Bid Tabulations
Letting of
05/30/2012
LA DOTD Headquarters
| Lead Project: H.001267.6 | |
| Parish: Rapides | |
| Routes: LA 1 | |
| Description: BAYOU JEAN DEJEAN BRIDGE | |
| Type Const: GRADING, CLEARING AND GRUBBING, REMOVAL OF BRIDGE, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE ROADWAY, TYPE IV GIRDER SPAN BRIDGE AND RELATED WORK. | |
| Estimated Construction Cost: $3,046,268.75 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $2,779,831.70 |
| 2 | 39462 | Jb James Construction Llc | $3,152,834.56 |
| 3 | 34567 | James Construction Group LLC | $3,198,344.20 |
| 4 | 01012 | Cecil D. Gassiott, LLC | $3,423,228.20 |
| 5 | 07740 | Cajun Constructors, Inc. | $3,426,309.70 |
| 6 | 00481 | Coastal Bridge Co., L.L.C. | $3,570,124.72 |
| 7 | 36827 | Shavers-Whittle Construction LLC | $4,274,094.90 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Jb James Construction Llc |
- 3 - James Construction Group LLC |
- 4 - Cecil D. Gassiott, LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 30,000.00 | 30,000.00 | 200,000.00 | 200,000.00 | 60,000.00 | 60,000.00 | 46,000.00 | 46,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 15,000.00 | 15,000.00 |
| 0003 | 202-02-02000 | Removal of Asphalt Drives | 130 | SQYD | 8.00 | 1,040.00 | 14.00 | 1,820.00 | 10.00 | 1,300.00 | 20.00 | 2,600.00 |
| 0004 | 202-02-02020 | Removal of Asphalt Pavement | 2,944.2 | SQYD | 4.00 | 11,776.80 | 5.00 | 14,721.00 | 5.00 | 14,721.00 | 5.00 | 14,721.00 |
| 0005 | 202-02-04000 | Removal of Bridge (Str. No. 08400530201471 (Sta. 122+03.22); 477.0' x 31.0' composite welded I-beam bridge) | 1 | EACH | 200,000.00 | 200,000.00 | 100,000.00 | 100,000.00 | 220,000.00 | 220,000.00 | 75,000.00 | 75,000.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,411.6 | SQYD | 6.00 | 8,469.60 | 6.00 | 8,469.60 | 5.00 | 7,058.00 | 7.00 | 9,881.20 |
| 0007 | 203-01-00100 | General Excavation | 221 | CUYD | 17.00 | 3,757.00 | 13.00 | 2,873.00 | 25.00 | 5,525.00 | 11.00 | 2,431.00 |
| 0008 | 203-02-00100 | Drainage Excavation | 3,117 | CUYD | 9.00 | 28,053.00 | 11.00 | 34,287.00 | 8.00 | 24,936.00 | 15.00 | 46,755.00 |
| 0009 | 203-03-00100 | Embankment | 1,800 | CUYD | 17.00 | 30,600.00 | 30.00 | 54,000.00 | 20.00 | 36,000.00 | 30.00 | 54,000.00 |
| 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 9 | EACH | 140.00 | 1,260.00 | 110.00 | 990.00 | 130.00 | 1,170.00 | 100.00 | 900.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 2,460 | LNFT | 1.40 | 3,444.00 | 2.00 | 4,920.00 | 2.50 | 6,150.00 | 2.00 | 4,920.00 |
| 0012 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,917.6 | SQYD | 20.00 | 98,352.00 | 24.00 | 118,022.40 | 20.00 | 98,352.00 | 30.00 | 147,528.00 |
| 0013 | 304-05-00100 | Lime Treatment (Type E) | 57.47 | TON | 150.00 | 8,620.50 | 50.00 | 2,873.50 | 300.00 | 17,241.00 | 200.00 | 11,494.00 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 15.00 | 750.00 | 75.00 | 3,750.00 | 50.00 | 2,500.00 | 85.00 | 4,250.00 |
