corrugated Metal Pipe Arch (Extension) (72" Equiv.) | 8 | LNFT | 600.00 | 4,800.00 | 650.22 | 5,201.76 |
| 0010 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,200.00 | 2,400.00 | 1,354.62 | 2,709.24 |
| 0011 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 50 | SQYD | 150.00 | 7,500.00 | 169.33 | 8,466.50 |
| 0012 | 711-04-00100 | Geotextile Fabric | 50 | SQYD | 5.00 | 250.00 | 4.06 | 203.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 38,000.00 | 38,000.00 | 13,532.83 | 13,532.83 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 40 | LNFT | 2.00 | 80.00 | 0.81 | 32.40 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.773 | MILE | 250.00 | 2,443.25 | 208.55 | 2,038.16 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 6.064 | MILE | 250.00 | 1,516.00 | 270.92 | 1,642.86 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 12.504 | MILE | 350.00 | 4,376.40 | 677.31 | 8,469.08 |
| 0018 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 100.00 | 200.00 | 67.73 | 135.46 |
| 0019 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,294 | EACH | 0.25 | 323.50 | 1.35 | 1,746.90 |
| 0020 | 716-01-00100 | Mulch (Vegetative) | 9.5 | TON | 500.00 | 4,750.00 | 677.31 | 6,434.45 |
| 0021 | 717-01-00100 | Seeding | 285 | LB | 8.00 | 2,280.00 | 10.84 | 3,089.40 |
| 0022 | 718-01-00100 | Fertilizer | 4,750 | LB | 0.60 | 2,850.00 | 1.02 | 4,845.00 |
| 0023 | 726-01-00100 | Bedding Material | 11 | CUYD | 150.00 | 1,650.00 | 169.33 | 1,862.63 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 120,000.00 | 120,000.00 | 89,000.00 | 89,000.00 |
| 0025 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 100.00 | 200.00 | 101.60 | 203.20 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 646 | EACH | 6.00 | 3,876.00 | 6.10 | 3,940.60 |
| 0027 | 732-01-04080 | Plastic Pavement Striping (24" Width) (Preformed Retroreflective Thermoplastic) (Heat Applied) (125 mil) | 20 | LNFT | 26.00 | 520.00 | 27.09 | 541.80 |
| 0028 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 6.252 | MILE | 3,500.00 | 21,882.00 | 3,522.00 | 22,019.54 |
| 0029 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.308 | MILE | 1,250.00 | 385.00 | 1,083.70 | 333.78 |
| 0030 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 600.00 | 600.00 | 507.98 | 507.98 |
| 0031 | 735-01-00100 | Mailboxes | 7 | EACH | 5.00 | 35.00 | 1.35 | 9.45 |
| 0032 | 735-02-00100 | Mailbox Supports (Single) | 7 | EACH | 175.00 | 1,225.00 | 216.74 | 1,517.18 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 26,821.37 | 26,821.37 |
| 0034 | NS-200-00020 | Cleaning Existing Ditches | 75 | LNFT | 15.00 | 1,125.00 | 13.55 | 1,016.25 |
| 0035 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 21,510 | INLF | 0.75 | 16,132.50 | 0.52 | 11,185.20 |
| CONTRACTOR TOTAL | 1,875,252.05 | 2,061,737.15 | ||||||