Bid Tabulations
Letting of
06/12/2013
LA DOTD Headquarters
| Lead Project: H.000492.6 | |
| Parish: St. Tammany | |
| Routes: US 190 | |
| Description: US 190 (I-12 - LA 22) | |
| Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $8,052,315.72 | |
| Maximum Number of Days Allowed for Construction: 9999 | |
| Calculated Daily User Cost: $5,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $8,716,670.88 | 150 | $9,466,670.88 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $9,135,331.00 | 225 | $10,260,331.00 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $11,137,728.63 | 398 | $13,127,728.63 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Boh Bros. Construction Co., LLC. |
- 3 - Diamond B Construction Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 25,000.00 | 25,000.00 | 2,000.00 | 2,000.00 | 25,000.00 | 25,000.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 1.00 | 1.00 | 2,000.00 | 2,000.00 | 125,000.00 | 125,000.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 8,454.1 | LNFT | 6.00 | 50,724.60 | 5.00 | 42,270.50 | 8.00 | 67,632.80 |
| 0004 | 202-02-12020 | Removal of Fence (Chain Link) | 650 | LNFT | 2.75 | 1,787.50 | 3.00 | 1,950.00 | 3.00 | 1,950.00 |
| 0005 | 202-02-14500 | Removal of Guard Rail | 4,992 | LNFT | 9.00 | 44,928.00 | 10.00 | 49,920.00 | 7.50 | 37,440.00 |
| 0006 | 202-02-38220 | Removal of Sign Supports | 89 | EACH | 160.00 | 14,240.00 | 155.00 | 13,795.00 | 250.00 | 22,250.00 |
| 0007 | 202-02-38280 | Removal of Sign Fascia Mountings | 2 | EACH | 525.00 | 1,050.00 | 520.00 | 1,040.00 | 1,250.00 | 2,500.00 |
| 0008 | 202-02-38330 | Removal of Sign Cantilever and Footing | 4 | EACH | 6,000.00 | 24,000.00 | 5,200.00 | 20,800.00 | 5,500.00 | 22,000.00 |
| 0009 | 202-02-38360 | Removal of Sign Faces | 126 | EACH | 55.00 | 6,930.00 | 55.00 | 6,930.00 | 90.00 | 11,340.00 |
| 0010 | 202-02-38380 | Removal of Sign Truss and Footings | 2 | EACH | 5,500.00 | 11,000.00 | 5,200.00 | 10,400.00 | 14,000.00 | 28,000.00 |
| 0011 | 202-02-38500 | Removal of Surfacing and Stablized Base | 8,150.3 | SQYD | 1.25 | 10,187.88 | 5.00 | 40,751.50 | 7.00 | 57,052.10 |
| 0012 | 203-01-00100 | General Excavation | 6,476 | CUYD | 4.00 | 25,904.00 | 18.00 | 116,568.00 | 14.00 | 90,664.00 |
| 0013 | 203-03-00100 | Embankment | 8,437 | CUYD | 15.00 | 126,555.00 | 24.00 | 202,488.00 | 15.00 | 126,555.00 |
| 0014 | 204-02-00100 | Temporary Hay or Straw Bales | 36 | EACH | 16.00 | 576.00 | 15.00 | 540.00 | 15.00 | 540.00 |
| 0015 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 150.00 | 1,200.00 | 125.00 | 1,000.00 | 140.00 | 1,120.00 |
| 0016 | 204-06-00100 | Temporary Silt Fencing | 8,117 | LNFT | 1.50 | 12,175.50 | 1.50 | 12,175.50 | 2.00 | 16,234.00 |
| 0017 | 302-01-00800 | Class II Base Course (Stone or Recycled Portland Cement Concrete) | 6,118.8 | CUYD | 70.00 | 428,316.00 | 80.00 | 489,504.00 | 85.00 | 520,098.00 |
| 0018 | 502-01-00100 | Superpave Asphaltic Concrete | 37,565 | TON | 69.00 | 2,591,985.00 | 80.00 | 3,005,200.00 | 83.00 | 3,117,895.00 |
