Bid Tabulations
Letting of
12/05/2012
LA DOTD Headquarters
| Lead Project: H.001805.6 | |
| Parish: Sabine | |
| Routes: LA 174 | |
| Description: LA 174: E. JCT. LA 483 - JCT. LA 175 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, DRAINAGE STRUCTURES, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $3,071,306.98 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $3,252,512.69 |
| 2 | 08815 | W. E. Mcdonald & Son, LLC. | $3,336,854.60 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $3,367,419.99 |
| 4 | 36374 | Best-Yet Builders, Llc | $3,519,225.11 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - W. E. Mcdonald & Son, LLC. |
- 3 - Gilchrist Construction Co. LLC |
- 4 - Best-Yet Builders, Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 16 | SQYD | 25.00 | 400.00 | 80.00 | 1,280.00 | 25.00 | 400.00 | 50.00 | 800.00 |
| 0003 | 202-02-14500 | Removal of Guard Rail | 765 | LNFT | 15.00 | 11,475.00 | 3.00 | 2,295.00 | 9.00 | 6,885.00 | 4.00 | 3,060.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 195 | SQYD | 10.00 | 1,950.00 | 15.00 | 2,925.00 | 15.00 | 2,925.00 | 25.00 | 4,875.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,000 | CUYD | 12.00 | 12,000.00 | 20.00 | 20,000.00 | 15.00 | 15,000.00 | 20.00 | 20,000.00 |
| 0006 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 1,000 | CUYD | 12.00 | 12,000.00 | 20.00 | 20,000.00 | 13.50 | 13,500.00 | 20.00 | 20,000.00 |
| 0007 | 304-05-00100 | Lime Treatment (Type E) | 137.43 | TON | 550.00 | 75,586.50 | 475.00 | 65,279.25 | 345.00 | 47,413.35 | 365.00 | 50,161.95 |
| 0008 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 97,879 | SQYD | 7.75 | 758,562.25 | 8.15 | 797,713.85 | 8.30 | 812,395.70 | 8.00 | 783,032.00 |
| 0009 | 308-02-00100 | Removal of Existing Patches | 350 | SQYD | 10.00 | 3,500.00 | 15.00 | 5,250.00 | 4.00 | 1,400.00 | 20.00 | 7,000.00 |
| 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,900 | CUYD | 32.85 | 62,415.00 | 1.00 | 1,900.00 | 30.00 | 57,000.00 | 20.00 | 38,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 18,189.7 | TON | 93.00 | 1,691,642.10 | 93.00 | 1,691,642.10 | 88.00 | 1,600,693.60 | 101.63 | 1,848,619.21 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,455.6 | TON | 50.00 | 72,780.00 | 50.00 | 72,780.00 | 130.00 | 189,228.00 | 110.00 | 160,116.00 |
| 0013 | 509-01-00100 | Cold Planing Asphaltic Pavement | 84,321 | SQYD | 2.00 | 168,642.00 | 1.96 | 165,269.16 | 1.20 | 101,185.20 | 2.25 | 189,722.25 |
| 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,513 | CUYD | 0.10 | -351.30 | 0.10 | -351.30 | 1.00 | -3,513.00 | 0.10 | -351.30 |
| 0015 | 701-08-00100 | Relaying Pipe | 4 | LNFT | 150.00 | 600.00 | 175.00 | 700.00 | 120.00 | 480.00 | 250.00 | 1,000.00 |
| 0016 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 24 | LNFT | 150.00 | 3,600.00 | 215.00 | 5,160.00 | 120.00 | 2,880.00 | 52.00 | 1,248.00 |
| 0017 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 16 | LNFT | 200.00 | 3,200.00 | 215.00 | 3,440.00 | 125.00 | 2,000.00 | 80.00 | 1,280.00 |
| 0018 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 32 | LNFT | 250.00 | 8,000.00 | 225.00 | 7,200.00 | 135.00 | 4,320.00 | 115.00 | 3,680.00 |
| 0019 | 701-13-01060 | Corrugated Metal Pipe Arch (Extension) (30" Equiv.) | 8 | LNFT | 300.00 | 2,400.00 | 230.00 | 1,840.00 | 145.00 | 1,160.00 | 150.00 | 1,200.00 |
| 0020 | 701-15-00100 | Concrete Collar | 10 | EACH | 1,250.00 | 12,500.00 | 1,200.00 | 12,000.00 | 800.00 | 8,000.00 | 1,000.00 | 10,000.00 |
| 0021 | 704-03-00100 | Blocked Out Guard Rail | 150 | LNFT | 20.00 | 3,000.00 | 20.00 | 3,000.00 | 22.00 | 3,300.00 | 25.00 | 3,750.00 |
| 0022 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 150 | LNFT | 48.00 | 7,200.00 | 48.00 | 7,200.00 | 58.00 | 8,700.00 | 70.00 | 10,500.00 |
| 0023 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 65.00 | 19,500.00 | 65.00 | 19,500.00 | 75.00 | 22,500.00 | 70.00 | 21,000.00 |
