Bid Tabulations
Letting of
10/12/2011
LA DOTD Headquarters
| Lead Project: H.001365.6 | |
| Parish: St. Helena | |
| Routes: LA 10 | |
| Description: WILLIE REDDEN ROAD - SOUTH JCT. LA 37 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $2,378,937.55 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $2,139,354.66 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,379,805.13 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $2,402,259.55 |
| 4 | 00849 | F.G. Sullivan, Jr. Contractor LLC | $2,947,831.90 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Gilchrist Construction Co. LLC |
- 4 - F.G. Sullivan, Jr. Contractor LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,740 | CUYD | 15.00 | 26,100.00 | 26.00 | 45,240.00 | 20.00 | 34,800.00 | 10.00 | 17,400.00 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 16,254.7 | TON | 74.00 | 1,202,847.80 | 77.00 | 1,251,611.90 | 80.00 | 1,300,376.00 | 100.00 | 1,625,470.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete (Shoulder Work) | 7,085.3 | TON | 74.00 | 524,312.20 | 77.00 | 545,568.10 | 78.00 | 552,653.40 | 100.00 | 708,530.00 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 799.8 | TON | 74.00 | 59,185.20 | 150.00 | 119,970.00 | 180.00 | 143,964.00 | 100.00 | 79,980.00 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 62,307 | SQYD | 1.25 | 77,883.75 | 1.80 | 112,152.60 | 0.60 | 37,384.20 | 2.00 | 124,614.00 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,991.25 | CUYD | 25.00 | -49,781.25 | 0.10 | -199.13 | 1.00 | -1,991.25 | 0.00 | 0.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 800 | SQYD | 75.00 | 60,000.00 | 100.00 | 80,000.00 | 95.00 | 76,000.00 | 100.00 | 80,000.00 |
| 0008 | 702-04-00100 | Adjusting Manholes | 3 | EACH | 100.00 | 300.00 | 1,400.00 | 4,200.00 | 1,100.00 | 3,300.00 | 100.00 | 300.00 |
| 0009 | 711-02-00300 | Riprap (30 lb) | 20 | CUYD | 175.00 | 3,500.00 | 200.00 | 4,000.00 | 140.00 | 2,800.00 | 100.00 | 2,000.00 |
| 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 11,000.00 | 11,000.00 | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 |
| 0011 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.077 | MILE | 110.00 | 1,438.47 | 175.00 | 2,288.48 | 350.00 | 4,576.95 | 500.00 | 6,538.50 |
| 0012 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 7.293 | MILE | 1.00 | 7.29 | 5,000.00 | 36,465.00 | 100.00 | 729.30 | 4,500.00 | 32,818.50 |
| 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 43.425 | MILE | 100.00 | 4,342.50 | 275.00 | 11,941.88 | 100.00 | 4,342.50 | 250.00 | 10,856.25 |
| 0014 | 717-01-00100 | Seeding | 153.2 | LB | 10.00 | 1,532.00 | 10.00 | 1,532.00 | 10.00 | 1,532.00 | 9.00 | 1,378.80 |
| 0015 | 718-01-00100 | Fertilizer | 5,107 | LB | 0.65 | 3,319.55 | 0.60 | 3,064.20 | 0.65 | 3,319.55 | 0.55 | 2,808.85 |
| 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 115,000.00 | 115,000.00 | 82,000.00 | 82,000.00 | 155,000.00 | 155,000.00 | 73,000.00 | 73,000.00 |
| 0017 | 729-01-00100 | Sign (Type A) (W11-1 "Bicycle Traffic" & W16-1P "Share The Road") | 37.1 | SQFT | 15.00 | 556.50 | 22.00 | 816.20 | 15.00 | 556.50 | 15.00 | 556.50 |
| 0018 | 729-21-00100 | U-Channel Post | 8 | EACH | 75.00 | 600.00 | 60.00 | 480.00 | 55.00 | 440.00 | 130.00 | 1,040.00 |
| 0019 | 731-02-00100 | Reflectorized Raised Pavement Markers | 578 | EACH | 5.00 | 2,890.00 | 6.00 | 3,468.00 | 5.70 | 3,294.60 | 5.25 | 3,034.50 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.475 | MILE | 2,850.00 | 41,253.75 | 3,000.00 | 43,425.00 | 2,800.00 | 40,530.00 | 2,800.00 | 40,530.00 |
| 0021 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.341 | MILE | 900.00 | 2,106.90 | 900.00 | 2,106.90 | 800.00 | 1,872.80 | 1,000.00 | 2,341.00 |
| 0022 | 735-01-00100 | Mailboxes | 14 | EACH | 10.00 | 140.00 | 11.00 | 154.00 | 11.00 | 154.00 | 5.00 | 70.00 |
| 0023 | 735-02-00100 | Mailbox Supports (Single) | 11 | EACH | 110.00 | 1,210.00 | 160.00 | 1,760.00 | 125.00 | 1,375.00 | 115.00 | 1,265.00 |
| 0024 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 250.00 | 250.00 | 360.00 | 360.00 | 250.00 | 250.00 | 300.00 | 300.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 9,200.00 | 9,200.00 | 6,000.00 | 6,000.00 | 40,000.00 | 40,000.00 |
| 0026 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 36,000 | INLF | 0.01 | 360.00 | 0.20 | 7,200.00 | 0.25 | 9,000.00 | 0.50 | 18,000.00 |
| CONTRACTOR TOTAL | 2,139,354.66 | 2,379,805.13 | 2,402,259.55 | 2,947,831.90 | ||||||||