Bid Tabulations
Letting of
01/09/2013
LA DOTD Headquarters
| Lead Project: H.001134.6 | |
| Parish: LaSalle | |
| Routes: LA 8 | |
| Description: LA 8: WHIITE SULPHUR SPRINGS - LA 3104 | |
| Type Const: ASPHALTIC SURFACE TREATMENT AND RELATED WORK. | |
| Estimated Construction Cost: $980,012.87 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 32934 | Vance Brothers Inc. | $920,483.89 |
| 2 | 14422 | T. L. Wallace Construction, Inc. | $972,909.29 |
| 3 | 05635 | Dreher Contracting, LLC | $1,246,127.17 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Vance Brothers Inc. |
- 2 - T. L. Wallace Construction, Inc. |
- 3 - Dreher Contracting, LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 59,174 | GAL | 3.10 | 183,439.40 | 3.55 | 210,067.70 | 3.50 | 207,109.00 |
| 0002 | 507-02-00200 | Aggregate (S2) | 144,317 | SQYD | 0.78 | 112,567.26 | 0.84 | 121,226.28 | 0.92 | 132,771.64 |
| 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 13,500.00 | 13,500.00 | 19,711.00 | 19,711.00 | 3,500.00 | 3,500.00 |
| 0004 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.527 | MILE | 0.01 | 0.14 | 150.00 | 2,029.05 | 450.00 | 6,087.15 |
| 0005 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.659 | MILE | 3.10 | 23.74 | 100.00 | 765.90 | 230.00 | 1,761.57 |
| 0006 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 43.351 | MILE | 302.50 | 13,113.68 | 150.00 | 6,502.65 | 330.00 | 14,305.83 |
| 0007 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,787 | EACH | 1.75 | 3,127.25 | 1.25 | 2,233.75 | 1.50 | 2,680.50 |
| 0008 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 19,711.00 | 19,711.00 | 100,000.00 | 100,000.00 |
| 0009 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,282 | EACH | 4.40 | 5,640.80 | 5.25 | 6,730.50 | 5.00 | 6,410.00 |
| 0010 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 21.677 | MILE | 2,420.00 | 52,458.34 | 2,300.00 | 49,857.10 | 2,600.00 | 56,360.20 |
| 0011 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.827 | MILE | 632.50 | 2,420.58 | 800.00 | 3,061.60 | 600.00 | 2,296.20 |
| 0012 | 732-05-00100 | Removal of Existing Markings For removal of Raised Pavement Markers Only | 6.764 | MILE | 1.10 | 7.44 | 100.00 | 676.40 | 300.00 | 2,029.20 |
| 0013 | NS-500-00380 | Micro-surfacing Aggregate | 2,238.3 | TON | 118.08 | 264,298.46 | 133.00 | 297,693.90 | 215.00 | 481,234.50 |
| 0014 | NS-500-00400 | Micro-surfacing Asphalt | 61,221.7 | GAL | 4.00 | 244,886.80 | 3.80 | 232,642.46 | 3.75 | 229,581.38 |
| CONTRACTOR TOTAL | 920,483.89 | 972,909.29 | 1,246,127.17 | |||||||