Bid Tabulations
Letting of
08/08/2012
LA DOTD Headquarters
| Lead Project: H.000477.6 | |
| Parish: Tangipahoa | |
| Routes: US 190 | |
| Description: US 190: LIVINGSTON LINE - U'PASS I-55 | |
| Type Const: COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALT CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $1,735,384.55 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $1,739,728.92 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,797,655.59 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $1,877,094.62 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 1,082 | LNFT | 11.00 | 11,902.00 | 6.58 | 7,119.56 | 7.00 | 7,574.00 |
| 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 20 | EACH | 1.00 | 20.00 | 25.00 | 500.00 | 50.00 | 1,000.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,600 | CUYD | 8.00 | 12,800.00 | 1.00 | 1,600.00 | 15.00 | 24,000.00 |
| 0004 | 204-02-00100 | Temporary Hay or Straw Bales | 20 | EACH | 12.00 | 240.00 | 70.00 | 1,400.00 | 20.00 | 400.00 |
| 0005 | 502-01-00100 | Superpave Asphaltic Concrete | 10,626.1 | TON | 85.00 | 903,218.50 | 87.00 | 924,470.70 | 90.00 | 956,349.00 |
| 0006 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,595.9 | TON | 100.00 | 159,590.00 | 1.00 | 1,595.90 | 107.00 | 170,761.30 |
| 0007 | 509-01-00100 | Cold Planing Asphaltic Pavement | 97,676 | SQYD | 1.40 | 136,746.40 | 2.50 | 244,190.00 | 0.85 | 83,024.60 |
| 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -4,070 | CUYD | 20.00 | -81,400.00 | 30.00 | -122,100.00 | 1.00 | -4,070.00 |
| 0009 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | 455.33 | SQYD | 250.00 | 113,832.50 | 300.00 | 136,599.00 | 195.00 | 88,789.35 |
| 0010 | 701-05-02060 | Side Drain Pipe (Erosion) (24" PP/CMP) | 16 | LNFT | 320.00 | 5,120.00 | 120.00 | 1,920.00 | 140.00 | 2,240.00 |
| 0011 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,300.00 | 1,300.00 | 1,000.00 | 1,000.00 | 900.00 | 900.00 |
| 0012 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 487.5 | LNFT | 65.00 | 31,687.50 | 42.00 | 20,475.00 | 60.00 | 29,250.00 |
| 0013 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 564 | LNFT | 35.00 | 19,740.00 | 55.00 | 31,020.00 | 38.00 | 21,432.00 |
| 0014 | 704-03-00100 | Blocked Out Guard Rail | 437.5 | LNFT | 20.00 | 8,750.00 | 22.00 | 9,625.00 | 22.00 | 9,625.00 |
| 0015 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 74.00 | 7,400.00 | 58.00 | 5,800.00 | 65.00 | 6,500.00 |
| 0016 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,400.00 | 9,600.00 | 2,200.00 | 8,800.00 | 2,200.00 | 8,800.00 |
| 0017 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 12 | EACH | 3,000.00 | 36,000.00 | 2,300.00 | 27,600.00 | 2,500.00 | 30,000.00 |
| 0018 | 707-04-00100 | Asphaltic Curb | 40 | LNFT | 40.00 | 1,600.00 | 50.00 | 2,000.00 | 35.00 | 1,400.00 |
| 0019 | 711-02-00300 | Riprap (30 lb) At stations 29+40 LT and 126+25 RT | 10 | CUYD | 250.00 | 2,500.00 | 350.00 | 3,500.00 | 160.00 | 1,600.00 |
| 0020 | 711-02-00400 | Riprap (55 lb) At stations 152+45 RT and 189+95 RT | 80 | CUYD | 250.00 | 20,000.00 | 125.00 | 10,000.00 | 115.00 | 9,200.00 |
| 0021 | 711-04-00100 | Geotextile Fabric | 2,430 | SQYD | 0.50 | 1,215.00 | 2.00 | 4,860.00 | 1.60 | 3,888.00 |
| 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 123,000.00 | 123,000.00 | 140,000.00 | 140,000.00 |
| 0023 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,788 | LNFT | 0.15 | 268.20 | 0.26 | 464.88 | 0.30 | 536.40 |
