Bid Tabulations
Letting of
06/27/2012
LA DOTD Headquarters
| Lead Project: H.001175.6 | |
| Parish: Caddo | |
| Routes: LA 169 | |
| Description: Soda Lake Canal Bridge | |
| Type Const: CLEARING AND GRUBBING, CLASS II BASE COURSE, LIME TREATMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE GIRDER SPAN BRIDGE AND RELATED WORK. | |
| Estimated Construction Cost: $1,587,187.92 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 39462 | Jb James Construction Llc | $1,653,407.75 |
| 2 | 12135 | Blount Bros. Construction, Inc. | $1,663,890.40 |
| 3 | 01012 | Cecil D. Gassiott, LLC | $1,736,364.40 |
| 4 | 00044 | Guinn Construction, LLC | $1,894,623.50 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Jb James Construction Llc |
- 2 - Blount Bros. Construction, Inc. |
- 3 - Cecil D. Gassiott, LLC |
- 4 - Guinn Construction, LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 75,000.00 | 75,000.00 | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 2,500.00 | 2,500.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge Sta. 112+31 to 113+45; 114' Long Timber Trestle Bridge; Str. No. 04090453103531 | 1 | EACH | 23,500.00 | 23,500.00 | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 | 22,000.00 | 22,000.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 620 | LNFT | 5.00 | 3,100.00 | 8.00 | 4,960.00 | 9.00 | 5,580.00 | 7.00 | 4,340.00 |
| 0005 | 202-02-38300 | Removal of Sign and U-Channel Post | 2 | EACH | 55.00 | 110.00 | 50.00 | 100.00 | 100.00 | 200.00 | 200.00 | 400.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 4,610 | SQYD | 5.00 | 23,050.00 | 6.00 | 27,660.00 | 8.00 | 36,880.00 | 6.00 | 27,660.00 |
| 0007 | 203-01-00100 | General Excavation | 868 | CUYD | 12.00 | 10,416.00 | 8.00 | 6,944.00 | 6.50 | 5,642.00 | 10.00 | 8,680.00 |
| 0008 | 203-02-00100 | Drainage Excavation | 630 | CUYD | 20.00 | 12,600.00 | 12.00 | 7,560.00 | 17.50 | 11,025.00 | 10.00 | 6,300.00 |
| 0009 | 203-03-00100 | Embankment | 13,653 | CUYD | 16.50 | 225,274.50 | 12.00 | 163,836.00 | 18.00 | 245,754.00 | 18.00 | 245,754.00 |
| 0010 | 203-08-00100 | Geotextile Fabric | 626 | SQYD | 2.00 | 1,252.00 | 3.00 | 1,878.00 | 4.00 | 2,504.00 | 5.00 | 3,130.00 |
| 0011 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 130.00 | 520.00 | 125.00 | 500.00 | 150.00 | 600.00 | 100.00 | 400.00 |
| 0012 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 5 | EACH | 400.00 | 2,000.00 | 400.00 | 2,000.00 | 375.00 | 1,875.00 | 1,000.00 | 5,000.00 |
| 0013 | 204-06-00100 | Temporary Silt Fencing | 3,000 | LNFT | 3.00 | 9,000.00 | 3.00 | 9,000.00 | 2.00 | 6,000.00 | 2.50 | 7,500.00 |
| 0014 | 302-02-03121 | Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 4,981.4 | SQYD | 22.00 | 109,590.80 | 21.00 | 104,609.40 | 23.00 | 114,572.20 | 19.00 | 94,646.60 |
| 0015 | 304-05-00100 | Lime Treatment (Type E) | 70.6 | TON | 350.00 | 24,710.00 | 300.00 | 21,180.00 | 150.00 | 10,590.00 | 425.00 | 30,005.00 |
| 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 188 | CUYD | 100.00 | 18,800.00 | 40.00 | 7,520.00 | 85.00 | 15,980.00 | 85.00 | 15,980.00 |
