Bid Tabulations
Letting of
12/14/2011
LA DOTD Headquarters
| Lead Project: H.000678.6 | |
| Parish: Orleans | |
| Routes: US 11 | |
| Description: US 11 DRAINAGE IMPROVEMENTS | |
| Type Const: GRADING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $388,166.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06487 | Huey Stockstill, Inc. | $263,390.40 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $356,933.20 |
| 3 | 06276 | Barriere Construction Co., LLC | $363,908.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Huey Stockstill, Inc. |
- 2 - Boh Bros. Construction Co., LLC. |
- 3 - Barriere Construction Co., LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 900 | CUYD | 18.00 | 16,200.00 | 20.00 | 18,000.00 | 14.00 | 12,600.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 134.7 | CUYD | 40.00 | 5,388.00 | 150.00 | 20,205.00 | 125.00 | 16,837.50 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 2,170.7 | TON | 80.00 | 173,656.00 | 100.00 | 217,070.00 | 107.00 | 232,264.90 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 45,000.00 | 45,000.00 | 32,000.00 | 32,000.00 |
| 0005 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1.628 | MILE | 100.00 | 162.80 | 100.00 | 162.80 | 200.00 | 325.60 |
| 0006 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.768 | MILE | 100.00 | 276.80 | 150.00 | 415.20 | 550.00 | 1,522.40 |
| 0007 | 717-01-00100 | Seeding | 4 | LB | 45.00 | 180.00 | 55.00 | 220.00 | 60.00 | 240.00 |
| 0008 | 718-01-00100 | Fertilizer | 130 | LB | 6.00 | 780.00 | 6.50 | 845.00 | 9.00 | 1,170.00 |
| 0009 | 727-01-00100 | Mobilization | 1 | LUMP | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 | 32,000.00 | 32,000.00 |
| 0010 | 731-02-00100 | Reflectorized Raised Pavement Markers | 96 | EACH | 6.00 | 576.00 | 5.50 | 528.00 | 6.00 | 576.00 |
| 0011 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.836 | MILE | 3,300.00 | 6,058.80 | 3,200.00 | 5,875.20 | 3,100.00 | 5,691.60 |
| 0012 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.68 | MILE | 900.00 | 612.00 | 900.00 | 612.00 | 1,000.00 | 680.00 |
| 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 13,500.00 | 13,500.00 | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 |
| 0014 | NS-500-00280 | Surface Preparation | 1 | LUMP | 6,000.00 | 6,000.00 | 12,000.00 | 12,000.00 | 23,000.00 | 23,000.00 |
| CONTRACTOR TOTAL | 263,390.40 | 356,933.20 | 363,908.00 | |||||||