Bid Tabulations
Letting of
12/14/2011
LA DOTD Headquarters
| Lead Project: H.001816.6 | |
| Parish: Vernon | |
| Routes: LA 117 | |
| Description: LA 117: GRANT ROAD - NATCHITOCHES PARISH LINE | |
| Type Const: GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $1,192,008.47 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34356 | Prairie Contractors Inc. | $1,259,379.46 |
| 2 | 41115 | Kdc Construction Co., Llc | $1,335,978.85 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $1,337,342.48 |
| 4 | 12487 | Diamond B Construction Co., L.L.C. | $1,460,760.54 |
| 5 | 05789 | D & J Construction Co., Inc. | $1,831,452.95 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Prairie Contractors Inc. |
- 2 - Kdc Construction Co., Llc |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Diamond B Construction Co., L.L.C. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 4 | SQYD | 100.00 | 400.00 | 15.00 | 60.00 | 100.00 | 400.00 | 200.00 | 800.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 260 | LNFT | 10.00 | 2,600.00 | 2.60 | 676.00 | 10.00 | 2,600.00 | 95.00 | 24,700.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 30.00 | 6,000.00 | 11.75 | 2,350.00 | 25.00 | 5,000.00 | 35.00 | 7,000.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,271 | CUYD | 70.00 | 158,970.00 | 56.50 | 128,311.50 | 61.00 | 138,531.00 | 60.00 | 136,260.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 6,586.3 | TON | 80.00 | 526,904.00 | 89.50 | 589,473.85 | 88.00 | 579,594.40 | 97.00 | 638,871.10 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 623.5 | TON | 115.00 | 71,702.50 | 124.00 | 77,314.00 | 135.00 | 84,172.50 | 170.00 | 105,995.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,194 | SQYD | 8.00 | 17,552.00 | 6.75 | 14,809.50 | 2.50 | 5,485.00 | 6.00 | 13,164.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -79 | CUYD | 0.01 | -0.79 | 1.35 | -106.65 | 6.00 | -474.00 | 1.00 | -79.00 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,000 | SQYD | 88.00 | 176,000.00 | 91.80 | 183,600.00 | 86.00 | 172,000.00 | 100.00 | 200,000.00 |
| 0010 | 510-02-00100 | Pavement Widening | 849.7 | SQYD | 88.00 | 74,773.60 | 88.00 | 74,773.60 | 85.00 | 72,224.50 | 80.00 | 67,976.00 |
| 0011 | 701-01-01041 | Cross Drain Pipe (36" RCP) | 8 | LNFT | 90.00 | 720.00 | 110.00 | 880.00 | 300.00 | 2,400.00 | 310.00 | 2,480.00 |
| 0012 | 701-08-00100 | Relaying Pipe | 30 | LNFT | 75.00 | 2,250.00 | 51.50 | 1,545.00 | 100.00 | 3,000.00 | 220.00 | 6,600.00 |
| 0013 | 701-15-00100 | Concrete Collar | 6 | EACH | 550.00 | 3,300.00 | 750.00 | 4,500.00 | 700.00 | 4,200.00 | 1,800.00 | 10,800.00 |
| 0014 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 400 | LNFT | 34.00 | 13,600.00 | 90.00 | 36,000.00 | 35.00 | 14,000.00 | 40.00 | 16,000.00 |
| 0015 | 704-03-00100 | Blocked Out Guard Rail | 87.5 | LNFT | 20.00 | 1,750.00 | 25.00 | 2,187.50 | 20.00 | 1,750.00 | 20.00 | 1,750.00 |
| 0016 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 55.00 | 5,500.00 | 80.00 | 8,000.00 | 60.00 | 6,000.00 | 55.00 | 5,500.00 |
| 0017 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 2,400.00 | 9,600.00 | 2,300.00 | 9,200.00 | 2,200.00 | 8,800.00 |
| 0018 | 707-01-00100 | Concrete Curb | 40 | LNFT | 24.00 | 960.00 | 17.50 | 700.00 | 75.00 | 3,000.00 | 25.00 | 1,000.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 13,000.00 | 13,000.00 | 8,800.00 | 8,800.00 | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 |