| 0015 | 502-01-00100 | Superpave Asphaltic Concrete | 1,047.5 | TON | 90.00 | 94,275.00 | 98.00 | 102,655.00 | 96.00 | 100,560.00 | 110.00 | 115,225.00 |
| 0016 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 267.5 | TON | 100.00 | 26,750.00 | 120.00 | 32,100.00 | 115.00 | 30,762.50 | 135.00 | 36,112.50 |
| 0017 | 704-03-00100 | Blocked Out Guard Rail | 262.5 | LNFT | 20.00 | 5,250.00 | 18.00 | 4,725.00 | 18.00 | 4,725.00 | 19.00 | 4,987.50 |
| 0018 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 60.00 | 6,000.00 | 54.00 | 5,400.00 | 55.00 | 5,500.00 | 56.00 | 5,600.00 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 2,000.00 | 8,000.00 | 2,000.00 | 8,000.00 | 2,000.00 | 8,000.00 |
| 0020 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 920 | LNFT | 7.50 | 6,900.00 | 9.00 | 8,280.00 | 9.00 | 8,280.00 | 10.00 | 9,200.00 |
| 0021 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,045 | SQYD | 55.00 | 57,475.00 | 51.00 | 53,295.00 | 50.00 | 52,250.00 | 55.00 | 57,475.00 |
| 0022 | 711-04-00100 | Geotextile Fabric | 1,045 | SQYD | 1.80 | 1,881.00 | 3.00 | 3,135.00 | 3.10 | 3,239.50 | 5.00 | 5,225.00 |
| 0023 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,000.00 | 9,000.00 | 20,000.00 | 20,000.00 | 7,000.00 | 7,000.00 | 25,000.00 | 25,000.00 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 15 | TON | 550.00 | 8,250.00 | 650.00 | 9,750.00 | 650.00 | 9,750.00 | 550.00 | 8,250.00 |
| 0025 | 717-01-00100 | Seeding | 600 | LB | 7.50 | 4,500.00 | 5.00 | 3,000.00 | 5.00 | 3,000.00 | 7.50 | 4,500.00 |
| 0026 | 718-01-00100 | Fertilizer | 7,500 | LB | 0.50 | 3,750.00 | 0.70 | 5,250.00 | 0.70 | 5,250.00 | 0.50 | 3,750.00 |
| 0027 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 | 7,000.00 | 7,000.00 | 35,000.00 | 35,000.00 |
| 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 260,000.00 | 260,000.00 | 300,000.00 | 300,000.00 | 310,000.00 | 310,000.00 | 200,000.00 | 200,000.00 |
| 0029 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | 75.00 | 300.00 | 75.00 | 300.00 | 75.00 | 300.00 |
| 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 36 | EACH | 5.90 | 212.40 | 10.00 | 360.00 | 10.00 | 360.00 | 10.00 | 360.00 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.53 | MILE | 3,100.00 | 1,643.00 | 5,500.00 | 2,915.00 | 5,500.00 | 2,915.00 | 6,000.00 | 3,180.00 |
| 0032 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.265 | MILE | 1,100.00 | 291.50 | 3,100.00 | 821.50 | 3,000.00 | 795.00 | 3,200.00 | 848.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 12,000.00 | 12,000.00 | 12,500.00 | 12,500.00 |
| 0034 | 804-01-00200 | Precast Concrete Piles (14") | 80 | LNFT | 55.00 | 4,400.00 | 80.00 | 6,400.00 | 140.00 | 11,200.00 | 175.00 | 14,000.00 |
| 0035 | 804-01-00600 | Precast Concrete Piles (24") | 1,580 | LNFT | 78.00 | 123,240.00 | 84.00 | 132,720.00 | 100.00 | 158,000.00 | 100.00 | 158,000.00 |
| 0036 | 804-01-00700 | Precast Concrete Piles (30") | 2,790 | LNFT | 115.00 | 320,850.00 | 108.00 | 301,320.00 | 150.00 | 418,500.00 | 155.00 | 432,450.00 |
