LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: H.001266.6
Parish: Rapides
Routes: LA 1
Description: STREET IMPROVEMENTS FOR THE CITY OF ALEXANDRIA
Type Const: GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost: $6,919,317.48


RankLicenseBidderConstruction Bid
1 12312 Gilchrist Construction Co. LLC $5,641,018.45
2 30774 Progressive Construction Co., LLC $5,710,071.14
3 12487 Diamond B Construction Co., L.L.C. $6,155,626.78
4 21982 Forby Contracting, Inc. $6,292,304.05
5 05789 D & J Construction Co., Inc. $6,978,967.75


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Gilchrist Construction Co. LLC
- 2 -
Progressive Construction Co., LLC
- 3 -
Diamond B Construction Co., L.L.C.
- 4 -
Forby Contracting, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-01-00100 Removal of Structures and Obstructions 1      LUMP 10,000.00 10,000.00 15,000.00 15,000.00 25,000.00 25,000.00 5,000.00 5,000.00
0002 202-02-06080 Removal of Concrete Combination Curb and Gutter 360      LNFT 15.00 5,400.00 8.50 3,060.00 9.00 3,240.00 10.00 3,600.00
0003 202-02-06100 Removal of Concrete Walks and Drives 231      SQYD 15.00 3,465.00 10.00 2,310.00 11.00 2,541.00 10.00 2,310.00
0004 202-02-06140 Removal of Curbs (Concrete) 6,790      LNFT 3.50 23,765.00 2.50 16,975.00 2.75 18,672.50 3.50 23,765.00
0005 202-02-32120 Removal of Pipe (Side Drain) (Various locations along Chester Street) 225      LNFT 25.00 5,625.00 12.00 2,700.00 13.00 2,925.00 20.00 4,500.00
0006 203-01-00100 General Excavation 3,062      CUYD 26.00 79,612.00 10.00 30,620.00 11.00 33,682.00 25.00 76,550.00
0007 203-07-00100 Borrow (Vehicular Measurement) 900      CUYD 25.00 22,500.00 25.00 22,500.00 25.00 22,500.00 25.00 22,500.00
0008 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 900      CUYD 25.00 22,500.00 25.00 22,500.00 25.00 22,500.00 16.00 14,400.00
0009 302-02-03100 Class II Base Course (8" Thick) (Stone) 13,717      SQYD 28.00 384,076.00 19.00 260,623.00 20.00 274,340.00 25.00 342,925.00
0010 304-01-00100 Lime 150.6    TON 185.00 27,861.00 200.00 30,120.00 190.00 28,614.00 180.00 27,108.00
0011 304-04-00400 Lime Treatment (Type D) (12" Thick) 21,707      SQYD 1.40 30,389.80 5.60 121,559.20 5.25 113,961.75 5.25 113,961.75
0012 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 28,089      SQYD 6.35 178,365.15 8.80 247,183.20 9.00 252,801.00 8.25 231,734.25
0013 308-02-00100 Removal of Existing Patches 700      SQYD 5.00 3,500.00 14.50 10,150.00 16.00 11,200.00 16.00 11,200.00
0014 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 1,355      CUYD 35.00 47,425.00 85.00 115,175.00 27.00 36,585.00 45.00 60,975.00
0015 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 235      CUYD 25.00 5,875.00 67.00 15,745.00 27.00 6,345.00 75.00 17,625.00
0016 502-01-00100 Superpave Asphaltic Concrete 18,334.8    TON 83.50 1,530,955.80 90.00 1,650,132.00 86.00 1,576,792.80 98.00 1,796,810.40
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,569      TON 190.00 298,110.00 122.00 191,418.00 180.00 282,420.00 152.00 238,488.00
0018 509-01-00100 Cold Planing Asphaltic Pavement 102,615      SQYD 1.40 143,661.00 2.25 230,883.75 3.50 359,152.50 3.25 333,498.75
0019 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -5,686      CUYD 1.00 -5,686.00 0.10 -568.60 0.10 -568.60 0.10 -568.60
0020 510-01-00200 Pavement Patching (12" Minimum Thickness) 1,240      SQYD 97.00 120,280.00 75.00 93,000.00 120.00 148,800.00 150.00 186,000.00
0021 510-02-00100 Pavement Widening 1,322      SQYD 50.00 66,100.00 58.00 76,676.00 11.50 15,203.00 65.00 85,930.00
0022 602-02-00100 Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints 32,069      LNFT 1.60 51,310.40 2.00 64,138.00 1.55 49,706.95 1.50 48,103.50
0023 602-03-00100 Cleaning and Sealing Random cracks 9,300      LNFT 2.75 25,575.00 2.50 23,250.00 3.00 27,900.00 2.50 23,250.00
0024 602-05-01120 Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) 468      SQYD 195.00 91,260.00 160.00 74,880.00 170.00 79,560.00 125.00 58,500.00
