LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.001909.6
Parish: Catahoula
Routes: LA 3264, LA 124
Description: Catahoula Parish Resurfacing Projects
Type Const: STABILIZE BASE, PATCH & OVERLAY AND RELATED WORK
Estimated Construction Cost: $6,005,048.96


RankLicenseBidderConstruction Bid
1 05789 D & J Construction Co., Inc. $5,061,801.50
2 12487 Diamond B Construction Co., L.L.C. $5,087,457.56
3 12312 Gilchrist Construction Co. LLC $5,250,220.57
4 02214 W. E. Blain & Sons, Inc. $5,565,081.26


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
D & J Construction Co., Inc.
- 2 -
Diamond B Construction Co., L.L.C.
- 3 -
Gilchrist Construction Co. LLC
- 4 -
W. E. Blain & Sons, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-14500 Removal of Guard Rail 2,500      LNFT 7.00 17,500.00 10.50 26,250.00 6.00 15,000.00 20.00 50,000.00
0002 203-01-00100 General Excavation 3,000      CUYD 2.00 6,000.00 8.00 24,000.00 5.00 15,000.00 4.55 13,650.00
0003 203-03-00100 Embankment 3,000      CUYD 2.00 6,000.00 6.00 18,000.00 3.00 9,000.00 7.15 21,450.00
0004 203-07-00100 Borrow (Vehicular Measurement) 865      CUYD 25.00 21,625.00 22.00 19,030.00 16.00 13,840.00 22.50 19,462.50
0005 303-01-00400 In-Place Cement Stabilized Base Course (12" Thick) 80,042      SQYD 8.50 680,357.00 6.00 480,252.00 8.90 712,373.80 8.60 688,361.20
0006 304-05-00100 Lime Treatment (Type E) 1,260.6    TON 400.00 504,240.00 333.00 419,779.80 350.00 441,210.00 440.00 554,664.00
0007 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 5,587      CUYD 33.00 184,371.00 38.00 212,306.00 29.00 162,023.00 11.00 61,457.00
0008 502-01-00100 Superpave Asphaltic Concrete 32,038.6    TON 82.50 2,643,184.50 82.00 2,627,165.20 80.00 2,563,088.00 87.00 2,787,358.20
0009 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 771.9    TON 140.00 108,066.00 140.00 108,066.00 175.00 135,082.50 160.00 123,504.00
0010 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 42,517      GAL 3.30 140,306.10 3.75 159,438.75 3.10 131,802.70 3.31 140,731.27
0011 507-02-00200 Aggregate (S2) 62,525      SQYD 0.93 58,148.25 1.15 71,903.75 1.10 68,777.50 0.85 53,146.25
0012 507-02-00300 Aggregate (S3) 62,525      SQYD 0.71 44,392.75 1.10 68,777.50 0.82 51,270.50 0.78 48,769.50
0013 509-01-00100 Cold Planing Asphaltic Pavement 138,931      SQYD 1.00 138,931.00 3.10 430,686.10 2.75 382,060.25 2.10 291,755.10
0014 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -8,621      CUYD 0.10 -862.10 15.00 -129,315.00 0.10 -862.10 0.10 -862.10
0015 510-01-00200 Pavement Patching (12" Minimum Thickness) 888      SQYD 140.00 124,320.00 72.00 63,936.00 82.00 72,816.00 98.00 87,024.00
0016 701-01-01000 Cross Drain Pipe (24" RCP/PP) 60      LNFT 100.00 6,000.00 215.00 12,900.00 118.00 7,080.00 140.00 8,400.00
0017 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 8      LNFT 110.00 880.00 221.00 1,768.00 190.00 1,520.00 230.00 1,840.00
0018 701-10-01080 Reinforced Concrete Pipe (Extension) (30") 8      LNFT 125.00 1,000.00 230.00 1,840.00 205.00 1,640.00 253.00 2,024.00
0019 701-15-00100 Concrete Collar 2      EACH 750.00 1,500.00 1,625.00 3,250.00 1,500.00 3,000.00 1,685.00 3,370.00
0020 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 1,592      LNFT 41.00 65,272.00 42.00 66,864.00 31.00 49,352.00 40.00 63,680.00
