Bid Tabulations
Letting of
07/11/2012
LA DOTD Headquarters
| Lead Project: H.001183.6 | |
| Parish: Orleans | |
| Routes: LA 46 | |
| Description: La 46 (St Claude)/St Roch Intersection Revitalization | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING AND RELATED WORK. | |
| Estimated Construction Cost: $91,017.40 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00935 | Fleming Construction Co., LLC | $119,923.20 |
| 2 | 54896 | Magee Excavation & Development LLC | $147,752.00 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $158,398.55 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Fleming Construction Co., LLC |
- 2 - Magee Excavation & Development LLC |
- 3 - Boh Bros. Construction Co., LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 380 | LNFT | 10.00 | 3,800.00 | 6.00 | 2,280.00 | 10.00 | 3,800.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 60 | SQYD | 25.00 | 1,500.00 | 11.75 | 705.00 | 15.00 | 900.00 |
| 0003 | 202-02-38500 | Removal of Surfacing and Stablized Base | 200 | SQYD | 15.00 | 3,000.00 | 17.60 | 3,520.00 | 17.00 | 3,400.00 |
| 0004 | 202-03-38000 | Relocation of Sign REQ'D RELOCATION OF HIGHWAY SIGNS AS DIRECTED BY PROJECT ENGINEER | 3 | EACH | 300.00 | 900.00 | 586.50 | 1,759.50 | 1,000.00 | 3,000.00 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement REQ'D COLD PLANING TO BE DONE AS DIRECTED BY PROJECT ENGINEER | 175 | SQYD | 40.00 | 7,000.00 | 23.46 | 4,105.50 | 15.00 | 2,625.00 |
| 0006 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 10 | SQYD | 200.00 | 2,000.00 | 293.85 | 2,938.50 | 200.00 | 2,000.00 |
| 0007 | 701-05-01000 | Side Drain Pipe (12" RCP/PP/CMP) | 8 | LNFT | 100.00 | 800.00 | 586.50 | 4,692.00 | 125.00 | 1,000.00 |
| 0008 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 1 | EACH | 2,500.00 | 2,500.00 | 1,173.00 | 1,173.00 | 1,000.00 | 1,000.00 |
| 0009 | 702-03-00500 | Catch Basins (CB-06) | 1 | EACH | 5,000.00 | 5,000.00 | 3,550.00 | 3,550.00 | 5,000.00 | 5,000.00 |
| 0010 | 702-04-00100 | Adjusting Manholes | 5 | EACH | 1,000.00 | 5,000.00 | 585.00 | 2,925.00 | 600.00 | 3,000.00 |
| 0011 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 335 | SQYD | 65.00 | 21,775.00 | 70.00 | 23,450.00 | 80.00 | 26,800.00 |
| 0012 | 706-04-00100 | Handicapped Curb Ramps | 10 | EACH | 2,000.00 | 20,000.00 | 900.00 | 9,000.00 | 2,500.00 | 25,000.00 |
| 0013 | 707-01-00200 | Concrete Curb (Barrier) | 430 | LNFT | 10.00 | 4,300.00 | 35.00 | 15,050.00 | 30.00 | 12,900.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,000.00 | 8,000.00 | 10,500.00 | 10,500.00 | 20,000.00 | 20,000.00 |
| 0015 | 713-02-00200 | Temporary Pavement Markings (6" Width) | 330 | LNFT | 0.30 | 99.00 | 1.20 | 396.00 | 0.50 | 165.00 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 350 | LNFT | 1.10 | 385.00 | 1.20 | 420.00 | 0.75 | 262.50 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.063 | MILE | 700.00 | 44.10 | 714.25 | 45.00 | 650.00 | 40.95 |
| 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 10,000.00 | 10,000.00 | 38,000.00 | 38,000.00 | 15,000.00 | 15,000.00 |
| 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 350 | LNFT | 5.00 | 1,750.00 | 9.50 | 3,325.00 | 9.00 | 3,150.00 |
| 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.063 | MILE | 10,000.00 | 630.00 | 5,865.00 | 369.50 | 5,500.00 | 346.50 |
| 0021 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 0.063 | MILE | 7,700.00 | 485.10 | 9,396.82 | 592.00 | 8,700.00 | 548.10 |
| 0022 | 732-03-02020 | Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) | 0.015 | MILE | 15,000.00 | 225.00 | 11,733.33 | 176.00 | 8,700.00 | 130.50 |
| 0023 | 732-04-02000 | Plastic Pavement Legends and Symbols (Bicycle) | 4 | EACH | 440.00 | 1,760.00 | 362.50 | 1,450.00 | 350.00 | 1,400.00 |
| 0024 | 732-05-00100 | Removal of Existing Markings | 0.1 | MILE | 15,000.00 | 1,500.00 | 2,500.00 | 250.00 | 11,000.00 | 1,100.00 |
| 0025 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 6,000.00 | 6,000.00 | 15,000.00 | 15,000.00 |
| 0026 | 741-06-00100 | Relocating Fire Hydrant | 1 | EACH | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 4,500.00 | 4,500.00 |
| 0027 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 1,050 | INLF | 1.00 | 1,050.00 | 1.00 | 1,050.00 | 1.00 | 1,050.00 |
| 0028 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,280 | INLF | 1.50 | 3,420.00 | 1.00 | 2,280.00 | 1.00 | 2,280.00 |
| 0029 | NS-SRP-00042 | Reset Street Names (Tile) | 10 | EACH | 700.00 | 7,000.00 | 475.00 | 4,750.00 | 300.00 | 3,000.00 |
| CONTRACTOR TOTAL | 119,923.20 | 147,752.00 | 158,398.55 | |||||||