| 0019 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4,519.2 | TON | 135.00 | 610,092.00 | 95.00 | 429,324.00 | 156.00 | 704,995.20 |
| 0020 | 508-01-00100 | Asphalt Concrete (SMA) Wearing Course | 12,858.5 | TON | 136.00 | 1,748,756.00 | 120.00 | 1,543,020.00 | 190.00 | 2,443,115.00 |
| 0021 | 509-01-00100 | Cold Planing Asphaltic Pavement | 166,432.4 | SQYD | 2.00 | 332,864.80 | 1.75 | 291,256.70 | 3.25 | 540,905.30 |
| 0022 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -6,935 | CUYD | 10.00 | -69,350.00 | 15.00 | -104,025.00 | 1.00 | -6,935.00 |
| 0023 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 2,500 | SQYD | 40.00 | 100,000.00 | 100.00 | 250,000.00 | 80.00 | 200,000.00 |
| 0024 | 602-13-00100 | Slabjacking Pavement | 120 | TON | 450.00 | 54,000.00 | 415.00 | 49,800.00 | 2,800.00 | 336,000.00 |
| 0025 | 602-14-00100 | Holes | 256 | EACH | 5.00 | 1,280.00 | 50.00 | 12,800.00 | 280.00 | 71,680.00 |
| 0026 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 36 | LNFT | 115.00 | 4,140.00 | 100.00 | 3,600.00 | 1,000.00 | 36,000.00 |
| 0027 | 701-15-00100 | Concrete Collar | 2 | EACH | 2,200.00 | 4,400.00 | 1,500.00 | 3,000.00 | 1,400.00 | 2,800.00 |
| 0028 | 702-04-00200 | Adjusting Catch Basins | 7 | EACH | 1,200.00 | 8,400.00 | 2,000.00 | 14,000.00 | 3,000.00 | 21,000.00 |
| 0029 | 704-01-02000 | Guard Rail (DoubleThrie Beam) (3'-1 1/2" post spacing) | 1,379.3 | LNFT | 46.00 | 63,447.80 | 50.00 | 68,965.00 | 55.00 | 75,861.50 |
| 0030 | 704-03-00100 | Blocked Out Guard Rail | 4,828.3 | LNFT | 17.00 | 82,081.10 | 19.00 | 91,737.70 | 19.00 | 91,737.70 |
| 0031 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 87.5 | LNFT | 66.00 | 5,775.00 | 70.00 | 6,125.00 | 90.00 | 7,875.00 |
| 0032 | 704-06-00200 | Guard Rail Anchor Sections (Trailing End) (Single Thrie Beam) | 50.3 | LNFT | 67.00 | 3,370.10 | 70.00 | 3,521.00 | 95.00 | 4,778.50 |
| 0033 | 704-07-00100 | Guard Rail Bridge Attachments | 40 | LNFT | 12.00 | 480.00 | 11.00 | 440.00 | 33.00 | 1,320.00 |
| 0034 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 250 | LNFT | 62.00 | 15,500.00 | 67.00 | 16,750.00 | 65.00 | 16,250.00 |
| 0035 | 704-11-00100 | Guard Rail End Treatment (Flared) | 30 | EACH | 2,100.00 | 63,000.00 | 2,500.00 | 75,000.00 | 2,200.00 | 66,000.00 |
| 0036 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 2 | EACH | 2,500.00 | 5,000.00 | 2,600.00 | 5,200.00 | 2,800.00 | 5,600.00 |
| 0037 | 704-11-00300 | Guard Rail End Treatment (Bi-Directional) | 2 | EACH | 5,100.00 | 10,200.00 | 5,600.00 | 11,200.00 | 5,600.00 | 11,200.00 |
| 0038 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 650 | LNFT | 30.00 | 19,500.00 | 19.00 | 12,350.00 | 25.00 | 16,250.00 |
| 0039 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 342.4 | SQYD | 69.00 | 23,625.60 | 70.00 | 23,968.00 | 70.00 | 23,968.00 |
| 0040 | 707-03-00100 | Combination Concrete Curb and Gutter | 8,454.1 | LNFT | 17.00 | 143,719.70 | 34.00 | 287,439.40 | 30.00 | 253,623.00 |
