Bid Tabulations
Letting of
03/14/2012
LA DOTD Headquarters
| Lead Project: H.001957.6 | |
| Parish: West Carroll, East Carroll | |
| Routes: LA 134 | |
| Description: BAYOU MACON BRIDGE | |
| Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE GIRDER SPAN BRIDGE AND RELATED WORK. | |
| Estimated Construction Cost: $5,198,000.51 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34567 | James Construction Group LLC | $4,660,507.28 |
| 2 | 38936 | Southern Industrial Contractors Llc | $4,877,743.21 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $4,923,872.61 |
| 4 | 14422 | T. L. Wallace Construction, Inc. | $5,194,621.39 |
| 5 | 39462 | Jb James Construction Llc | $5,910,328.04 |
| 6 | 36827 | Shavers-Whittle Construction LLC | $6,530,944.47 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - James Construction Group LLC |
- 2 - Southern Industrial Contractors Llc |
- 3 - Gilchrist Construction Co. LLC |
- 4 - T. L. Wallace Construction, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 120,000.00 | 120,000.00 | 122,000.00 | 122,000.00 | 100,000.00 | 100,000.00 | 325,000.00 | 325,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge Sta. 20+14, 690'x21', steel high truss bridge | 1 | EACH | 75,000.00 | 75,000.00 | 260,000.00 | 260,000.00 | 370,000.00 | 370,000.00 | 280,000.00 | 280,000.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 175 | LNFT | 5.00 | 875.00 | 4.00 | 700.00 | 10.00 | 1,750.00 | 6.85 | 1,198.75 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 12,484.5 | SQYD | 4.00 | 49,938.00 | 4.00 | 49,938.00 | 6.00 | 74,907.00 | 8.20 | 102,372.90 |
| 0005 | 203-01-00100 | General Excavation | 21,063.33 | CUYD | 7.00 | 147,443.31 | 7.00 | 147,443.31 | 5.00 | 105,316.65 | 4.90 | 103,210.32 |
| 0006 | 203-02-00100 | Drainage Excavation | 240 | CUYD | 12.00 | 2,880.00 | 28.75 | 6,900.00 | 30.00 | 7,200.00 | 9.15 | 2,196.00 |
| 0007 | 203-03-00100 | Embankment | 13,879.84 | CUYD | 14.00 | 194,317.76 | 15.00 | 208,197.60 | 15.00 | 208,197.60 | 6.40 | 88,830.98 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 105 | EACH | 150.00 | 15,750.00 | 143.75 | 15,093.75 | 150.00 | 15,750.00 | 130.00 | 13,650.00 |
| 0009 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 1 | EACH | 500.00 | 500.00 | 1,500.00 | 1,500.00 | 600.00 | 600.00 | 1,200.00 | 1,200.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 9,303 | LNFT | 3.00 | 27,909.00 | 2.00 | 18,606.00 | 1.40 | 13,024.20 | 1.65 | 15,349.95 |
| 0011 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 20,411.1 | SQYD | 25.00 | 510,277.50 | 22.78 | 464,964.86 | 22.00 | 449,044.20 | 25.00 | 510,277.50 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 157.04 | CUYD | 75.00 | 11,778.00 | 100.00 | 15,704.00 | 30.00 | 4,711.20 | 48.00 | 7,537.92 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 75.00 | 15,000.00 | 100.00 | 20,000.00 | 35.00 | 7,000.00 | 59.00 | 11,800.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 3,544.7 | TON | 125.00 | 443,087.50 | 144.90 | 513,627.03 | 130.00 | 460,811.00 | 130.00 | 460,811.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 566.6 | TON | 170.00 | 96,322.00 | 179.20 | 101,534.72 | 160.00 | 90,656.00 | 180.00 | 101,988.00 |
| 0016 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 200 | LNFT | 55.00 | 11,000.00 | 84.00 | 16,800.00 | 95.00 | 19,000.00 | 75.00 | 15,000.00 |
| 0017 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 160 | LNFT | 75.00 | 12,000.00 | 100.00 | 16,000.00 | 115.00 | 18,400.00 | 88.00 | 14,080.00 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 260 | LNFT | 45.00 | 11,700.00 | 70.00 | 18,200.00 | 50.00 | 13,000.00 | 46.00 | 11,960.00 |