| 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.912 | MILE | 350.00 | 1,369.20 | 275.00 | 1,075.80 | 265.00 | 1,036.68 | 170.00 | 665.04 |
| 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.898 | MILE | 0.01 | 0.03 | 275.00 | 796.95 | 115.00 | 333.27 | 210.00 | 608.58 |
| 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 11.701 | MILE | 0.01 | 0.12 | 600.00 | 7,020.60 | 45.00 | 526.55 | 350.00 | 4,095.35 |
| 0023 | 726-01-00100 | Bedding Material | 28 | CUYD | 85.00 | 2,380.00 | 65.00 | 1,820.00 | 250.00 | 7,000.00 | 90.00 | 2,520.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 48,000.00 | 48,000.00 | 65,000.00 | 65,000.00 | 100,000.00 | 100,000.00 | 57,500.00 | 57,500.00 |
| 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 80.00 | 800.00 | 120.00 | 1,200.00 | 85.00 | 850.00 | 80.00 | 800.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 516 | EACH | 5.00 | 2,580.00 | 5.00 | 2,580.00 | 5.20 | 2,683.20 | 5.00 | 2,580.00 |
| 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.701 | MILE | 2,700.00 | 31,592.70 | 2,850.00 | 33,347.85 | 3,000.00 | 35,103.00 | 2,700.00 | 31,592.70 |
| 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.898 | MILE | 900.00 | 2,608.20 | 900.00 | 2,608.20 | 865.00 | 2,506.77 | 825.00 | 2,390.85 |
| 0029 | 735-01-00100 | Mailboxes | 26 | EACH | 11.00 | 286.00 | 12.00 | 312.00 | 20.00 | 520.00 | 1.00 | 26.00 |
| 0030 | 735-02-00100 | Mailbox Supports (Single) | 14 | EACH | 100.00 | 1,400.00 | 125.00 | 1,750.00 | 110.00 | 1,540.00 | 120.00 | 1,680.00 |
| 0031 | 735-03-00100 | Mailbox Supports (Double) | 9 | EACH | 140.00 | 1,260.00 | 175.00 | 1,575.00 | 155.00 | 1,395.00 | 170.00 | 1,530.00 |
| 0032 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 200.00 | 200.00 | 250.00 | 250.00 | 215.00 | 215.00 | 300.00 | 300.00 |
| 0033 | 739-01-00100 | Hydro-Seeding | 2.8 | ACRE | 1,200.00 | 3,360.00 | 2,400.00 | 6,720.00 | 1,300.00 | 3,640.00 | 1,200.00 | 3,360.00 |
| 0034 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 6,500.00 | 6,500.00 | 4,800.00 | 4,800.00 | 9,000.00 | 9,000.00 |
| 0035 | NS-200-00020 | Cleaning Existing Ditches | 120 | LNFT | 10.00 | 1,200.00 | 9.45 | 1,134.00 | 13.00 | 1,560.00 | 37.49 | 4,498.80 |
| 0036 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 200 | LNFT | 3.50 | 700.00 | 3.30 | 660.00 | 7.00 | 1,400.00 | 3.41 | 682.00 |
| 0037 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 280 | LNFT | 4.50 | 1,260.00 | 2.40 | 672.00 | 7.00 | 1,960.00 | 3.98 | 1,114.40 |
| 0038 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 480 | LNFT | 2.50 | 1,200.00 | 1.65 | 792.00 | 4.00 | 1,920.00 | 2.84 | 1,363.20 |
| 0039 | NS-500-00280 | Surface Preparation | 1 | LUMP | 62,000.00 | 62,000.00 | 3,500.00 | 3,500.00 | 30,000.00 | 30,000.00 | 62,736.33 | 62,736.33 |
| 0040 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 39,273 | INLF | 0.30 | 11,781.90 | 1.35 | 53,018.55 | 0.25 | 9,818.25 | 0.35 | 13,745.55 |
| 0041 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 104 | INLF | 5.00 | 520.00 | 1.65 | 171.60 | 4.34 | 451.36 | 3.41 | 354.64 |
