LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.001471.6
Parish: Assumption
Routes: LA 1
Description: LA 1: LAFOURCHE PARISH LINE - LA 401
Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, AST, SUPERPAVE ASPHALT CONCRETE OVERLAY AND RELATED WORK.
Estimated Construction Cost: $5,568,277.64


RankLicenseBidderConstruction Bid
1 06487 Huey Stockstill, Inc. $4,955,368.54
2 00481 Coastal Bridge Co., L.L.C. $5,282,421.99
3 06276 Barriere Construction Co., LLC $5,938,811.06
4 00849 F.G. Sullivan, Jr. Contractor LLC $6,144,897.90


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Huey Stockstill, Inc.
- 2 -
Coastal Bridge Co., L.L.C.
- 3 -
Barriere Construction Co., LLC
- 4 -
F.G. Sullivan, Jr. Contractor LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 35      SQYD 20.00 700.00 50.00 1,750.00 16.00 560.00 12.00 420.00
0002 202-02-14500 Removal of Guard Rail 434      LNFT 4.50 1,953.00 3.25 1,410.50 4.00 1,736.00 3.00 1,302.00
0003 203-07-00100 Borrow (Vehicular Measurement) 4,585      CUYD 10.00 45,850.00 1.00 4,585.00 15.00 68,775.00 15.00 68,775.00
0004 204-02-00100 Temporary Hay or Straw Bales 226      EACH 10.00 2,260.00 1.00 226.00 1.00 226.00 11.50 2,599.00
0005 204-06-00100 Temporary Silt Fencing 5,650      LNFT 1.30 7,345.00 0.10 565.00 1.00 5,650.00 1.75 9,887.50
0006 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 975      CUYD 70.00 68,250.00 25.00 24,375.00 50.00 48,750.00 40.00 39,000.00
0007 502-01-00100 Superpave Asphaltic Concrete 36,537.2    TON 82.00 2,996,050.40 77.50 2,831,633.00 83.00 3,032,587.60 95.00 3,471,034.00
0008 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 4,928.2    TON 1.00 4,928.20 1.00 4,928.20 120.00 591,384.00 95.00 468,179.00
0009 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 103,560.7    GAL 3.60 372,818.52 3.60 372,818.52 3.50 362,462.45 4.00 414,242.80
0010 507-02-00200 Aggregate (S2) 152,295.1    SQYD 0.85 129,450.84 0.90 137,065.59 0.89 135,542.64 1.00 152,295.10
0011 507-02-00300 Aggregate (S3) 152,295.1    SQYD 0.75 114,221.33 0.70 106,606.57 0.70 106,606.57 1.00 152,295.10
0012 509-01-00100 Cold Planing Asphaltic Pavement 167,313      SQYD 1.25 209,141.25 3.50 585,595.50 1.00 167,313.00 2.15 359,722.95
0013 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -3,634      CUYD 0.00 0.00 0.10 -363.40 10.00 -36,340.00 0.00 0.00
0014 510-01-00100 Pavement Patching (6" Minimum Thickness) 300      SQYD 80.00 24,000.00 75.00 22,500.00 55.00 16,500.00 85.00 25,500.00
0015 510-01-00300 Pavement Patching (18" Minimum Thickness) 1,530.6    SQYD 135.00 206,631.00 50.00 76,530.00 130.00 198,978.00 160.00 244,896.00
0016 701-03-02040 Storm Drain Pipe (Outfall) (24" PP or 30" CMP) 80      LNFT 60.00 4,800.00 65.00 5,200.00 60.00 4,800.00 95.00 7,600.00
0017 702-03-00100 Catch Basins (CB-01) 1      EACH 3,200.00 3,200.00 3,100.00 3,100.00 3,000.00 3,000.00 3,000.00 3,000.00
0018 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 268      LNFT 31.00 8,308.00 43.00 11,524.00 30.00 8,040.00 40.00 10,720.00
0019 704-03-00100 Blocked Out Guard Rail 187.6    LNFT 19.00 3,564.40 16.00 3,001.60 20.00 3,752.00 15.00 2,814.00
0020 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 91.7    LNFT 63.00 5,777.10 60.00 5,502.00 60.00 5,502.00 55.00 5,043.50
0021 704-11-00200 Guard Rail End Treatment (Tangent) 3      EACH 2,400.00 7,200.00 2,900.00 8,700.00 2,300.00 6,900.00 2,700.00 8,100.00
0022 706-02-00200 Concrete Drive (6" Thick) 48.8    SQYD 54.00 2,635.20 90.00 4,392.00 55.00 2,684.00 90.00 4,392.00
0023 713-01-00100 Temporary Signs and Barricades 1      LUMP 30,000.00 30,000.00 125,000.00 125,000.00 313,000.00 313,000.00 100,000.00 100,000.00
