Bid Tabulations
Letting of
05/15/2013
LA DOTD Headquarters
| Lead Project: H.001067.6 | |
| Parish: Natchitoches | |
| Routes: LA 1 | |
| Description: LA 1: SIBLEY LAKE - JCT. LA 3191 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,247,716.41 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12312 | Gilchrist Construction Co. LLC | $1,330,794.70 |
| 2 | 08584 | Madden Contracting Co., Inc. | $1,334,242.31 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Gilchrist Construction Co. LLC |
- 2 - Madden Contracting Co., Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 130 | SQYD | 18.00 | 2,340.00 | 15.00 | 1,950.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 384 | LNFT | 7.00 | 2,688.00 | 15.00 | 5,760.00 |
| 0003 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 7,862 | SQYD | 7.50 | 58,965.00 | 7.00 | 55,034.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 6,145 | SQYD | 5.00 | 30,725.00 | 6.20 | 38,099.00 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 500 | CUYD | 25.00 | 12,500.00 | 25.00 | 12,500.00 |
| 0007 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 200 | CUYD | 19.00 | 3,800.00 | 25.00 | 5,000.00 |
| 0008 | 303-01-00200 | In-Place Cement Stabilized Base Course (8 1/2" Thick) | 15,399 | SQYD | 7.30 | 112,412.70 | 10.00 | 153,990.00 |
| 0009 | 304-05-00100 | Lime Treatment (Type E) | 43.66 | TON | 475.00 | 20,738.50 | 910.00 | 39,730.60 |
| 0010 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 500 | CUYD | 20.00 | 10,000.00 | 30.00 | 15,000.00 |
| 0011 | 502-01-00100 | Superpave Asphaltic Concrete | 7,350.1 | TON | 91.50 | 672,534.15 | 95.00 | 698,259.50 |
| 0012 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 322.9 | TON | 135.00 | 43,591.50 | 125.00 | 40,362.50 |
| 0013 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 10,472 | GAL | 3.75 | 39,270.00 | 3.14 | 32,882.08 |
| 0014 | 507-02-00200 | Aggregate (S2) | 15,399 | SQYD | 2.05 | 31,567.95 | 1.49 | 22,944.51 |
| 0015 | 507-02-00300 | Aggregate (S3) | 15,399 | SQYD | 1.70 | 26,178.30 | 1.28 | 19,710.72 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 278 | SQYD | 16.00 | 4,448.00 | 10.00 | 2,780.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -6 | CUYD | 0.10 | -0.60 | 0.10 | -0.60 |
| 0018 | 602-05-02160 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9" Thick) | 54 | SQYD | 315.00 | 17,010.00 | 180.00 | 9,720.00 |
| 0019 | 704-03-00100 | Blocked Out Guard Rail | 143.8 | LNFT | 21.00 | 3,019.80 | 20.00 | 2,876.00 |
| 0020 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 66.00 | 6,600.00 | 65.00 | 6,500.00 |
| 0021 | 704-10-00100 | Guard Rail Anchor Block | 4 | EACH | 5,100.00 | 20,400.00 | 5,000.00 | 20,000.00 |
| 0022 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,200.00 | 8,800.00 | 2,100.00 | 8,400.00 |
| 0023 | 707-01-00100 | Concrete Curb | 40 | LNFT | 92.00 | 3,680.00 | 60.00 | 2,400.00 |
| 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 32,200.00 | 32,200.00 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1.6 | MILE | 300.00 | 480.00 | 400.00 | 640.00 |
| 0026 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.6 | MILE | 575.00 | 920.00 | 200.00 | 320.00 |
| 0027 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 5 | MILE | 610.00 | 3,050.00 | 400.00 | 2,000.00 |
| 0028 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 280 | EACH | 1.65 | 462.00 | 1.50 | 420.00 |
| 0029 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 5,000.00 | 5,000.00 | 2,000.00 | 2,000.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 130,000.00 | 130,000.00 | 32,200.00 | 32,200.00 |
| 0031 | 729-01-00100 | Sign (Type A) | 44 | SQFT | 23.00 | 1,012.00 | 22.00 | 968.00 |
| 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 78.00 | 312.00 | 76.00 | 304.00 |
| 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 200 | EACH | 6.25 | 1,250.00 | 4.50 | 900.00 |
| 0034 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 500 | LNFT | 1.40 | 700.00 | 1.00 | 500.00 |
| 0035 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 144 | LNFT | 2.60 | 374.40 | 1.50 | 216.00 |
| 0036 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 24 | LNFT | 5.25 | 126.00 | 4.00 | 96.00 |
| 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.05 | MILE | 3,100.00 | 3,255.00 | 2,500.00 | 2,625.00 |
| 0038 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.05 | MILE | 1,100.00 | 1,155.00 | 700.00 | 735.00 |
| 0039 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 9 | EACH | 220.00 | 1,980.00 | 200.00 | 1,800.00 |
| 0040 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 220.00 | 440.00 | 200.00 | 400.00 |
| 0041 | 732-05-00100 | Removal of Existing Markings | 0.2 | MILE | 5,100.00 | 1,020.00 | 2,000.00 | 400.00 |
| 0042 | 735-01-00100 | Mailboxes | 4 | EACH | 1.00 | 4.00 | 1.00 | 4.00 |
| 0043 | 735-02-00100 | Mailbox Supports (Single) | 3 | EACH | 110.00 | 330.00 | 250.00 | 750.00 |
| 0044 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 180.00 | 180.00 | 250.00 | 250.00 |
| 0045 | 739-01-00100 | Hydro-Seeding | 0.5 | ACRE | 2,600.00 | 1,300.00 | 4,000.00 | 2,000.00 |
| 0046 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,000.00 | 8,000.00 | 10,000.00 | 10,000.00 |
| 0047 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 1,000 | INLF | 2.40 | 2,400.00 | 5.00 | 5,000.00 |
| 0048 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,740 | INLF | 1.40 | 2,436.00 | 5.00 | 8,700.00 |
| 0049 | NS-713-00001 | Dynamic Message Sign Unit | 3 | EACH | 2,300.00 | 6,900.00 | 4,500.00 | 13,500.00 |
| 0050 | NS-729-00013 | Square Steel Tubular Sign Posts and Hardware (2" x 2")(2.23lb/ft) | 8 | EACH | 140.00 | 1,120.00 | 139.00 | 1,112.00 |
| 0051 | NS-729-00014 | Square Steel Tubular Sign Posts and Hardware (2 1/4" x 2 1/4") | 8 | EACH | 40.00 | 320.00 | 38.00 | 304.00 |
| CONTRACTOR TOTAL | 1,330,794.70 | 1,334,242.31 | ||||||