| 0017 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 95.00 | 9,500.00 | 45.00 | 4,500.00 | 90.00 | 9,000.00 | 75.00 | 7,500.00 |
| 0018 | 502-01-00100 | Superpave Asphaltic Concrete | 974.8 | TON | 150.00 | 146,220.00 | 120.00 | 116,976.00 | 165.00 | 160,842.00 | 225.00 | 219,330.00 |
| 0019 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4.2 | TON | 300.00 | 1,260.00 | 150.00 | 630.00 | 165.00 | 693.00 | 400.00 | 1,680.00 |
| 0020 | 701-05-01100 | Side Drain Pipe (36" RCP/PP/CMP) | 32 | LNFT | 100.00 | 3,200.00 | 90.00 | 2,880.00 | 170.00 | 5,440.00 | 200.00 | 6,400.00 |
| 0021 | 704-03-00100 | Blocked Out Guard Rail | 400 | LNFT | 19.00 | 7,600.00 | 30.00 | 12,000.00 | 21.00 | 8,400.00 | 25.00 | 10,000.00 |
| 0022 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 75.00 | 7,500.00 | 70.00 | 7,000.00 | 60.00 | 6,000.00 | 65.00 | 6,500.00 |
| 0023 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 2 | EACH | 2,300.00 | 4,600.00 | 3,000.00 | 6,000.00 | 2,700.00 | 5,400.00 | 3,000.00 | 6,000.00 |
| 0024 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 2,540 | LNFT | 8.00 | 20,320.00 | 10.00 | 25,400.00 | 8.00 | 20,320.00 | 15.00 | 38,100.00 |
| 0025 | 705-04-00100 | Single Swinging Driveway Gates | 2 | EACH | 800.00 | 1,600.00 | 700.00 | 1,400.00 | 800.00 | 1,600.00 | 1,000.00 | 2,000.00 |
| 0026 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 8 | SQYD | 150.00 | 1,200.00 | 45.00 | 360.00 | 210.00 | 1,680.00 | 200.00 | 1,600.00 |
| 0027 | 708-01-00100 | Right-of-Way Monument | 27 | EACH | 125.00 | 3,375.00 | 300.00 | 8,100.00 | 300.00 | 8,100.00 | 150.00 | 4,050.00 |
| 0028 | 708-02-00100 | Right-of-Way Monument Witness Post | 27 | EACH | 125.00 | 3,375.00 | 250.00 | 6,750.00 | 125.00 | 3,375.00 | 150.00 | 4,050.00 |
| 0029 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 61 | SQYD | 110.00 | 6,710.00 | 75.00 | 4,575.00 | 110.00 | 6,710.00 | 100.00 | 6,100.00 |
| 0030 | 712-04-00100 | Flexible Revetment | 779 | SQYD | 50.00 | 38,950.00 | 55.00 | 42,845.00 | 60.00 | 46,740.00 | 75.00 | 58,425.00 |
| 0031 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 9,000.00 | 9,000.00 | 20,000.00 | 20,000.00 | 14,000.00 | 14,000.00 |
| 0032 | 716-01-00100 | Mulch (Vegetative) | 0.45 | TON | 1,500.00 | 675.00 | 600.00 | 270.00 | 3,200.00 | 1,440.00 | 2,500.00 | 1,125.00 |
| 0033 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 21,827 | SQYD | 1.15 | 25,101.05 | 2.00 | 43,654.00 | 1.00 | 21,827.00 | 1.50 | 32,740.50 |
| 0034 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 5,000.00 | 5,000.00 | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 |
| 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 160,000.00 | 160,000.00 | 60,000.00 | 60,000.00 | 125,000.00 | 125,000.00 | 175,000.00 | 175,000.00 |
| 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 111.00 | 444.00 | 150.00 | 600.00 | 75.00 | 300.00 | 100.00 | 400.00 |