| 0019 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 160 | LNFT | 55.00 | 8,800.00 | 75.00 | 12,000.00 | 75.00 | 12,000.00 | 61.00 | 9,760.00 |
| 0020 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 18.50 | 4,625.00 | 20.70 | 5,175.00 | 20.00 | 5,000.00 | 19.00 | 4,750.00 |
| 0021 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 55.00 | 5,500.00 | 69.00 | 6,900.00 | 65.00 | 6,500.00 | 63.00 | 6,300.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,000.00 | 8,000.00 | 2,300.00 | 9,200.00 | 2,300.00 | 9,200.00 | 2,100.00 | 8,400.00 |
| 0023 | 705-01-00100 | Barbed Wire Fence | 1,973 | LNFT | 6.50 | 12,824.50 | 6.50 | 12,824.50 | 7.50 | 14,797.50 | 6.85 | 13,515.05 |
| 0024 | 708-01-00100 | Right-of-Way Monument | 40 | EACH | 200.00 | 8,000.00 | 220.00 | 8,800.00 | 230.00 | 9,200.00 | 150.00 | 6,000.00 |
| 0025 | 708-02-00100 | Right-of-Way Monument Witness Post | 40 | EACH | 100.00 | 4,000.00 | 110.00 | 4,400.00 | 230.00 | 9,200.00 | 53.00 | 2,120.00 |
| 0026 | 712-04-00100 | Flexible Revetment | 759 | SQYD | 50.00 | 37,950.00 | 43.18 | 32,773.62 | 50.00 | 37,950.00 | 61.00 | 46,299.00 |
| 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 225,000.00 | 225,000.00 | 115,000.00 | 115,000.00 | 26,600.00 | 26,600.00 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 24.2 | TON | 650.00 | 15,730.00 | 747.52 | 18,089.98 | 500.00 | 12,100.00 | 680.00 | 16,456.00 |
| 0029 | 717-01-00100 | Seeding | 364 | LB | 8.50 | 3,094.00 | 9.77 | 3,556.28 | 9.50 | 3,458.00 | 8.95 | 3,257.80 |
| 0030 | 718-01-00100 | Fertilizer | 12,107 | LB | 0.56 | 6,779.92 | 0.65 | 7,869.55 | 0.50 | 6,053.50 | 0.60 | 7,264.20 |
| 0031 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,238.61 | SQYD | 1.30 | 1,610.19 | 1.53 | 1,895.07 | 2.00 | 2,477.22 | 1.35 | 1,672.12 |
| 0032 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 7,500.00 | 7,500.00 | 20,100.00 | 20,100.00 |
| 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 440,000.00 | 440,000.00 | 490,000.00 | 490,000.00 | 500,000.00 | 500,000.00 |
| 0034 | 729-16-00200 | Object Marker Assembly (Type 2) | 8 | EACH | 70.00 | 560.00 | 86.25 | 690.00 | 80.00 | 640.00 | 79.00 | 632.00 |
| 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 75.00 | 300.00 | 86.25 | 345.00 | 85.00 | 340.00 | 79.00 | 316.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 136 | EACH | 4.50 | 612.00 | 5.17 | 703.12 | 12.00 | 1,632.00 | 4.75 | 646.00 |
| 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.992 | MILE | 2,600.00 | 10,379.20 | 2,991.00 | 11,940.07 | 3,000.00 | 11,976.00 | 2,700.00 | 10,778.40 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | 53,200.00 | 53,200.00 |
| 0039 | 804-01-00200 | Precast Concrete Piles (14") | 100 | LNFT | 90.00 | 9,000.00 | 70.00 | 7,000.00 | 115.00 | 11,500.00 | 120.00 | 12,000.00 |
| 0040 | 804-01-00600 | Precast Concrete Piles (24") | 1,264 | LNFT | 120.00 | 151,680.00 | 85.62 | 108,223.68 | 90.00 | 113,760.00 | 127.50 | 161,160.00 |
| 0041 | 804-01-00700 | Precast Concrete Piles (30") | 3,456 | LNFT | 160.00 | 552,960.00 | 127.83 | 441,780.48 | 130.00 | 449,280.00 | 149.50 | 516,672.00 |
| 0042 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 | 36,500.00 | 36,500.00 |
| 0043 | 804-13-00100 | Precast Concrete Indicator Piles | 1 | EACH | 58,000.00 | 58,000.00 | 20,000.00 | 20,000.00 | 55,000.00 | 55,000.00 | 41,900.00 | 41,900.00 |
