Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 859-09-0020 | |
| Parish: Washington | |
| Routes: LA 430 | |
| Description: JCT. LA 1069 - JCT. LA 438 | |
| Type Const: PAVEMENT PATCHING, SURFACE PREPARATION, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $1,456,329.58 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC. | $1,515,967.72 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $1,706,239.18 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC. |
- 2 - Diamond B Construction Co., L.L.C. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,578.5 | CUYD | 35.00 | 125,247.50 | 79.51 | 284,526.54 |
| 0002 | 502-01-00100 | Superpave Asphaltic Concrete | 11,472.9 | TON | 68.00 | 780,157.20 | 73.91 | 847,962.04 |
| 0003 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 750.8 | TON | 115.00 | 86,342.00 | 159.40 | 119,677.52 |
| 0004 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 3,144 | SQYD | 35.00 | 110,040.00 | 82.44 | 259,191.36 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 125,000.00 | 125,000.00 | 14,884.99 | 14,884.99 |
| 0006 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 20 | LNFT | 0.10 | 2.00 | 1.13 | 22.60 |
| 0007 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.6 | MILE | 150.00 | 2,640.00 | 171.00 | 3,009.60 |
| 0008 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.646 | MILE | 1.00 | 4.65 | 441.29 | 2,050.23 |
| 0009 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 26.114 | MILE | 1.00 | 26.11 | 819.54 | 21,401.47 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 35,671.56 | 35,671.56 |
| 0011 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,159 | EACH | 5.50 | 6,374.50 | 6.30 | 7,301.70 |
| 0012 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 10 | LNFT | 5.50 | 55.00 | 7.57 | 75.70 |
| 0013 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.057 | MILE | 2,750.00 | 35,906.75 | 3,152.06 | 41,156.45 |
| 0014 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.323 | MILE | 935.00 | 2,172.01 | 882.57 | 2,050.21 |
| 0015 | 740-01-00100 | Construction Layout | 1 | LUMP | 24,000.00 | 24,000.00 | 8,195.35 | 8,195.35 |
| 0016 | NS-500-00280 | Surface Preparation | 1 | LUMP | 68,000.00 | 68,000.00 | 59,061.86 | 59,061.86 |
| CONTRACTOR TOTAL | 1,515,967.72 | 1,706,239.18 | ||||||