Bid Tabulations
Letting of
10/10/2012
LA DOTD Headquarters
| Lead Project: H.000735.6 | |
| Parish: Desoto | |
| Routes: LA 175, LA 513, US 84-B, | |
| Description: Mansfield Sidewalk Program, Phase I | |
| Type Const: CLEARING AND GRUBBING, GRADING CLASS II BASE COURSE, CONCRETE SIDEWALKS, AND RELATED WORK. | |
| Estimated Construction Cost: $419,050.53 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 28218 | F. J. Burnell, Inc. | $459,514.90 |
| 2 | 56298 | Cercontec, LLC | $496,940.65 |
| 3 | 40486 | Regional Construction, LLC | $498,079.40 |
| 4 | 49239 | WL Bass Construction Inc. | $540,542.10 |
| 5 | 30774 | Progressive Construction Co., LLC | $549,560.72 |
| 6 | 36374 | Best-Yet Builders, Llc | $652,858.90 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F. J. Burnell, Inc. |
- 2 - Cercontec, LLC |
- 3 - Regional Construction, LLC |
- 4 - WL Bass Construction Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 25,000.00 | 25,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 2,500.00 | 2,500.00 | 20,000.00 | 20,000.00 | 250.00 | 250.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 189.4 | SQYD | 10.00 | 1,894.00 | 6.58 | 1,246.25 | 10.00 | 1,894.00 | 6.00 | 1,136.40 |
| 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 151 | LNFT | 10.00 | 1,510.00 | 7.38 | 1,114.38 | 10.00 | 1,510.00 | 6.00 | 906.00 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | 81.2 | SQYD | 10.00 | 812.00 | 21.50 | 1,745.80 | 10.00 | 812.00 | 6.00 | 487.20 |
| 0006 | 202-03-38000 | Relocation of Sign Speed Limit | 1 | EACH | 250.00 | 250.00 | 450.00 | 450.00 | 150.00 | 150.00 | 250.00 | 250.00 |
| 0007 | 202-03-38000 | Relocation of Sign Yield | 1 | EACH | 250.00 | 250.00 | 450.00 | 450.00 | 150.00 | 150.00 | 250.00 | 250.00 |
| 0008 | 202-03-38000 | Relocation of Sign Street Sign | 2 | EACH | 250.00 | 500.00 | 450.00 | 900.00 | 150.00 | 300.00 | 250.00 | 500.00 |
| 0009 | 202-03-38000 | Relocation of Sign Yield Ahead | 2 | EACH | 250.00 | 500.00 | 450.00 | 900.00 | 150.00 | 300.00 | 250.00 | 500.00 |
| 0010 | 202-03-38000 | Relocation of Sign Wrong Way | 1 | EACH | 250.00 | 250.00 | 450.00 | 450.00 | 150.00 | 150.00 | 250.00 | 250.00 |
| 0011 | 202-03-38000 | Relocation of Sign Fiber Optic Locate | 5 | EACH | 250.00 | 1,250.00 | 450.00 | 2,250.00 | 100.00 | 500.00 | 250.00 | 1,250.00 |
| 0012 | 202-03-38000 | Relocation of Sign One Way | 1 | EACH | 250.00 | 250.00 | 450.00 | 450.00 | 150.00 | 150.00 | 250.00 | 250.00 |
| 0013 | 202-03-38000 | Relocation of Sign J & J BBQ | 1 | EACH | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 400.00 | 400.00 | 250.00 | 250.00 |
| 0014 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 6,500.00 | 6,500.00 | 35,000.00 | 35,000.00 | 15,000.00 | 15,000.00 |
| 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 40 | EACH | 15.00 | 600.00 | 27.50 | 1,100.00 | 50.00 | 2,000.00 | 20.00 | 800.00 |
| 0016 | 204-06-00100 | Temporary Silt Fencing | 9,250 | LNFT | 2.00 | 18,500.00 | 1.65 | 15,262.50 | 3.00 | 27,750.00 | 1.00 | 9,250.00 |
| 0017 | 302-02-01061 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 5,573.8 | SQYD | 10.00 | 55,738.00 | 10.00 | 55,738.00 | 14.00 | 78,033.20 | 15.00 | 83,607.00 |
| 0018 | 706-01-00100 | Concrete Walk (4" Thick) | 5,198.2 | SQYD | 40.00 | 207,928.00 | 51.00 | 265,108.20 | 36.00 | 187,135.20 | 65.00 | 337,883.00 |
| 0019 | 706-01-00300 | Concrete Walk (6" Thick) | 374.9 | SQYD | 46.00 | 17,245.40 | 65.00 | 24,368.50 | 50.00 | 18,745.00 | 75.00 | 28,117.50 |
| 0020 | 706-04-00100 | Handicapped Curb Ramps | 28 | EACH | 1,000.00 | 28,000.00 | 1,200.00 | 33,600.00 | 500.00 | 14,000.00 | 500.00 | 14,000.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 14,000.00 | 14,000.00 | 7,500.00 | 7,500.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 |