0025 602-05-02120 Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) 2,017      SQYD 115.00 231,955.00 95.00 191,615.00 105.00 211,785.00 115.00 231,955.00
0026 602-05-03120 Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) 11,521      SQYD 98.00 1,129,058.00 85.00 979,285.00 95.00 1,094,495.00 95.00 1,094,495.00
0027 701-01-02140 Cross Drain Pipe (42" RCP/PP or 54" CMP) 48      LNFT 185.00 8,880.00 317.00 15,216.00 325.00 15,600.00 190.00 9,120.00
0028 701-02-01000 Cross Drain Pipe Arch (24" Equiv. RCPA) 134      LNFT 135.00 18,090.00 115.00 15,410.00 125.00 16,750.00 120.00 16,080.00
0029 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 96      LNFT 76.00 7,296.00 88.75 8,520.00 85.00 8,160.00 120.00 11,520.00
0030 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 32      LNFT 125.00 4,000.00 148.00 4,736.00 155.00 4,960.00 175.00 5,600.00
0031 701-14-00100 Cleaning Existing Pipes 300      LNFT 20.00 6,000.00 13.75 4,125.00 15.00 4,500.00 18.00 5,400.00
0032 701-15-00100 Concrete Collar 3      EACH 900.00 2,700.00 1,050.00 3,150.00 1,100.00 3,300.00 750.00 2,250.00
0033 702-03-00001 Catch Basin (Remove and Replace Frame and Cover) 1      EACH 1,000.00 1,000.00 1,900.00 1,900.00 2,100.00 2,100.00 2,500.00 2,500.00
0034 702-04-00100 Adjusting Manholes 29      EACH 1,000.00 29,000.00 1,500.00 43,500.00 1,600.00 46,400.00 500.00 14,500.00
0035 702-04-00150 Adjusting Manholes w/Manhole Adjustment Rings 6      EACH 750.00 4,500.00 870.00 5,220.00 925.00 5,550.00 320.00 1,920.00
0036 702-04-00200 Adjusting Catch Basins 30      EACH 950.00 28,500.00 2,250.00 67,500.00 2,400.00 72,000.00 1,050.00 31,500.00
0037 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 100      LNFT 54.00 5,400.00 55.00 5,500.00 52.00 5,200.00 50.00 5,000.00
0038 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 362      LNFT 43.00 15,566.00 44.00 15,928.00 43.00 15,566.00 40.00 14,480.00
0039 704-03-00100 Blocked Out Guard Rail 100      LNFT 21.00 2,100.00 22.00 2,200.00 21.00 2,100.00 20.00 2,000.00
0040 704-11-00100 Guard Rail End Treatment (Flared) 8      EACH 2,300.00 18,400.00 2,300.00 18,400.00 2,200.00 17,600.00 2,100.00 16,800.00
0041 706-02-00200 Concrete Drive (6" Thick) 510      SQYD 75.00 38,250.00 65.00 33,150.00 70.00 35,700.00 75.00 38,250.00
0042 707-01-00100 Concrete Curb 6,358      LNFT 13.00 82,654.00 12.00 76,296.00 13.00 82,654.00 15.00 95,370.00
0043 707-03-00100 Combination Concrete Curb and Gutter 360      LNFT 35.00 12,600.00 37.00 13,320.00 42.00 15,120.00 35.00 12,600.00
0044 711-04-00100 Geotextile Fabric 430      SQYD 2.35 1,010.50 2.00 860.00 2.10 903.00 2.50 1,075.00
0045 713-01-00100 Temporary Signs and Barricades 1      LUMP 45,000.00 45,000.00 82,000.00 82,000.00 55,000.00 55,000.00 170,000.00 170,000.00
0046 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 9.698  MILE 350.00 3,394.30 330.00 3,200.34 160.00 1,551.68 500.00 4,849.00
0047 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 18.59   MILE 100.00 1,859.00 330.00 6,134.70 310.00 5,762.90 300.00 5,577.00
0048 720-01-01000 Erosion Control System (Slope Protection) (Type A) 1,500      SQYD 1.15 1,725.00 1.75 2,625.00 1.10 1,650.00 1.60 2,400.00
0049 726-01-00100 Bedding Material 105      CUYD 90.00 9,450.00 83.00 8,715.00 85.00 8,925.00 75.00 7,875.00
0050 727-01-00100 Mobilization 1      LUMP 325,000.00 325,000.00 260,000.00 260,000.00 564,000.00 564,000.00 350,000.00 350,000.00
0051 729-16-00200 Object Marker Assembly (Type 2) 20      EACH 70.00 1,400.00 88.00 1,760.00 70.00 1,400.00 65.00 1,300.00
0052 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 80.00 640.00 88.00 704.00 80.00 640.00 75.00 600.00
0053 731-02-00100 Reflectorized Raised Pavement Markers 1,570      EACH 5.85 9,184.50 5.00 7,850.00 5.00 7,850.00 4.50 7,065.00