| CONTRACTOR TOTAL | 1,259,379.46 | 1,335,978.85 | 1,337,342.48 | 1,460,760.54 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - D & J Construction Co., Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 4 | SQYD | 30.00 | 120.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 260 | LNFT | 75.00 | 19,500.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 45.00 | 9,000.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,271 | CUYD | 100.00 | 227,100.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 6,586.3 | TON | 118.00 | 777,183.40 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 623.5 | TON | 152.00 | 94,772.00 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,194 | SQYD | 10.00 | 21,940.00 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -79 | CUYD | 0.10 | -7.90 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,000 | SQYD | 115.00 | 230,000.00 |
| 0010 | 510-02-00100 | Pavement Widening | 849.7 | SQYD | 95.00 | 80,721.50 |
| 0011 | 701-01-01041 | Cross Drain Pipe (36" RCP) | 8 | LNFT | 100.00 | 800.00 |
| 0012 | 701-08-00100 | Relaying Pipe | 30 | LNFT | 100.00 | 3,000.00 |
| 0013 | 701-15-00100 | Concrete Collar | 6 | EACH | 600.00 | 3,600.00 |
| 0014 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 400 | LNFT | 33.00 | 13,200.00 |
| 0015 | 704-03-00100 | Blocked Out Guard Rail | 87.5 | LNFT | 21.00 | 1,837.50 |
| 0016 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 55.00 | 5,500.00 |
| 0017 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,100.00 | 8,400.00 |
| 0018 | 707-01-00100 | Concrete Curb | 40 | LNFT | 20.00 | 800.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 |
| 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.912 | MILE | 225.00 | 880.20 |
| 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.898 | MILE | 200.00 | 579.60 |
| 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 11.701 | MILE | 400.00 | 4,680.40 |
| 0023 | 726-01-00100 | Bedding Material | 28 | CUYD | 90.00 | 2,520.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 125,000.00 | 125,000.00 |
| 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 100.00 | 1,000.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 516 | EACH | 6.00 | 3,096.00 |
| 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 11.701 | MILE | 3,000.00 | 35,103.00 |
| 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.898 | MILE | 1,000.00 | 2,898.00 |
| 0029 | 735-01-00100 | Mailboxes | 26 | EACH | 6.00 | 156.00 |
| 0030 | 735-02-00100 | Mailbox Supports (Single) | 14 | EACH | 130.00 | 1,820.00 |
| 0031 | 735-03-00100 | Mailbox Supports (Double) | 9 | EACH | 225.00 | 2,025.00 |
| 0032 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 350.00 | 350.00 |
| 0033 | 739-01-00100 | Hydro-Seeding | 2.8 | ACRE | 1,250.00 | 3,500.00 |
| 0034 | 740-01-00100 | Construction Layout | 1 | LUMP | 18,000.00 | 18,000.00 |
| 0035 | NS-200-00020 | Cleaning Existing Ditches | 120 | LNFT | 10.00 | 1,200.00 |
| 0036 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 200 | LNFT | 7.00 | 1,400.00 |
| 0037 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 280 | LNFT | 7.00 | 1,960.00 |
| 0038 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 480 | LNFT | 3.00 | 1,440.00 |
| 0039 | NS-500-00280 | Surface Preparation | 1 | LUMP | 40,000.00 | 40,000.00 |
| 0040 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 39,273 | INLF | 0.25 | 9,818.25 |
| 0041 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 104 | INLF | 15.00 | 1,560.00 |
| CONTRACTOR TOTAL | 1,831,452.95 | |||||