| 0024 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 4,016 | LNFT | 0.65 | 2,610.40 | 0.80 | 3,212.80 | 0.80 | 3,212.80 |
| 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.9 | MILE | 0.85 | 6.72 | 175.00 | 1,382.50 | 400.00 | 3,160.00 |
| 0026 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 6.853 | MILE | 500.00 | 3,426.50 | 500.00 | 3,426.50 | 1.00 | 6.85 |
| 0027 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 25.34 | MILE | 625.00 | 15,837.50 | 600.00 | 15,204.00 | 1.00 | 25.34 |
| 0028 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 42 | EACH | 25.00 | 1,050.00 | 47.00 | 1,974.00 | 55.00 | 2,310.00 |
| 0029 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 25.00 | 100.00 | 82.00 | 328.00 | 100.00 | 400.00 |
| 0030 | 726-01-00100 | Bedding Material | 3.5 | CUYD | 90.00 | 315.00 | 80.00 | 280.00 | 165.00 | 577.50 |
| 0031 | 727-01-00100 | Mobilization | 1 | LUMP | 90,000.00 | 90,000.00 | 170,000.00 | 170,000.00 | 150,000.00 | 150,000.00 |
| 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 75.00 | 1,200.00 | 80.00 | 1,280.00 | 85.00 | 1,360.00 |
| 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 540 | EACH | 6.50 | 3,510.00 | 6.00 | 3,240.00 | 6.00 | 3,240.00 |
| 0034 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 894 | LNFT | 1.00 | 894.00 | 1.60 | 1,430.40 | 1.70 | 1,519.80 |
| 0035 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 2,008 | LNFT | 7.00 | 14,056.00 | 5.25 | 10,542.00 | 5.75 | 11,546.00 |
| 0036 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.67 | MILE | 2,900.00 | 36,743.00 | 2,600.00 | 32,942.00 | 2,800.00 | 35,476.00 |
| 0037 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.427 | MILE | 1,100.00 | 3,769.70 | 850.00 | 2,912.95 | 975.00 | 3,341.33 |
| 0038 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 20 | EACH | 225.00 | 4,500.00 | 225.00 | 4,500.00 | 250.00 | 5,000.00 |
| 0039 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 225.00 | 225.00 | 225.00 | 225.00 | 250.00 | 250.00 |
| 0040 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 4 | EACH | 435.00 | 1,740.00 | 425.00 | 1,700.00 | 450.00 | 1,800.00 |
| 0041 | 735-01-00100 | Mailboxes | 69 | EACH | 5.00 | 345.00 | 6.00 | 414.00 | 1.15 | 79.35 |
| 0042 | 735-02-00100 | Mailbox Supports (Single) | 53 | EACH | 100.00 | 5,300.00 | 115.00 | 6,095.00 | 120.00 | 6,360.00 |
| 0043 | 735-04-00100 | Mailbox Supports (Multiple) | 16 | EACH | 350.00 | 5,600.00 | 375.00 | 6,000.00 | 370.00 | 5,920.00 |
| 0044 | 736-09-00100 | Loop Detector | 150 | LNFT | 18.50 | 2,775.00 | 26.00 | 3,900.00 | 15.00 | 2,250.00 |
| 0045 | 739-01-00100 | Hydro-Seeding | 3.38 | ACRE | 1,550.00 | 5,239.00 | 1,200.00 | 4,056.00 | 1,200.00 | 4,056.00 |
| 0046 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 7,400.00 | 7,400.00 |
| 0047 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 31,392 | INLF | 1.00 | 31,392.00 | 0.20 | 6,278.40 | 0.25 | 7,848.00 |
| 0048 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 8,064 | INLF | 1.00 | 8,064.00 | 0.50 | 4,032.00 | 0.25 | 2,016.00 |
| 0049 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,280 | INLF | 1.00 | 2,280.00 | 2.00 | 4,560.00 | 1.50 | 3,420.00 |
| 0050 | NS-713-00001 | Dynamic Message Sign Unit | 4 | EACH | 500.00 | 2,000.00 | 8,500.00 | 34,000.00 | 5,000.00 | 20,000.00 |
| 0051 | NS-724-00001 | Rumble Strips (Centerline Ground-In) | 2.2 | MILE | 2,100.00 | 4,620.00 | 1,500.00 | 3,300.00 | 600.00 | 1,320.00 |
| CONTRACTOR TOTAL | 1,739,728.92 | 1,797,655.59 | 1,877,094.62 | |||||||