0054 732-01-01020 Plastic Pavement Striping (6" Width) (Thermoplastic 90 mil) 2,000      LNFT 1.15 2,300.00 1.00 2,000.00 0.80 1,600.00 0.75 1,500.00
0055 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 2,000      LNFT 1.50 3,000.00 1.10 2,200.00 1.10 2,200.00 1.00 2,000.00
0056 732-01-02060 Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) 3,090      LNFT 2.75 8,497.50 5.00 15,450.00 5.00 15,450.00 4.50 13,905.00
0057 732-01-02080 Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 1,271      LNFT 5.50 6,990.50 5.00 6,355.00 5.00 6,355.00 4.50 5,719.50
0058 732-01-04080 Plastic Pavement Striping (24" Width) (Preformed Retroreflective Thermoplastic) (Heat Applied) (125 mil) 1,110      LNFT 16.00 17,760.00 17.50 19,425.00 16.00 17,760.00 15.00 16,650.00
0059 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 29.044  MILE 2,700.00 78,418.80 2,860.00 83,065.84 2,700.00 78,418.80 2,600.00 75,514.40
0060 732-02-03000 Plastic Pavement Striping (Solid Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) 12.611  MILE 11,400.00 143,765.40 14,520.00 183,111.72 14,000.00 176,554.00 13,200.00 166,465.20
0061 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 3.898  MILE 950.00 3,703.10 880.00 3,430.24 850.00 3,313.30 800.00 3,118.40
0062 732-03-02030 Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 1.5    MILE 3,300.00 4,950.00 4,365.00 6,547.50 4,200.00 6,300.00 3,960.00 5,940.00
0063 732-03-03000 Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) 2.17   MILE 4,700.00 10,199.00 3,630.00 7,877.10 3,500.00 7,595.00 3,300.00 7,161.00
0064 732-04-01020 Plastic Pavement Legends and Symbols (Arrow - Straight) 52      EACH 215.00 11,180.00 220.00 11,440.00 210.00 10,920.00 200.00 10,400.00
0065 732-04-01040 Plastic Pavement Legends and Symbols (Arrow - Double) 16      EACH 290.00 4,640.00 220.00 3,520.00 210.00 3,360.00 200.00 3,200.00
0066 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 89      EACH 230.00 20,470.00 220.00 19,580.00 210.00 18,690.00 200.00 17,800.00
0067 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 76      EACH 230.00 17,480.00 220.00 16,720.00 210.00 15,960.00 200.00 15,200.00
0068 732-04-02000 Plastic Pavement Legends and Symbols (Bicycle) 40      EACH 365.00 14,600.00 220.00 8,800.00 210.00 8,400.00 200.00 8,000.00
0069 732-04-04000 Plastic Pavement Legends and Symbols (Diamond) 12      EACH 225.00 2,700.00 220.00 2,640.00 210.00 2,520.00 200.00 2,400.00
0070 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 5      EACH 250.00 1,250.00 275.00 1,375.00 260.00 1,300.00 250.00 1,250.00
0071 735-01-00100 Mailboxes 32      EACH 75.00 2,400.00 1.20 38.40 1.00 32.00 10.00 320.00
0072 735-02-00100 Mailbox Supports (Single) 27      EACH 100.00 2,700.00 116.50 3,145.50 110.00 2,970.00 90.00 2,430.00
0073 735-03-00100 Mailbox Supports (Double) 1      EACH 135.00 135.00 141.00 141.00 125.00 125.00 120.00 120.00
0074 735-04-00100 Mailbox Supports (Multiple) 1      EACH 300.00 300.00 223.50 223.50 200.00 200.00 195.00 195.00
0075 739-01-00100 Hydro-Seeding 4.07   ACRE 1,400.00 5,698.00 1,375.00 5,596.25 1,300.00 5,291.00 1,250.00 5,087.50
0076 740-01-00100 Construction Layout 1      LUMP 25,000.00 25,000.00 38,000.00 38,000.00 40,000.00 40,000.00 12,500.00 12,500.00
0077 741-11-00100 Adjusting Water Valve 8      EACH 1,000.00 8,000.00 250.00 2,000.00 300.00 2,400.00 150.00 1,200.00
0078 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 17,520      INLF 0.45 7,884.00 1.00 17,520.00 0.30 5,256.00 0.20 3,504.00
0079 NS-500-00360 Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement 32,150      INLF 0.35 11,252.50 1.25 40,187.50 0.30 9,645.00 0.30 9,645.00
0080 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 10,832      INLF 0.85 9,207.20 1.00 10,832.00 1.10 11,915.20 1.00 10,832.00
                         
    CONTRACTOR TOTAL       5,641,018.45   5,710,071.14   6,155,626.78   6,292,304.05



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
D & J Construction Co., Inc.
