Bid Tabulations
Letting of
04/11/2012
LA DOTD Headquarters
| Lead Project: H.001391.6 | |
| Parish: Plaquemines | |
| Routes: LA 23 | |
| Description: LA 23 (SOUTH OF JESUIT BEND - ALLIANCE) | |
| Type Const: PAVEMENT PATCHING, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK | |
| Estimated Construction Cost: $5,364,325.80 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $5,463,481.90 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $5,735,087.36 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 10,450 | CUYD | 6.00 | 62,700.00 | 25.00 | 261,250.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 31,129.6 | TON | 100.00 | 3,112,960.00 | 110.00 | 3,424,256.00 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 455.6 | TON | 200.00 | 91,120.00 | 200.00 | 91,120.00 |
| 0004 | 509-01-00100 | Cold Planing Asphaltic Pavement | 128,039 | SQYD | 2.00 | 256,078.00 | 2.00 | 256,078.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,556.64 | CUYD | 10.00 | -35,566.40 | 25.00 | -88,916.00 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 260 | SQYD | 75.00 | 19,500.00 | 60.00 | 15,600.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 4,635.1 | SQYD | 83.00 | 384,713.30 | 110.00 | 509,861.00 |
| 0008 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 92,394 | LNFT | 1.00 | 92,394.00 | 1.30 | 120,112.20 |
| 0009 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 36,958 | LNFT | 1.50 | 55,437.00 | 1.55 | 57,284.90 |
| 0010 | 602-03-00100 | Cleaning and Sealing Random cracks | 2,000 | LNFT | 5.00 | 10,000.00 | 2.60 | 5,200.00 |
| 0011 | 701-14-00100 | Cleaning Existing Pipes 24" CPP | 75 | LNFT | 6.50 | 487.50 | 10.00 | 750.00 |
| 0012 | 701-14-00100 | Cleaning Existing Pipes 24" RCP | 775 | LNFT | 6.50 | 5,037.50 | 10.00 | 7,750.00 |
| 0013 | 701-14-00100 | Cleaning Existing Pipes 30" RCP | 310 | LNFT | 7.00 | 2,170.00 | 15.00 | 4,650.00 |
| 0014 | 701-14-00100 | Cleaning Existing Pipes 60" CMP | 150 | LNFT | 8.00 | 1,200.00 | 30.00 | 4,500.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 40,000.00 | 40,000.00 |
| 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 46.7 | MILE | 150.00 | 7,005.00 | 10.00 | 467.00 |
| 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 65 | MILE | 150.00 | 9,750.00 | 10.00 | 650.00 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 23 | MILE | 225.00 | 5,175.00 | 15.00 | 345.00 |
| 0019 | 717-01-00100 | Seeding | 850 | LB | 11.00 | 9,350.00 | 10.00 | 8,500.00 |
| 0020 | 718-01-00100 | Fertilizer | 28,280 | LB | 1.00 | 28,280.00 | 0.65 | 18,382.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 500,000.00 | 500,000.00 | 350,000.00 | 350,000.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,750 | EACH | 5.00 | 8,750.00 | 5.50 | 9,625.00 |
| 0023 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,220 | LNFT | 1.50 | 1,830.00 | 1.40 | 1,708.00 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 23.32 | MILE | 2,900.00 | 67,628.00 | 2,600.00 | 60,632.00 |
| 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 11.7 | MILE | 2,200.00 | 25,740.00 | 875.00 | 10,237.50 |
| 0026 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 7 | EACH | 250.00 | 1,750.00 | 225.00 | 1,575.00 |
| 0027 | 732-04-19020 | Plastic Pavement Legends and Symbols (SCHOOL ZONE) | 2 | EACH | 300.00 | 600.00 | 415.00 | 830.00 |
| 0028 | 735-01-00100 | Mailboxes | 106 | EACH | 12.00 | 1,272.00 | 6.25 | 662.50 |
| 0029 | 735-02-00100 | Mailbox Supports (Single) | 100 | EACH | 200.00 | 20,000.00 | 125.00 | 12,500.00 |
| 0030 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 350.00 | 1,400.00 | 225.00 | 900.00 |
| 0031 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 500.00 | 1,000.00 | 415.00 | 830.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 5,000.00 | 5,000.00 |
| 0033 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 184,788 | LNFT | 0.75 | 138,591.00 | 0.52 | 96,089.76 |
| 0034 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 73,915.2 | LNFT | 0.75 | 55,436.40 | 0.52 | 38,435.90 |
| 0035 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 129,352 | LNFT | 2.50 | 323,380.00 | 1.30 | 168,157.60 |
| 0036 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 163,812 | INLF | 0.05 | 8,190.60 | 0.50 | 81,906.00 |
| 0037 | NS-702-00001 | Cleaning Existing Catch Basin | 75 | EACH | 85.00 | 6,375.00 | 325.00 | 24,375.00 |
| 0038 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 23.82 | MILE | 400.00 | 9,528.00 | 650.00 | 15,483.00 |
| 0039 | NS-P38-00001 | Concrete Curb Barrier (Drilled and Doweled) | 3,380 | LNFT | 19.00 | 64,220.00 | 35.00 | 118,300.00 |
| CONTRACTOR TOTAL | 5,463,481.90 | 5,735,087.36 | ||||||