| 0037 | 804-05-00700 | Precast Concrete Test Piles (30") | 1 | EACH | 55,000.00 | 55,000.00 | 65,000.00 | 65,000.00 | 75,000.00 | 75,000.00 | 20,000.00 | 20,000.00 |
| 0038 | 804-09-00100 | Loading Test Piles | 1 | EACH | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 |
| 0039 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 5,000.00 | 5,000.00 | 100.00 | 100.00 | 2,000.00 | 2,000.00 | 1,000.00 | 1,000.00 |
| 0040 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1,000.00 | 1,000.00 | 100.00 | 100.00 | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 |
| 0041 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,000.00 | 1,000.00 | 100.00 | 100.00 | 5,000.00 | 5,000.00 | 1,000.00 | 1,000.00 |
| 0042 | 804-17-00100 | Dynamic Monitoring | 7 | EACH | 650.00 | 4,550.00 | 1,000.00 | 7,000.00 | 1,200.00 | 8,400.00 | 5,200.00 | 36,400.00 |
| 0043 | 805-01-00700 | Class A Concrete (Bents) | 187.93 | CUYD | 800.00 | 150,344.00 | 820.00 | 154,102.60 | 800.00 | 150,344.00 | 1,300.00 | 244,309.00 |
| 0044 | 805-04-00100 | Class AA(M) Concrete | 695.3 | CUYD | 485.00 | 337,220.50 | 575.00 | 399,797.50 | 550.00 | 382,415.00 | 900.00 | 625,770.00 |
| 0045 | 805-08-00400 | Precast-Prestressed Concrete Girder (Type IV) | 2,985 | LNFT | 120.00 | 358,200.00 | 150.00 | 447,750.00 | 160.00 | 477,600.00 | 136.00 | 405,960.00 |
| 0046 | 805-11-00100 | Strip Seal Joints | 176 | LNFT | 150.00 | 26,400.00 | 175.00 | 30,800.00 | 135.00 | 23,760.00 | 135.00 | 23,760.00 |
| 0047 | 806-01-00100 | Deformed Reinforcing Steel | 314,859 | LB | 0.80 | 251,887.20 | 0.94 | 295,967.46 | 0.80 | 251,887.20 | 1.00 | 314,859.00 |
| 0048 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | 7,500.00 | 7,500.00 | 5,600.00 | 5,600.00 |
| 0049 | 810-01-00100 | Concrete Railing (Standard Barrier) | 296 | LNFT | 60.00 | 17,760.00 | 63.00 | 18,648.00 | 65.00 | 19,240.00 | 65.00 | 19,240.00 |
| 0050 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 800 | LNFT | 65.00 | 52,000.00 | 62.00 | 49,600.00 | 45.00 | 36,000.00 | 72.00 | 57,600.00 |
| 0051 | 813-01-00100 | Concrete Approach Slabs | 400 | SQYD | 200.00 | 80,000.00 | 200.00 | 80,000.00 | 200.00 | 80,000.00 | 200.00 | 80,000.00 |
| 0052 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 858 | INLF | 2.40 | 2,059.20 | 2.00 | 1,716.00 | 1.00 | 858.00 | 1.50 | 1,287.00 |
| CONTRACTOR TOTAL | 2,779,831.70 | 3,152,834.56 | 3,198,344.20 | 3,423,228.20 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Cajun Constructors, Inc. |
- 6 - Coastal Bridge Co., L.L.C. |
- 7 - Shavers-Whittle Construction LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 35,000.00 | 35,000.00 | 160,000.00 | 160,000.00 | 60,000.00 | 60,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 40,000.00 | 40,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-02000 | Removal of Asphalt Drives | 130 | SQYD | 5.00 | 650.00 | 5.00 | 650.00 | 8.00 | 1,040.00 |
| 0004 | 202-02-02020 | Removal of Asphalt Pavement | 2,944.2 | SQYD | 6.25 | 18,401.25 | 5.00 | 14,721.00 | 8.00 | 23,553.60 |