0021 704-03-00100 Blocked Out Guard Rail 175      LNFT 21.00 3,675.00 21.00 3,675.00 21.00 3,675.00 20.00 3,500.00
0023 704-11-00100 Guard Rail End Treatment (Flared) 12      EACH 2,150.00 25,800.00 2,200.00 26,400.00 2,000.00 24,000.00 2,150.00 25,800.00
0024 713-01-00100 Temporary Signs and Barricades 1      LUMP 23,000.00 23,000.00 17,500.00 17,500.00 10,000.00 10,000.00 25,000.00 25,000.00
0025 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.41   MILE 750.00 1,057.50 165.00 232.65 250.00 352.50 1,500.00 2,115.00
0026 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 29.302  MILE 200.00 5,860.40 155.00 4,541.81 1.00 29.30 200.00 5,860.40
0027 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 35.203  MILE 1.00 35.20 200.00 7,040.60 1.00 35.20 400.00 14,081.20
0028 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 5,062      EACH 1.75 8,858.50 1.50 7,593.00 1.25 6,327.50 1.30 6,580.60
0029 722-01-00100 Project Site Laboratory 1      EACH 6,000.00 6,000.00 3,750.00 3,750.00 9,500.00 9,500.00 12,660.00 12,660.00
0030 726-01-00100 Bedding Material 35.3    CUYD 100.00 3,530.00 105.00 3,706.50 100.00 3,530.00 95.00 3,353.50
0031 727-01-00100 Mobilization 1      LUMP 80,000.00 80,000.00 130,000.00 130,000.00 230,000.00 230,000.00 145,000.00 145,000.00
0032 729-16-00300 Object Marker Assembly (Type 3) 12      EACH 100.00 1,200.00 85.00 1,020.00 65.00 780.00 80.00 960.00
0033 731-02-00100 Reflectorized Raised Pavement Markers 3,013      EACH 4.00 12,052.00 3.50 10,545.50 3.25 9,792.25 4.00 12,052.00
0034 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 17.601  MILE 2,400.00 42,242.40 2,200.00 38,722.20 2,100.00 36,962.10 2,200.00 38,722.20
0035 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 14.651  MILE 600.00 8,790.60 605.00 8,863.86 650.00 9,523.15 600.00 8,790.60
0036 732-05-00100 Removal of Existing Markings For Removal of Raised Pavement Markers Only 13.124  MILE 300.00 3,937.20 155.00 2,034.22 155.00 2,034.22 150.00 1,968.60
0037 735-01-00100 Mailboxes 80      EACH 5.00 400.00 1.10 88.00 12.00 960.00 1.00 80.00
0038 735-02-00100 Mailbox Supports (Single) 51      EACH 110.00 5,610.00 115.00 5,865.00 100.00 5,100.00 108.00 5,508.00
0039 735-03-00100 Mailbox Supports (Double) 11      EACH 130.00 1,430.00 130.00 1,430.00 130.00 1,430.00 125.00 1,375.00
0040 735-04-00100 Mailbox Supports (Multiple) 2      EACH 260.00 520.00 260.00 520.00 260.00 520.00 250.00 500.00
0041 740-01-00100 Construction Layout 1      LUMP 35,000.00 35,000.00 23,000.00 23,000.00 20,000.00 20,000.00 160,000.00 160,000.00
0042 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 42,768      INLF 0.15 6,415.20 0.59 25,233.12 0.15 6,415.20 0.68 29,082.24
0043 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 100      LNFT 35.00 3,500.00 35.00 3,500.00 51.00 5,100.00 34.00 3,400.00
0044 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 70.00 14,000.00 69.00 13,800.00 76.00 15,200.00 65.00 13,000.00
0045 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 842      CUYD 20.00 16,840.00 69.00 58,098.00 16.00 13,472.00 23.50 19,787.00
0046 202-02-32100 Removal of Pipe (Cross Drain) 1086+65 4'-24" 1034+00 4'-30" 1106+88 60'-24" 68      LNFT 12.00 816.00 50.00 3,400.00 6.00 408.00 90.00 6,120.00
                         
    CONTRACTOR TOTAL       5,061,801.50   5,087,457.56   5,250,220.57   5,565,081.26