| 0024 | 704-11-00100 | Guard Rail End Treatment (Flared) | 12 | EACH | 2,100.00 | 25,200.00 | 2,100.00 | 25,200.00 | 2,300.00 | 27,600.00 | 2,500.00 | 30,000.00 |
| 0025 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 198 | SQYD | 100.00 | 19,800.00 | 72.00 | 14,256.00 | 60.00 | 11,880.00 | 150.00 | 29,700.00 |
| 0026 | 711-04-00100 | Geotextile Fabric | 219 | SQYD | 2.50 | 547.50 | 3.50 | 766.50 | 2.00 | 438.00 | 2.50 | 547.50 |
| 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 81,000.00 | 81,000.00 | 40,000.00 | 40,000.00 | 90,000.00 | 90,000.00 | 20,000.00 | 20,000.00 |
| 0028 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 21.847 | MILE | 300.00 | 6,554.10 | 300.00 | 6,554.10 | 400.00 | 8,738.80 | 700.00 | 15,292.90 |
| 0029 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 14.016 | MILE | 1.00 | 14.02 | 1.00 | 14.02 | 1.00 | 14.02 | 250.00 | 3,504.00 |
| 0030 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 66.617 | MILE | 1.00 | 66.62 | 1.00 | 66.62 | 1.00 | 66.62 | 150.00 | 9,992.55 |
| 0031 | 716-01-00100 | Mulch (Vegetative) | 12.7 | TON | 600.00 | 7,620.00 | 750.00 | 9,525.00 | 700.00 | 8,890.00 | 1,500.00 | 19,050.00 |
| 0032 | 717-01-00100 | Seeding | 190 | LB | 15.00 | 2,850.00 | 10.00 | 1,900.00 | 10.00 | 1,900.00 | 8.50 | 1,615.00 |
| 0033 | 718-01-00100 | Fertilizer | 6,333 | LB | 1.00 | 6,333.00 | 0.60 | 3,799.80 | 0.70 | 4,433.10 | 0.55 | 3,483.15 |
| 0034 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 1.00 | 1.00 | 3,000.00 | 3,000.00 | 7,000.00 | 7,000.00 | 15,000.00 | 15,000.00 |
| 0035 | 726-01-00100 | Bedding Material | 18.5 | CUYD | 100.00 | 1,850.00 | 95.00 | 1,757.50 | 120.00 | 2,220.00 | 100.00 | 1,850.00 |
| 0036 | 727-01-00100 | Mobilization | 1 | LUMP | 81,000.00 | 81,000.00 | 215,000.00 | 215,000.00 | 200,000.00 | 200,000.00 | 75,000.00 | 75,000.00 |
| 0037 | 729-16-00300 | Object Marker Assembly (Type 3) | 23 | EACH | 87.00 | 2,001.00 | 87.00 | 2,001.00 | 95.00 | 2,185.00 | 110.00 | 2,530.00 |
| 0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,315 | EACH | 4.00 | 5,260.00 | 4.00 | 5,260.00 | 5.90 | 7,758.50 | 4.00 | 5,260.00 |
| 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 3.00 | 36.00 | 20.00 | 240.00 | 5.60 | 67.20 | 10.00 | 120.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 22.206 | MILE | 2,100.00 | 46,632.60 | 2,300.00 | 51,073.80 | 3,000.00 | 66,618.00 | 2,700.00 | 59,956.20 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.672 | MILE | 600.00 | 2,803.20 | 600.00 | 2,803.20 | 950.00 | 4,438.40 | 600.00 | 2,803.20 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 0.1 | MILE | 2,000.00 | 200.00 | 3,000.00 | 300.00 | 5,600.00 | 560.00 | 5,000.00 | 500.00 |
| 0043 | 735-01-00100 | Mailboxes | 29 | EACH | 1.00 | 29.00 | 1.00 | 29.00 | 11.00 | 319.00 | 50.00 | 1,450.00 |
| 0044 | 735-02-00100 | Mailbox Supports (Single) | 19 | EACH | 135.00 | 2,565.00 | 135.00 | 2,565.00 | 120.00 | 2,280.00 | 75.00 | 1,425.00 |
| 0045 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 175.00 | 700.00 | 175.00 | 700.00 | 145.00 | 580.00 | 100.00 | 400.00 |
| 0046 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 325.00 | 650.00 | 325.00 | 650.00 | 270.00 | 540.00 | 110.00 | 220.00 |
| 0047 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0048 | NS-200-00020 | Cleaning Existing Ditches | 120 | LNFT | 10.00 | 1,200.00 | 15.00 | 1,800.00 | 8.00 | 960.00 | 100.00 | 12,000.00 |
| 0049 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 270 | INLF | 4.45 | 1,201.50 | 5.00 | 1,350.00 | 3.00 | 810.00 | 5.00 | 1,350.00 |
| 0050 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 7.3 | MILE | 1,342.00 | 9,796.60 | 1,400.00 | 10,220.00 | 585.00 | 4,270.50 | 1,025.00 | 7,482.50 |
| CONTRACTOR TOTAL | 3,252,512.69 | 3,336,854.60 | 3,367,419.99 | 3,519,225.11 | ||||||||