Unit PriceTotal
Amount
0001 202-01-00100 Removal of Structures and Obstructions 1      LUMP 3,000.00 3,000.00
0002 202-02-06080 Removal of Concrete Combination Curb and Gutter 360      LNFT 11.00 3,960.00
0003 202-02-06100 Removal of Concrete Walks and Drives 231      SQYD 11.00 2,541.00
0004 202-02-06140 Removal of Curbs (Concrete) 6,790      LNFT 4.00 27,160.00
0005 202-02-32120 Removal of Pipe (Side Drain) (Various locations along Chester Street) 225      LNFT 16.00 3,600.00
0006 203-01-00100 General Excavation 3,062      CUYD 26.00 79,612.00
0007 203-07-00100 Borrow (Vehicular Measurement) 900      CUYD 35.00 31,500.00
0008 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 900      CUYD 16.00 14,400.00
0009 302-02-03100 Class II Base Course (8" Thick) (Stone) 13,717      SQYD 30.00 411,510.00
0010 304-01-00100 Lime 150.6    TON 180.00 27,108.00
0011 304-04-00400 Lime Treatment (Type D) (12" Thick) 21,707      SQYD 5.50 119,388.50
0012 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 28,089      SQYD 11.00 308,979.00
0013 308-02-00100 Removal of Existing Patches 700      SQYD 16.00 11,200.00
0014 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 1,355      CUYD 35.00 47,425.00
0015 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 235      CUYD 70.00 16,450.00
0016 502-01-00100 Superpave Asphaltic Concrete 18,334.8    TON 98.00 1,796,810.40
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,569      TON 148.00 232,212.00
0018 509-01-00100 Cold Planing Asphaltic Pavement 102,615      SQYD 3.50 359,152.50
0019 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -5,686      CUYD 0.10 -568.60
0020 510-01-00200 Pavement Patching (12" Minimum Thickness) 1,240      SQYD 150.00 186,000.00
0021 510-02-00100 Pavement Widening 1,322      SQYD 65.00 85,930.00
0022 602-02-00100 Cleaning and Resealing Existing Longitudinal and Transverse Pavement Joints 32,069      LNFT 2.00 64,138.00
0023 602-03-00100 Cleaning and Sealing Random cracks 9,300      LNFT 3.00 27,900.00
0024 602-05-01120 Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) 468      SQYD 150.00 70,200.00
0025 602-05-02120 Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) 2,017      SQYD 140.00 282,380.00
0026 602-05-03120 Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) 11,521      SQYD 120.00 1,382,520.00
0027 701-01-02140 Cross Drain Pipe (42" RCP/PP or 54" CMP) 48      LNFT 250.00 12,000.00
0028 701-02-01000 Cross Drain Pipe Arch (24" Equiv. RCPA) 134      LNFT 150.00 20,100.00
0029 701-10-01060 Reinforced Concrete Pipe (Extension) (24") 96      LNFT 200.00 19,200.00
0030 701-10-01100 Reinforced Concrete Pipe (Extension) (36") 32      LNFT 250.00 8,000.00
0031 701-14-00100 Cleaning Existing Pipes 300      LNFT 15.00 4,500.00
0032 701-15-00100 Concrete Collar 3      EACH 1,200.00 3,600.00
0033 702-03-00001 Catch Basin (Remove and Replace Frame and Cover) 1      EACH 500.00 500.00
0034 702-04-00100 Adjusting Manholes 29      EACH 2,500.00 72,500.00
0035 702-04-00150 Adjusting Manholes w/Manhole Adjustment Rings 6      EACH 1,500.00 9,000.00
0036 702-04-00200 Adjusting Catch Basins 30      EACH 2,850.00 85,500.00
0037 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 100      LNFT 55.00 5,500.00
0038 704-01-01020 Guard Rail (Single Thrie Beam) (6'-3" post spacing) 362      LNFT 45.00 16,290.00
0039 704-03-00100 Blocked Out Guard Rail 100      LNFT 21.00 2,100.00
0040 704-11-00100 Guard Rail End Treatment (Flared) 8      EACH 2,200.00 17,600.00
0041 706-02-00200 Concrete Drive (6" Thick) 510      SQYD 76.00 38,760.00