| 0044 | 804-17-00100 | Dynamic Monitoring | 14 | EACH | 1,000.00 | 14,000.00 | 1,500.00 | 21,000.00 | 700.00 | 9,800.00 | 2,100.00 | 29,400.00 |
| 0045 | 805-01-00700 | Class A Concrete (Bents) | 246.12 | CUYD | 850.00 | 209,202.00 | 1,000.00 | 246,120.00 | 700.00 | 172,284.00 | 750.00 | 184,590.00 |
| 0046 | 805-04-00100 | Class AA(M) Concrete | 810.66 | CUYD | 650.00 | 526,929.00 | 500.00 | 405,330.00 | 650.00 | 526,929.00 | 630.00 | 510,715.80 |
| 0047 | 805-08-00300 | Precast-Prestressed Concrete Girder (Type III) | 3,352.5 | LNFT | 100.00 | 335,250.00 | 116.00 | 388,890.00 | 95.00 | 318,487.50 | 107.00 | 358,717.50 |
| 0048 | 805-11-00100 | Strip Seal Joints | 80 | LNFT | 200.00 | 16,000.00 | 175.00 | 14,000.00 | 170.00 | 13,600.00 | 200.00 | 16,000.00 |
| 0049 | 806-01-00100 | Deformed Reinforcing Steel | 288,201 | LB | 1.00 | 288,201.00 | 0.70 | 201,740.70 | 0.84 | 242,088.84 | 1.00 | 288,201.00 |
| 0050 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 12,000.00 | 12,000.00 | 12,500.00 | 12,500.00 | 18,000.00 | 18,000.00 | 9,900.00 | 9,900.00 |
| 0051 | 810-01-00100 | Concrete Railing (Standard Barrier) | 1,422 | LNFT | 55.00 | 78,210.00 | 45.00 | 63,990.00 | 65.00 | 92,430.00 | 86.00 | 122,292.00 |
| 0052 | 813-01-00100 | Concrete Approach Slabs | 364.44 | SQYD | 210.00 | 76,532.40 | 199.75 | 72,796.89 | 230.00 | 83,821.20 | 280.00 | 102,043.20 |
| CONTRACTOR TOTAL | 4,660,507.28 | 4,877,743.21 | 4,923,872.61 | 5,194,621.39 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Jb James Construction Llc |
- 6 - Shavers-Whittle Construction LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 490,000.00 | 490,000.00 | 200,000.00 | 200,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge Sta. 20+14, 690'x21', steel high truss bridge | 1 | EACH | 80,000.00 | 80,000.00 | 615,000.00 | 615,000.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 175 | LNFT | 10.00 | 1,750.00 | 8.00 | 1,400.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 12,484.5 | SQYD | 4.00 | 49,938.00 | 6.00 | 74,907.00 |
| 0005 | 203-01-00100 | General Excavation | 21,063.33 | CUYD | 6.50 | 136,911.65 | 9.00 | 189,569.97 |
| 0006 | 203-02-00100 | Drainage Excavation | 240 | CUYD | 50.00 | 12,000.00 | 30.00 | 7,200.00 |
| 0007 | 203-03-00100 | Embankment | 13,879.84 | CUYD | 21.00 | 291,476.64 | 22.00 | 305,356.48 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 105 | EACH | 130.00 | 13,650.00 | 155.00 | 16,275.00 |
| 0009 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 1 | EACH | 900.00 | 900.00 | 1,300.00 | 1,300.00 |
| 0010 | 204-06-00100 | Temporary Silt Fencing | 9,303 | LNFT | 2.00 | 18,606.00 | 2.00 | 18,606.00 |
| 0011 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 20,411.1 | SQYD | 24.00 | 489,866.40 | 25.00 | 510,277.50 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 157.04 | CUYD | 75.00 | 11,778.00 | 95.00 | 14,918.80 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 200 | CUYD | 100.00 | 20,000.00 | 70.00 | 14,000.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 3,544.7 | TON | 125.00 | 443,087.50 | 140.00 | 496,258.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 566.6 | TON | 170.00 | 96,322.00 | 165.00 | 93,489.00 |
| 0016 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 200 | LNFT | 85.00 | 17,000.00 | 100.00 | 20,000.00 |
| 0017 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 160 | LNFT | 110.00 | 17,600.00 | 125.00 | 20,000.00 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 260 | LNFT | 45.00 | 11,700.00 | 70.00 | 18,200.00 |
