Bid Tabulations
Letting of
04/28/2010
LA DOTD Headquarters
| Lead Project: 859-25-0011 | |
| Parish: Washington | |
| Routes: LA 1055 | |
| Description: JCT. LA 38 - JCT. LA 438 | |
| Type Const: ASPHALTIC SURFACE TREATMENT AND RELATED WORK. | |
| Estimated Construction Cost: $176,545.62 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 01552 | W. R. Core, LLC. | $163,103.19 |
| 2 | 14422 | T. L. Wallace Construction, Inc. | $168,252.15 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W. R. Core, LLC. |
- 2 - T. L. Wallace Construction, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 23,483 | GAL | 3.15 | 73,971.45 | 3.35 | 78,668.05 |
| 0002 | 507-02-00300 | Aggregate (S3) Stone Only | 75,751 | SQYD | 0.74 | 56,055.74 | 0.85 | 64,388.35 |
| 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,254.00 | 3,254.00 | 3,300.00 | 3,300.00 |
| 0004 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,705 | EACH | 1.50 | 2,557.50 | 1.25 | 2,131.25 |
| 0005 | 727-01-00100 | Mobilization | 1 | LUMP | 9,000.00 | 9,000.00 | 2,500.00 | 2,500.00 |
| 0006 | 731-02-00100 | Reflectorized Raised Pavement Markers | 853 | EACH | 4.50 | 3,838.50 | 4.50 | 3,838.50 |
| 0007 | 737-01-00100 | Painted Traffic Striping (Solid Line) (4" Width) | 11.977 | MILE | 1,000.00 | 11,977.00 | 1,000.00 | 11,977.00 |
| 0008 | 737-02-00100 | Painted Traffic Striping (Broken Line) (4" Width) | 0.844 | MILE | 500.00 | 422.00 | 500.00 | 422.00 |
| 0009 | 737-03-00500 | Painted Traffic Striping (Solid Line) (24" Width) | 30 | LNFT | 0.90 | 27.00 | 0.90 | 27.00 |
| 0010 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 1,000.00 | 1,000.00 |
| CONTRACTOR TOTAL | 163,103.19 | 168,252.15 | ||||||