0042 707-01-00100 Concrete Curb 6,358      LNFT 15.00 95,370.00
0043 707-03-00100 Combination Concrete Curb and Gutter 360      LNFT 40.00 14,400.00
0044 711-04-00100 Geotextile Fabric 430      SQYD 5.00 2,150.00
0045 713-01-00100 Temporary Signs and Barricades 1      LUMP 185,000.00 185,000.00
0046 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 9.698  MILE 225.00 2,182.05
0047 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 18.59   MILE 350.00 6,506.50
0048 720-01-01000 Erosion Control System (Slope Protection) (Type A) 1,500      SQYD 1.00 1,500.00
0049 726-01-00100 Bedding Material 105      CUYD 100.00 10,500.00
0050 727-01-00100 Mobilization 1      LUMP 280,000.00 280,000.00
0051 729-16-00200 Object Marker Assembly (Type 2) 20      EACH 100.00 2,000.00
0052 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 100.00 800.00
0053 731-02-00100 Reflectorized Raised Pavement Markers 1,570      EACH 7.00 10,990.00
0054 732-01-01020 Plastic Pavement Striping (6" Width) (Thermoplastic 90 mil) 2,000      LNFT 2.00 4,000.00
0055 732-01-01040 Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 2,000      LNFT 4.00 8,000.00
0056 732-01-02060 Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) 3,090      LNFT 5.00 15,450.00
0057 732-01-02080 Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 1,271      LNFT 6.00 7,626.00
0058 732-01-04080 Plastic Pavement Striping (24" Width) (Preformed Retroreflective Thermoplastic) (Heat Applied) (125 mil) 1,110      LNFT 15.00 16,650.00
0059 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 29.044  MILE 2,850.00 82,775.40
0060 732-02-03000 Plastic Pavement Striping (Solid Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) 12.611  MILE 12,000.00 151,332.00
0061 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 3.898  MILE 1,000.00 3,898.00
0062 732-03-02030 Plastic Pvmt Strip (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 1.5    MILE 5,000.00 7,500.00
0063 732-03-03000 Plastic Pavement Striping (Broken Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) 2.17   MILE 5,000.00 10,850.00
0064 732-04-01020 Plastic Pavement Legends and Symbols (Arrow - Straight) 52      EACH 300.00 15,600.00
0065 732-04-01040 Plastic Pavement Legends and Symbols (Arrow - Double) 16      EACH 300.00 4,800.00
0066 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 89      EACH 300.00 26,700.00
0067 732-04-01100 Plastic Pavement Legends and Symbols (Arrow - Right Turn) 76      EACH 300.00 22,800.00
0068 732-04-02000 Plastic Pavement Legends and Symbols (Bicycle) 40      EACH 400.00 16,000.00
0069 732-04-04000 Plastic Pavement Legends and Symbols (Diamond) 12      EACH 400.00 4,800.00
0070 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 5      EACH 400.00 2,000.00
0071 735-01-00100 Mailboxes 32      EACH 5.00 160.00
0072 735-02-00100 Mailbox Supports (Single) 27      EACH 125.00 3,375.00
0073 735-03-00100 Mailbox Supports (Double) 1      EACH 200.00 200.00
0074 735-04-00100 Mailbox Supports (Multiple) 1      EACH 300.00 300.00
0075 739-01-00100 Hydro-Seeding 4.07   ACRE 1,400.00 5,698.00
0076 740-01-00100 Construction Layout 1      LUMP 10,000.00 10,000.00
0077 741-11-00100 Adjusting Water Valve 8      EACH 1,000.00 8,000.00
0078 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 17,520      INLF 0.20 3,504.00
0079 NS-500-00360 Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement 32,150      INLF 0.30 9,645.00
0080 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 10,832      INLF 1.50 16,248.00
             
    CONTRACTOR TOTAL       6,978,967.75