| 0005 | 202-02-04000 | Removal of Bridge (Str. No. 08400530201471 (Sta. 122+03.22); 477.0' x 31.0' composite welded I-beam bridge) | 1 | EACH | 120,000.00 | 120,000.00 | 170,000.00 | 170,000.00 | 165,000.00 | 165,000.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 1,411.6 | SQYD | 6.00 | 8,469.60 | 5.00 | 7,058.00 | 4.00 | 5,646.40 |
| 0007 | 203-01-00100 | General Excavation | 221 | CUYD | 4.25 | 939.25 | 23.00 | 5,083.00 | 11.00 | 2,431.00 |
| 0008 | 203-02-00100 | Drainage Excavation | 3,117 | CUYD | 20.00 | 62,340.00 | 16.00 | 49,872.00 | 9.50 | 29,611.50 |
| 0009 | 203-03-00100 | Embankment | 1,800 | CUYD | 18.00 | 32,400.00 | 25.50 | 45,900.00 | 20.00 | 36,000.00 |
| 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 9 | EACH | 125.00 | 1,125.00 | 112.00 | 1,008.00 | 125.00 | 1,125.00 |
| 0011 | 204-06-00100 | Temporary Silt Fencing | 2,460 | LNFT | 1.50 | 3,690.00 | 1.50 | 3,690.00 | 1.50 | 3,690.00 |
| 0012 | 302-02-05121 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,917.6 | SQYD | 21.00 | 103,269.60 | 29.00 | 142,610.40 | 16.50 | 81,140.40 |
| 0013 | 304-05-00100 | Lime Treatment (Type E) | 57.47 | TON | 350.00 | 20,114.50 | 450.00 | 25,861.50 | 50.00 | 2,873.50 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 50 | CUYD | 65.00 | 3,250.00 | 80.00 | 4,000.00 | 50.00 | 2,500.00 |
| 0015 | 502-01-00100 | Superpave Asphaltic Concrete | 1,047.5 | TON | 105.00 | 109,987.50 | 110.00 | 115,225.00 | 135.00 | 141,412.50 |
| 0016 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 267.5 | TON | 125.00 | 33,437.50 | 127.00 | 33,972.50 | 150.00 | 40,125.00 |
| 0017 | 704-03-00100 | Blocked Out Guard Rail | 262.5 | LNFT | 18.00 | 4,725.00 | 20.50 | 5,381.25 | 25.00 | 6,562.50 |
| 0018 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 54.00 | 5,400.00 | 51.00 | 5,100.00 | 60.00 | 6,000.00 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,300.00 | 9,200.00 | 2,350.00 | 9,400.00 | 2,800.00 | 11,200.00 |
| 0020 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 920 | LNFT | 9.50 | 8,740.00 | 9.00 | 8,280.00 | 10.00 | 9,200.00 |
| 0021 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,045 | SQYD | 55.00 | 57,475.00 | 48.00 | 50,160.00 | 65.00 | 67,925.00 |
| 0022 | 711-04-00100 | Geotextile Fabric | 1,045 | SQYD | 3.50 | 3,657.50 | 2.75 | 2,873.75 | 3.00 | 3,135.00 |
| 0023 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 15 | TON | 650.00 | 9,750.00 | 650.00 | 9,750.00 | 750.00 | 11,250.00 |
| 0025 | 717-01-00100 | Seeding | 600 | LB | 5.00 | 3,000.00 | 5.00 | 3,000.00 | 6.00 | 3,600.00 |
| 0026 | 718-01-00100 | Fertilizer | 7,500 | LB | 0.69 | 5,175.00 | 0.70 | 5,250.00 | 0.75 | 5,625.00 |
| 0027 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 |
| 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 334,765.00 | 334,765.00 | 355,000.00 | 355,000.00 | 350,000.00 | 350,000.00 |
| 0029 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 75.00 | 300.00 | 75.00 | 300.00 | 90.00 | 360.00 |
