Bid Tabulations
Letting of
05/09/2012
LA DOTD Headquarters
| Lead Project: H.001090.6 | |
| Parish: Franklin | |
| Routes: LA 4 | |
| Description: LA 4: 2 M. EAST CALDWELL P/L - LA 562 | |
| Type Const: STABILIZE, ASPHALTIC CONCRETE OVERLAY & RELATED WORK | |
| Estimated Construction Cost: $2,663,598.72 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $2,482,594.98 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,587,518.92 |
| 3 | 05789 | D & J Construction Co., Inc. | $2,650,280.81 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - D & J Construction Co., Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing 5.2 acres | 1 | LUMP | 60,000.00 | 60,000.00 | 60,000.00 | 60,000.00 | 125,000.00 | 125,000.00 |
| 0002 | 202-02-06040 | Removal of Concrete Box Headwall STATION 37+64, STATION 58+44, STATION 77+52, STATION 139+36, STATION 146+33, STATION 265+38, STATION 286+09 | 12 | EACH | 225.00 | 2,700.00 | 225.00 | 2,700.00 | 900.00 | 10,800.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) STATION 51+61 | 12 | LNFT | 6.50 | 78.00 | 7.00 | 84.00 | 15.00 | 180.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 3,436 | CUYD | 16.00 | 54,976.00 | 17.00 | 58,412.00 | 15.00 | 51,540.00 |
| 0005 | 304-05-00100 | Lime Treatment (Type E) | 993.8 | TON | 325.00 | 322,985.00 | 3.65 | 3,627.37 | 330.00 | 327,954.00 |
| 0006 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 63,100 | SQYD | 5.80 | 365,980.00 | 8.25 | 520,575.00 | 7.80 | 492,180.00 |
| 0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,306 | CUYD | 34.00 | 44,404.00 | 100.00 | 130,600.00 | 16.00 | 20,896.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 11,759.2 | TON | 90.00 | 1,058,328.00 | 92.00 | 1,081,846.40 | 96.00 | 1,128,883.20 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 240.6 | TON | 190.00 | 45,714.00 | 200.00 | 48,120.00 | 115.00 | 27,669.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 50,480 | SQYD | 2.00 | 100,960.00 | 3.80 | 191,824.00 | 2.50 | 126,200.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,908 | CUYD | 2.00 | -9,816.00 | 0.10 | -490.80 | 0.10 | -490.80 |
| 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 16 | LNFT | 150.00 | 2,400.00 | 150.00 | 2,400.00 | 125.00 | 2,000.00 |
| 0013 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 8 | LNFT | 160.00 | 1,280.00 | 160.00 | 1,280.00 | 135.00 | 1,080.00 |
| 0014 | 701-15-00100 | Concrete Collar | 3 | EACH | 1,000.00 | 3,000.00 | 1,000.00 | 3,000.00 | 800.00 | 2,400.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 16,000.00 | 16,000.00 | 25,000.00 | 25,000.00 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.56 | MILE | 10.00 | 115.60 | 225.00 | 2,601.00 | 200.00 | 2,312.00 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 31.514 | MILE | 10.00 | 315.14 | 325.00 | 10,242.05 | 1.00 | 31.51 |
| 0018 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 |
| 0019 | 726-01-00100 | Bedding Material | 51.1 | CUYD | 110.00 | 5,621.00 | 115.00 | 5,876.50 | 110.00 | 5,621.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 165,000.00 | 165,000.00 | 225,750.00 | 225,750.00 | 50,000.00 | 50,000.00 |
| 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 569 | EACH | 7.50 | 4,267.50 | 5.00 | 2,845.00 | 5.00 | 2,845.00 |
| 0022 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.505 | MILE | 3,000.00 | 31,515.00 | 2,800.00 | 29,414.00 | 2,700.00 | 28,363.50 |
| 0023 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.853 | MILE | 900.00 | 3,467.70 | 800.00 | 3,082.40 | 800.00 | 3,082.40 |
| 0024 | 735-01-00100 | Mailboxes | 13 | EACH | 15.00 | 195.00 | 1.00 | 13.00 | 5.00 | 65.00 |
| 0025 | 735-02-00100 | Mailbox Supports (Single) | 11 | EACH | 110.00 | 1,210.00 | 125.00 | 1,375.00 | 135.00 | 1,485.00 |
| 0026 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 150.00 | 150.00 | 160.00 | 160.00 | 175.00 | 175.00 |
| 0027 | 739-01-00100 | Hydro-Seeding | 5 | ACRE | 1,200.00 | 6,000.00 | 1,100.00 | 5,500.00 | 1,100.00 | 5,500.00 |
| 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 6,000.00 | 6,000.00 | 10,000.00 | 10,000.00 |
| 0029 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 126.8 | CUYD | 1,000.00 | 126,800.00 | 1,000.00 | 126,800.00 | 1,100.00 | 139,480.00 |
| 0030 | 805-12-32000 | Reinforced Concrete Box Culverts (3' x 3') (Extension) | 38 | LNFT | 430.00 | 16,340.00 | 410.00 | 15,580.00 | 400.00 | 15,200.00 |
| 0031 | 805-12-32040 | Reinforced Concrete Box Culverts (5' x 3') (Extension) | 14 | LNFT | 560.00 | 7,840.00 | 550.00 | 7,700.00 | 400.00 | 5,600.00 |
| 0032 | 805-12-33000 | Reinforced Concrete Box Culverts (4' x 4') (Extension) | 4 | LNFT | 560.00 | 2,240.00 | 550.00 | 2,200.00 | 400.00 | 1,600.00 |
| 0033 | 805-12-35000 | Reinforced Concrete Box Culverts (6' x 6') (Extension) | 6 | LNFT | 675.00 | 4,050.00 | 650.00 | 3,900.00 | 650.00 | 3,900.00 |
| 0034 | 806-01-00100 | Deformed Reinforcing Steel | 9,168 | LB | 1.78 | 16,319.04 | 1.25 | 11,460.00 | 3.00 | 27,504.00 |
| 0035 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 4.3 | MILE | 1,200.00 | 5,160.00 | 940.00 | 4,042.00 | 750.00 | 3,225.00 |
| CONTRACTOR TOTAL | 2,482,594.98 | 2,587,518.92 | 2,650,280.81 | |||||||