| 0041 | 707-04-00100 | Asphaltic Curb | 100 | LNFT | 41.00 | 4,100.00 | 34.00 | 3,400.00 | 55.00 | 5,500.00 |
| 0042 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 250,000.00 | 250,000.00 | 100,000.00 | 100,000.00 | 485,000.00 | 485,000.00 |
| 0043 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 20.36 | MILE | 265.00 | 5,395.40 | 475.00 | 9,671.00 | 270.00 | 5,497.20 |
| 0044 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 7.727 | MILE | 3,000.00 | 23,181.00 | 2,500.00 | 19,317.50 | 3,800.00 | 29,362.60 |
| 0045 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.011 | MILE | 750.00 | 6,758.25 | 550.00 | 4,956.05 | 525.00 | 4,730.78 |
| 0046 | 716-01-00100 | Mulch (Vegetative) | 2.5 | TON | 1,250.00 | 3,125.00 | 1,200.00 | 3,000.00 | 1,250.00 | 3,125.00 |
| 0047 | 717-01-00100 | Seeding | 308 | LB | 11.00 | 3,388.00 | 10.00 | 3,080.00 | 10.00 | 3,080.00 |
| 0048 | 718-01-00100 | Fertilizer | 5,130 | LB | 1.00 | 5,130.00 | 0.70 | 3,591.00 | 0.70 | 3,591.00 |
| 0049 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 | 13,000.00 | 13,000.00 |
| 0050 | 726-01-00100 | Bedding Material | 10 | CUYD | 100.00 | 1,000.00 | 60.00 | 600.00 | 125.00 | 1,250.00 |
| 0051 | 727-01-00100 | Mobilization | 1 | LUMP | 800,000.00 | 800,000.00 | 815,000.00 | 815,000.00 | 120,000.00 | 120,000.00 |
| 0052 | 729-01-00100 | Sign (Type A) | 1,084.6 | SQFT | 22.00 | 23,861.20 | 22.00 | 23,861.20 | 20.00 | 21,692.00 |
| 0053 | 729-04-00100 | Sign (Type D) | 963.5 | SQFT | 22.00 | 21,197.00 | 22.00 | 21,197.00 | 28.00 | 26,978.00 |
| 0054 | 729-06-00100 | Sign (Overhead Mounted) | 3,297.5 | SQFT | 32.00 | 105,520.00 | 31.00 | 102,222.50 | 29.00 | 95,627.50 |
| 0055 | 729-08-00200 | Mounting (3 1/2" Size Post) | 47 | EACH | 800.00 | 37,600.00 | 800.00 | 37,600.00 | 1,000.00 | 47,000.00 |
| 0056 | 729-08-00500 | Mounting (S3 x 5.7 Size Post) | 6 | EACH | 925.00 | 5,550.00 | 925.00 | 5,550.00 | 925.00 | 5,550.00 |
| 0057 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 20 | EACH | 1,000.00 | 20,000.00 | 1,000.00 | 20,000.00 | 1,575.00 | 31,500.00 |
| 0058 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 10 | EACH | 1,850.00 | 18,500.00 | 1,800.00 | 18,000.00 | 2,000.00 | 20,000.00 |
| 0059 | 729-09-00100 | Mounting (Overhead Truss) (Ground Mounted) (60' Span) | 1 | EACH | 45,000.00 | 45,000.00 | 46,000.00 | 46,000.00 | 63,000.00 | 63,000.00 |
| 0060 | 729-09-00800 | Mounting (Overhead Truss) (Ground Mounted) (102' Span) | 1 | EACH | 67,500.00 | 67,500.00 | 67,000.00 | 67,000.00 | 76,000.00 | 76,000.00 |
| 0061 | 729-11-00100 | Mounting (Overhead Cantilever) (Ground Mounted) | 4 | EACH | 27,500.00 | 110,000.00 | 26,000.00 | 104,000.00 | 35,000.00 | 140,000.00 |
| 0062 | 729-13-00100 | Mounting (Bridge Fascia Mounted) | 2 | EACH | 10,000.00 | 20,000.00 | 10,500.00 | 21,000.00 | 6,000.00 | 12,000.00 |
| 0063 | 729-16-00300 | Object Marker Assembly (Type 3) | 54 | EACH | 67.00 | 3,618.00 | 70.00 | 3,780.00 | 85.00 | 4,590.00 |