| 0037 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 64 | EACH | 25.00 | 1,600.00 | 10.00 | 640.00 | 10.00 | 640.00 | 20.00 | 1,280.00 |
| 0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | 40 | EACH | 25.00 | 1,000.00 | 10.00 | 400.00 | 10.00 | 400.00 | 125.00 | 5,000.00 |
| 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.436 | MILE | 3,600.00 | 1,569.60 | 10,000.00 | 4,360.00 | 3,500.00 | 1,526.00 | 12,500.00 | 5,450.00 |
| 0040 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.218 | MILE | 1,600.00 | 348.80 | 5,000.00 | 1,090.00 | 1,500.00 | 327.00 | 7,000.00 | 1,526.00 |
| 0041 | 739-01-00100 | Hydro-Seeding | 5.2 | ACRE | 1,200.00 | 6,240.00 | 1,500.00 | 7,800.00 | 1,500.00 | 7,800.00 | 1,500.00 | 7,800.00 |
| 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | 13,500.00 | 13,500.00 | 30,000.00 | 30,000.00 |
| 0043 | 804-01-00600 | Precast Concrete Piles (24") | 1,334 | LNFT | 120.00 | 160,080.00 | 180.00 | 240,120.00 | 135.00 | 180,090.00 | 158.00 | 210,772.00 |
| 0044 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 100.00 | 100.00 | 2,000.00 | 2,000.00 | 2,500.00 | 2,500.00 | 1.00 | 1.00 |
| 0045 | 805-01-00700 | Class A Concrete (Bents) | 57.34 | CUYD | 925.00 | 53,039.50 | 800.00 | 45,872.00 | 1,100.00 | 63,074.00 | 1,000.00 | 57,340.00 |
| 0046 | 805-04-00100 | Class AA(M) Concrete | 150.98 | CUYD | 900.00 | 135,882.00 | 750.00 | 113,235.00 | 1,200.00 | 181,176.00 | 850.00 | 128,333.00 |
| 0047 | 805-11-00100 | Strip Seal Joints | 64 | LNFT | 175.00 | 11,200.00 | 300.00 | 19,200.00 | 170.00 | 10,880.00 | 200.00 | 12,800.00 |
| 0048 | 806-01-00100 | Deformed Reinforcing Steel | 54,734 | LB | 1.00 | 54,734.00 | 2.00 | 109,468.00 | 1.00 | 54,734.00 | 1.10 | 60,207.40 |
| 0049 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 3,800.00 | 3,800.00 | 5,000.00 | 5,000.00 |
| 0050 | 810-01-00100 | Concrete Railing (Standard Barrier) | 320 | LNFT | 60.00 | 19,200.00 | 110.00 | 35,200.00 | 75.00 | 24,000.00 | 90.00 | 28,800.00 |
| 0051 | 813-01-00100 | Concrete Approach Slabs | 292.88 | SQYD | 200.00 | 58,576.00 | 300.00 | 87,864.00 | 240.00 | 70,291.20 | 250.00 | 73,220.00 |
| 0052 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 62 | LNFT | 20.00 | 1,240.00 | 20.00 | 1,240.00 | 5.00 | 310.00 | 30.00 | 1,860.00 |
| 0053 | NS-700-00240 | Special Guard Rail Anchor Section | 2 | EACH | 1,300.00 | 2,600.00 | 2,000.00 | 4,000.00 | 1,800.00 | 3,600.00 | 2,000.00 | 4,000.00 |
| 0054 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 0.436 | MILE | 18,000.00 | 7,848.00 | 1,500.00 | 654.00 | 14,000.00 | 6,104.00 | 18,000.00 | 7,848.00 |
| 0055 | NS-800-00182 | Precast Prestressed Concrete Girder (Type Quad Beam) Class P(HPC) | 960 | LNFT | 100.00 | 96,000.00 | 140.00 | 134,400.00 | 83.00 | 79,680.00 | 110.00 | 105,600.00 |
| 0056 | NS-800-00560 | Deformed Reinforcing Steel (Stainless Steel) | 3,066 | LB | 5.25 | 16,096.50 | 10.00 | 30,660.00 | 5.50 | 16,863.00 | 15.00 | 45,990.00 |
| CONTRACTOR TOTAL | 1,653,407.75 | 1,663,890.40 | 1,736,364.40 | 1,894,623.50 | ||||||||