| 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 36 | EACH | 10.00 | 360.00 | 10.00 | 360.00 | 12.00 | 432.00 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.53 | MILE | 5,500.00 | 2,915.00 | 5,600.00 | 2,968.00 | 6,500.00 | 3,445.00 |
| 0032 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.265 | MILE | 3,000.00 | 795.00 | 3,000.00 | 795.00 | 3,800.00 | 1,007.00 |
| 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0034 | 804-01-00200 | Precast Concrete Piles (14") | 80 | LNFT | 70.00 | 5,600.00 | 105.00 | 8,400.00 | 150.00 | 12,000.00 |
| 0035 | 804-01-00600 | Precast Concrete Piles (24") | 1,580 | LNFT | 113.00 | 178,540.00 | 85.00 | 134,300.00 | 165.00 | 260,700.00 |
| 0036 | 804-01-00700 | Precast Concrete Piles (30") | 2,790 | LNFT | 184.00 | 513,360.00 | 125.00 | 348,750.00 | 220.00 | 613,800.00 |
| 0037 | 804-05-00700 | Precast Concrete Test Piles (30") | 1 | EACH | 42,000.00 | 42,000.00 | 28,500.00 | 28,500.00 | 50,000.00 | 50,000.00 |
| 0038 | 804-09-00100 | Loading Test Piles | 1 | EACH | 21,000.00 | 21,000.00 | 45,000.00 | 45,000.00 | 20,000.00 | 20,000.00 |
| 0039 | 804-10-00100 | Reloading Test Piles | 1 | EACH | 1,500.00 | 1,500.00 | 100.00 | 100.00 | 2,500.00 | 2,500.00 |
| 0040 | 804-11-00100 | Redriving Test Piles | 1 | EACH | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 | 500.00 | 500.00 |
| 0041 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 1,500.00 | 1,500.00 | 100.00 | 100.00 | 500.00 | 500.00 |
| 0042 | 804-17-00100 | Dynamic Monitoring | 7 | EACH | 2,500.00 | 17,500.00 | 1,000.00 | 7,000.00 | 1,400.00 | 9,800.00 |
| 0043 | 805-01-00700 | Class A Concrete (Bents) | 187.93 | CUYD | 850.00 | 159,740.50 | 950.00 | 178,533.50 | 1,300.00 | 244,309.00 |
| 0044 | 805-04-00100 | Class AA(M) Concrete | 695.3 | CUYD | 625.00 | 434,562.50 | 750.00 | 521,475.00 | 1,000.00 | 695,300.00 |
| 0045 | 805-08-00400 | Precast-Prestressed Concrete Girder (Type IV) | 2,985 | LNFT | 163.00 | 486,555.00 | 140.00 | 417,900.00 | 195.00 | 582,075.00 |
| 0046 | 805-11-00100 | Strip Seal Joints | 176 | LNFT | 190.00 | 33,440.00 | 230.00 | 40,480.00 | 180.00 | 31,680.00 |
| 0047 | 806-01-00100 | Deformed Reinforcing Steel | 314,859 | LB | 1.00 | 314,859.00 | 0.98 | 308,561.82 | 1.00 | 314,859.00 |
| 0048 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 4,000.00 | 4,000.00 | 16,000.00 | 16,000.00 | 35,000.00 | 35,000.00 |
| 0049 | 810-01-00100 | Concrete Railing (Standard Barrier) | 296 | LNFT | 56.00 | 16,576.00 | 58.00 | 17,168.00 | 80.00 | 23,680.00 |
| 0050 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 800 | LNFT | 62.00 | 49,600.00 | 63.50 | 50,800.00 | 75.00 | 60,000.00 |
| 0051 | 813-01-00100 | Concrete Approach Slabs | 400 | SQYD | 195.00 | 78,000.00 | 200.00 | 80,000.00 | 250.00 | 100,000.00 |
| 0052 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 858 | INLF | 2.50 | 2,145.00 | 1.50 | 1,287.00 | 1.75 | 1,501.50 |
| CONTRACTOR TOTAL | 3,426,309.70 | 3,570,124.72 | 4,274,094.90 | |||||||