| 0023 | 739-01-00100 | Hydro-Seeding | 2.15 | ACRE | 2,500.00 | 5,375.00 | 1,250.00 | 2,687.50 | 3,000.00 | 6,450.00 | 1,500.00 | 3,225.00 |
| 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 3,500.00 | 3,500.00 | 14,000.00 | 14,000.00 | 3,500.00 | 3,500.00 |
| 0025 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 3,726 | INLF | 1.25 | 4,657.50 | 0.42 | 1,564.92 | 1.00 | 3,726.00 | 1.00 | 3,726.00 |
| 0026 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,524 | INLF | 1.25 | 1,905.00 | 1.65 | 2,514.60 | 1.00 | 1,524.00 | 1.00 | 1,524.00 |
| 0027 | NS-ENH-18040 | Retaining Walls Special Detail | 242 | LNFT | 50.00 | 12,100.00 | 120.00 | 29,040.00 | 200.00 | 48,400.00 | 15.00 | 3,630.00 |
| CONTRACTOR TOTAL | 459,514.90 | 496,940.65 | 498,079.40 | 540,542.10 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Progressive Construction Co., LLC |
- 6 - Best-Yet Builders, Llc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 50,000.00 | 50,000.00 |
| 0003 | 202-02-02020 | Removal of Asphalt Pavement | 189.4 | SQYD | 9.00 | 1,704.60 | 52.00 | 9,848.80 |
| 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 151 | LNFT | 5.00 | 755.00 | 50.00 | 7,550.00 |
| 0005 | 202-02-06100 | Removal of Concrete Walks and Drives | 81.2 | SQYD | 9.00 | 730.80 | 50.00 | 4,060.00 |
| 0006 | 202-03-38000 | Relocation of Sign Speed Limit | 1 | EACH | 100.00 | 100.00 | 100.00 | 100.00 |
| 0007 | 202-03-38000 | Relocation of Sign Yield | 1 | EACH | 100.00 | 100.00 | 100.00 | 100.00 |
| 0008 | 202-03-38000 | Relocation of Sign Street Sign | 2 | EACH | 100.00 | 200.00 | 100.00 | 200.00 |
| 0009 | 202-03-38000 | Relocation of Sign Yield Ahead | 2 | EACH | 100.00 | 200.00 | 150.00 | 300.00 |
| 0010 | 202-03-38000 | Relocation of Sign Wrong Way | 1 | EACH | 100.00 | 100.00 | 150.00 | 150.00 |
| 0011 | 202-03-38000 | Relocation of Sign Fiber Optic Locate | 5 | EACH | 100.00 | 500.00 | 200.00 | 1,000.00 |
| 0012 | 202-03-38000 | Relocation of Sign One Way | 1 | EACH | 100.00 | 100.00 | 100.00 | 100.00 |
| 0013 | 202-03-38000 | Relocation of Sign J & J BBQ | 1 | EACH | 100.00 | 100.00 | 1,000.00 | 1,000.00 |
| 0014 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 16,500.00 | 16,500.00 | 50,000.00 | 50,000.00 |
| 0015 | 204-02-00100 | Temporary Hay or Straw Bales | 40 | EACH | 10.00 | 400.00 | 20.00 | 800.00 |
| 0016 | 204-06-00100 | Temporary Silt Fencing | 9,250 | LNFT | 2.00 | 18,500.00 | 2.00 | 18,500.00 |
| 0017 | 302-02-01061 | Class II Base Course (4" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 5,573.8 | SQYD | 12.80 | 71,344.64 | 11.00 | 61,311.80 |
| 0018 | 706-01-00100 | Concrete Walk (4" Thick) | 5,198.2 | SQYD | 50.00 | 259,910.00 | 44.00 | 228,720.80 |
| 0019 | 706-01-00300 | Concrete Walk (6" Thick) | 374.9 | SQYD | 63.75 | 23,899.88 | 75.00 | 28,117.50 |
| 0020 | 706-04-00100 | Handicapped Curb Ramps | 28 | EACH | 2,200.00 | 61,600.00 | 1,000.00 | 28,000.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 14,000.00 | 14,000.00 | 12,000.00 | 12,000.00 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 32,000.00 | 32,000.00 | 50,000.00 | 50,000.00 |
| 0023 | 739-01-00100 | Hydro-Seeding | 2.15 | ACRE | 2,500.00 | 5,375.00 | 2,500.00 | 5,375.00 |
| 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,500.00 | 1,500.00 | 7,500.00 | 7,500.00 |
| 0025 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 3,726 | INLF | 0.80 | 2,980.80 | 1.50 | 5,589.00 |
| 0026 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,524 | INLF | 2.50 | 3,810.00 | 1.50 | 2,286.00 |
| 0027 | NS-ENH-18040 | Retaining Walls Special Detail | 242 | LNFT | 75.00 | 18,150.00 | 125.00 | 30,250.00 |
| CONTRACTOR TOTAL | 549,560.72 | 652,858.90 | ||||||