| 0019 | 701-05-01060 | Side Drain Pipe (24" RCP/PP/CMP) | 160 | LNFT | 60.00 | 9,600.00 | 75.00 | 12,000.00 |
| 0020 | 704-03-00100 | Blocked Out Guard Rail | 250 | LNFT | 19.00 | 4,750.00 | 22.00 | 5,500.00 |
| 0021 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 60.00 | 6,000.00 | 68.00 | 6,800.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,000.00 | 8,000.00 | 2,400.00 | 9,600.00 |
| 0023 | 705-01-00100 | Barbed Wire Fence | 1,973 | LNFT | 7.00 | 13,811.00 | 9.00 | 17,757.00 |
| 0024 | 708-01-00100 | Right-of-Way Monument | 40 | EACH | 125.00 | 5,000.00 | 200.00 | 8,000.00 |
| 0025 | 708-02-00100 | Right-of-Way Monument Witness Post | 40 | EACH | 125.00 | 5,000.00 | 155.00 | 6,200.00 |
| 0026 | 712-04-00100 | Flexible Revetment | 759 | SQYD | 58.00 | 44,022.00 | 65.00 | 49,335.00 |
| 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 24,000.00 | 24,000.00 | 25,000.00 | 25,000.00 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 24.2 | TON | 650.00 | 15,730.00 | 800.00 | 19,360.00 |
| 0029 | 717-01-00100 | Seeding | 364 | LB | 9.00 | 3,276.00 | 10.00 | 3,640.00 |
| 0030 | 718-01-00100 | Fertilizer | 12,107 | LB | 0.60 | 7,264.20 | 0.70 | 8,474.90 |
| 0031 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,238.61 | SQYD | 1.40 | 1,734.05 | 1.50 | 1,857.92 |
| 0032 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 40,000.00 | 40,000.00 |
| 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 590,000.00 | 590,000.00 | 600,000.00 | 600,000.00 |
| 0034 | 729-16-00200 | Object Marker Assembly (Type 2) | 8 | EACH | 80.00 | 640.00 | 85.00 | 680.00 |
| 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | 90.00 | 360.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 136 | EACH | 5.00 | 680.00 | 5.00 | 680.00 |
| 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.992 | MILE | 2,600.00 | 10,379.20 | 3,000.00 | 11,976.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 48,000.00 | 48,000.00 | 175,000.00 | 175,000.00 |
| 0039 | 804-01-00200 | Precast Concrete Piles (14") | 100 | LNFT | 84.00 | 8,400.00 | 55.00 | 5,500.00 |
| 0040 | 804-01-00600 | Precast Concrete Piles (24") | 1,264 | LNFT | 85.00 | 107,440.00 | 120.00 | 151,680.00 |
| 0041 | 804-01-00700 | Precast Concrete Piles (30") | 3,456 | LNFT | 121.00 | 418,176.00 | 190.00 | 656,640.00 |
| 0042 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 500.00 | 500.00 | 5,000.00 | 5,000.00 |
| 0043 | 804-13-00100 | Precast Concrete Indicator Piles | 1 | EACH | 5,000.00 | 5,000.00 | 13,500.00 | 13,500.00 |
| 0044 | 804-17-00100 | Dynamic Monitoring | 14 | EACH | 500.00 | 7,000.00 | 1,500.00 | 21,000.00 |
| 0045 | 805-01-00700 | Class A Concrete (Bents) | 246.12 | CUYD | 1,600.00 | 393,792.00 | 1,400.00 | 344,568.00 |
| 0046 | 805-04-00100 | Class AA(M) Concrete | 810.66 | CUYD | 1,400.00 | 1,134,924.00 | 950.00 | 770,127.00 |
| 0047 | 805-08-00300 | Precast-Prestressed Concrete Girder (Type III) | 3,352.5 | LNFT | 100.00 | 335,250.00 | 135.00 | 452,587.50 |
| 0048 | 805-11-00100 | Strip Seal Joints | 80 | LNFT | 175.00 | 14,000.00 | 240.00 | 19,200.00 |
| 0049 | 806-01-00100 | Deformed Reinforcing Steel | 288,201 | LB | 1.00 | 288,201.00 | 1.00 | 288,201.00 |
| 0050 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0051 | 810-01-00100 | Concrete Railing (Standard Barrier) | 1,422 | LNFT | 60.00 | 85,320.00 | 65.00 | 92,430.00 |
| 0052 | 813-01-00100 | Concrete Approach Slabs | 364.44 | SQYD | 210.00 | 76,532.40 | 210.00 | 76,532.40 |
| CONTRACTOR TOTAL | 5,910,328.04 | 6,530,944.47 | ||||||