0024 713-02-00300 Temporary Pavement Markings (8" Width) 200      LNFT 0.10 20.00 0.30 60.00 0.10 20.00 0.15 30.00
0025 713-02-00500 Temporary Pavement Markings (24" Width) 2,700      LNFT 0.10 270.00 0.85 2,295.00 0.10 270.00 0.35 945.00
0026 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 32.22   MILE 200.00 6,444.00 400.00 12,888.00 130.00 4,188.60 500.00 16,110.00
0027 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 22.464  MILE 225.00 5,054.40 330.00 7,413.12 100.00 2,246.40 100.00 2,246.40
0028 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 93.192  MILE 275.00 25,627.80 330.00 30,753.36 100.00 9,319.20 100.00 9,319.20
0029 713-05-00100 Temporary Pavement Legends & Symbols (Arrow) 12      EACH 1.00 12.00 50.00 600.00 15.00 180.00 25.00 300.00
0030 726-01-00100 Bedding Material 76.9    CUYD 70.00 5,383.00 1.00 76.90 70.00 5,383.00 1.00 76.90
0031 727-01-00100 Mobilization 1      LUMP 365,000.00 365,000.00 500,000.00 500,000.00 605,000.00 605,000.00 200,000.00 200,000.00
0032 729-16-00200 Object Marker Assembly (Type 2) 48      EACH 47.00 2,256.00 50.00 2,400.00 45.00 2,160.00 45.00 2,160.00
0033 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 80.00 320.00 85.00 340.00 80.00 320.00 75.00 300.00
0034 731-02-00100 Reflectorized Raised Pavement Markers 1,937      EACH 4.50 8,716.50 5.41 10,479.17 4.00 7,748.00 5.25 10,169.25
0035 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 200      LNFT 1.25 250.00 1.50 300.00 1.25 250.00 1.35 270.00
0036 732-01-02080 Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 2,700      LNFT 4.25 11,475.00 5.50 14,850.00 4.25 11,475.00 5.00 13,500.00
0037 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 31.064  MILE 2,500.00 77,660.00 2,750.00 85,426.00 2,500.00 77,660.00 2,600.00 80,766.40
0038 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 7.488  MILE 700.00 5,241.60 950.00 7,113.60 700.00 5,241.60 850.00 6,364.80
0039 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 6      EACH 200.00 1,200.00 250.00 1,500.00 200.00 1,200.00 215.00 1,290.00
0040 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 6      EACH 200.00 1,200.00 250.00 1,500.00 200.00 1,200.00 215.00 1,290.00
0041 735-01-00100 Mailboxes 394      EACH 1.00 394.00 1.03 405.82 1.00 394.00 1.00 394.00
0042 735-02-00100 Mailbox Supports (Single) 373      EACH 105.00 39,165.00 120.00 44,760.00 100.00 37,300.00 105.00 39,165.00
0043 735-03-00100 Mailbox Supports (Double) 3      EACH 185.00 555.00 200.00 600.00 200.00 600.00 185.00 555.00
0044 735-04-00100 Mailbox Supports (Multiple) 4      EACH 350.00 1,400.00 385.00 1,540.00 300.00 1,200.00 350.00 1,400.00
0045 739-01-00100 Hydro-Seeding 25.94   ACRE 1,000.00 25,940.00 1.00 25.94 900.00 23,346.00 1,200.00 31,128.00
0046 740-01-00100 Construction Layout 1      LUMP 20,000.00 20,000.00 75,000.00 75,000.00 20,000.00 20,000.00 100,000.00 100,000.00
0047 NS-201-00001 Tree and Stump Removal (Under 36" - 36" Diameter) 1      EACH 1,900.00 1,900.00 5,000.00 5,000.00 1,900.00 1,900.00 1,000.00 1,000.00
0048 NS-500-00360 Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement 58,000      INLF 1.50 87,000.00 2.25 130,500.00 1.00 58,000.00 1.00 58,000.00
0049 NS-700-00240 Special Guard Rail Anchor Section 1      EACH 900.00 900.00 1,350.00 1,350.00 900.00 900.00 1,250.00 1,250.00
0050 NS-724-00002 Rumble Strips (Shoulder Ground-In) 21.5    MILE 600.00 12,900.00 400.00 8,600.00 600.00 12,900.00 700.00 15,050.00
                         
    CONTRACTOR TOTAL       4,955,368.54   5,282,421.99   5,938,811.06   6,144,897.90