| 0064 | 729-20-00600 | Footings for Overhead Mountings (Cantilever) | 4 | EACH | 32,000.00 | 128,000.00 | 31,000.00 | 124,000.00 | 36,000.00 | 144,000.00 |
| 0065 | 729-20-00700 | Footings for Overhead Mountings (Truss) | 4 | EACH | 26,000.00 | 104,000.00 | 26,000.00 | 104,000.00 | 30,000.00 | 120,000.00 |
| 0066 | 729-21-00100 | U-Channel Post | 54 | EACH | 1.00 | 54.00 | 75.00 | 4,050.00 | 85.00 | 4,590.00 |
| 0067 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,120 | EACH | 8.00 | 16,960.00 | 5.50 | 11,660.00 | 4.50 | 9,540.00 |
| 0068 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 9,452 | LNFT | 1.10 | 10,397.20 | 1.40 | 13,232.80 | 1.00 | 9,452.00 |
| 0069 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 2,122 | LNFT | 4.00 | 8,488.00 | 4.50 | 9,549.00 | 3.20 | 6,790.40 |
| 0070 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 71 | LNFT | 4.50 | 319.50 | 5.25 | 372.75 | 4.25 | 301.75 |
| 0071 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.976 | MILE | 2,750.00 | 41,184.00 | 2,825.00 | 42,307.20 | 2,400.00 | 35,942.40 |
| 0072 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.39 | MILE | 800.00 | 5,912.00 | 875.00 | 6,466.25 | 650.00 | 4,803.50 |
| 0073 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 4 | EACH | 260.00 | 1,040.00 | 275.00 | 1,100.00 | 210.00 | 840.00 |
| 0074 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 200.00 | 800.00 | 225.00 | 900.00 | 210.00 | 840.00 |
| 0075 | 732-04-05020 | Plastic Pavement Legends and Symbols (EXIT) | 3 | EACH | 250.00 | 750.00 | 210.00 | 630.00 | 210.00 | 630.00 |
| 0076 | 732-05-00100 | Removal of Existing Markings | 2.94 | MILE | 5,000.00 | 14,700.00 | 4,000.00 | 11,760.00 | 2,600.00 | 7,644.00 |
| 0077 | 740-01-00100 | Construction Layout | 1 | LUMP | 60,000.00 | 60,000.00 | 20,000.00 | 20,000.00 | 55,000.00 | 55,000.00 |
| 0078 | NS-200-00020 | Cleaning Existing Ditches | 390 | LNFT | 4.00 | 1,560.00 | 4.00 | 1,560.00 | 21.00 | 8,190.00 |
| 0079 | NS-500-00300 | Traffic Maintenance Superpave Asphaltic Concrete | 1,000 | TON | 1.00 | 1,000.00 | 70.00 | 70,000.00 | 170.00 | 170,000.00 |
| 0080 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 141,659 | INLF | 0.25 | 35,414.75 | 0.55 | 77,912.45 | 0.60 | 84,995.40 |
| 0081 | NS-713-00001 | Dynamic Message Sign Unit | 6 | EACH | 7,500.00 | 45,000.00 | 9,000.00 | 54,000.00 | 3,750.00 | 22,500.00 |
| 0082 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 12 | MILE | 750.00 | 9,000.00 | 650.00 | 7,800.00 | 300.00 | 3,600.00 |
| 0083 | 701-14-00100 | Cleaning Existing Pipes | 325 | LNFT | 11.00 | 3,575.00 | 7.00 | 2,275.00 | 30.00 | 9,750.00 |
| 0084 | 705-09-00100 | Rebuilt Fence | 850 | LNFT | 25.00 | 21,250.00 | 22.50 | 19,125.00 | 27.00 | 22,950.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 8,716,670.88 | 9,135,331.00 | 11,137,728.63 | |||||||
| NUMBER OF DAYS BID AT $5000 PER DAY. | 750,000.00 | 1,125,000.00 | 1,990,000.00 | |||||||
| TOTAL BID | 9,466,670.88 | 10,260,331.00 | 13,127,728.63 | |||||||