Bid Tabulations
Letting of
02/23/2011
LA DOTD Headquarters
| Lead Project: 853-36-0040 | |
| Parish: Tangipahoa | |
| Routes: US 51B/LA22 | |
| Description: Ponchatoula Pedestrian Project, Phase II | |
| Type Const: GRADING, CONCRETE SIDEWALK RECONSTRUCTION AND RELATED WORK. | |
| Estimated Construction Cost: $120,349.98 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 49356 | Kort's Trucking Inc. | $108,506.10 |
| 2 | 41947 | M & M Enterprises of Bastrop, LLC | $113,192.95 |
| 3 | 14807 | Richard Price Contracting Co, Llc | $118,656.42 |
| 4 | 38610 | Three C's Properties Inc | $123,687.60 |
| 5 | 16724 | Stranco, Inc. | $125,333.20 |
| 6 | 50267 | Hhp Construction Group Llc | $125,937.45 |
| 7 | 12198 | Byron E. Talbot Contractor, Inc. | $146,590.46 |
| 8 | 02179 | Boh Bros. Construction Co., LLC. | $146,985.00 |
| 9 | 47020 | T.N.T. Construction Group LLC | $182,554.92 |
| 10 | 49194 | Task Force Llc | $237,078.54 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Kort's Trucking Inc. |
- 2 - M & M Enterprises of Bastrop, LLC |
- 3 - Richard Price Contracting Co, Llc |
- 4 - Three C's Properties Inc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 66.7 | SQYD | 12.00 | 800.40 | 4.50 | 300.15 | 12.00 | 800.40 | 20.00 | 1,334.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 321 | SQYD | 12.00 | 3,852.00 | 9.00 | 2,889.00 | 8.00 | 2,568.00 | 10.50 | 3,370.50 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 100 | LNFT | 8.00 | 800.00 | 17.00 | 1,700.00 | 11.50 | 1,150.00 | 13.50 | 1,350.00 |
| 0004 | 202-03-38000 | Relocation of Sign (Sta. 26+00) | 1 | EACH | 55.00 | 55.00 | 100.00 | 100.00 | 62.00 | 62.00 | 275.00 | 275.00 |
| 0005 | 202-03-38020 | Relocation of Sign Pole (Sta. 26+00) | 1 | EACH | 55.00 | 55.00 | 100.00 | 100.00 | 62.00 | 62.00 | 275.00 | 275.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 5,000.00 | 5,000.00 | 8,000.00 | 8,000.00 | 7,500.00 | 7,500.00 | 4,000.00 | 4,000.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 30 | EACH | 12.00 | 360.00 | 8.00 | 240.00 | 20.50 | 615.00 | 12.00 | 360.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 2.00 | 2,000.00 | 2.75 | 2,750.00 | 2.50 | 2,500.00 | 1.25 | 1,250.00 |
| 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 20 | CUYD | 75.00 | 1,500.00 | 100.00 | 2,000.00 | 99.00 | 1,980.00 | 45.00 | 900.00 |
| 0010 | 701-06-01040 | Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) | 27 | LNFT | 100.00 | 2,700.00 | 120.00 | 3,240.00 | 94.00 | 2,538.00 | 150.00 | 4,050.00 |
| 0011 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,000.00 | 2,000.00 | 2,400.00 | 2,400.00 | 2,625.00 | 2,625.00 | 3,800.00 | 3,800.00 |
| 0012 | 706-01-00300 | Concrete Walk (6" Thick) | 940.6 | SQYD | 60.00 | 56,436.00 | 43.00 | 40,445.80 | 51.25 | 48,205.75 | 65.00 | 61,139.00 |
| 0013 | 706-02-00200 | Concrete Drive (6" Thick) | 31.4 | SQYD | 70.00 | 2,198.00 | 50.00 | 1,570.00 | 46.25 | 1,452.25 | 70.00 | 2,198.00 |
| 0014 | 706-04-00100 | Handicapped Curb Ramps | 9 | EACH | 500.00 | 4,500.00 | 800.00 | 7,200.00 | 313.00 | 2,817.00 | 650.00 | 5,850.00 |
| 0015 | 707-01-00200 | Concrete Curb (Barrier) | 122 | LNFT | 12.00 | 1,464.00 | 15.00 | 1,830.00 | 7.50 | 915.00 | 30.00 | 3,660.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 | 11,000.00 | 11,000.00 | 5,000.00 | 5,000.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 5,000.00 | 5,000.00 | 11,000.00 | 11,000.00 | 10,000.00 | 10,000.00 | 9,000.00 | 9,000.00 |
| 0018 | 729-01-00100 | Sign (Type A) | 31.3 | SQFT | 29.00 | 907.70 | 20.00 | 626.00 | 13.18 | 412.53 | 17.00 | 532.10 |
| 0019 | 729-21-00100 | U-Channel Post | 5 | EACH | 90.00 | 450.00 | 75.00 | 375.00 | 80.44 | 402.20 | 130.00 | 650.00 |
| 0020 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 75 | LNFT | 11.00 | 825.00 | 13.00 | 975.00 | 8.52 | 639.00 | 8.00 | 600.00 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 265 | LNFT | 11.00 | 2,915.00 | 20.00 | 5,300.00 | 17.03 | 4,512.95 | 16.00 | 4,240.00 |
| 0022 | 739-01-00100 | Hydro-Seeding Sta. 14+45 to 14+93, 19+69 to 19+99, 25+35 to 25+85, 33+00 to 34+30 | 0.3 | ACRE | 3,800.00 | 1,140.00 | 4,000.00 | 1,200.00 | 4,087.33 | 1,226.20 | 4,000.00 | 1,200.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,500.00 | 2,500.00 | 5,500.00 | 5,500.00 | 11,000.00 | 11,000.00 | 5,000.00 | 5,000.00 |
| 0024 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 240 | INLF | 1.50 | 360.00 | 2.00 | 480.00 | 0.91 | 218.40 | 0.70 | 168.00 |
| 0025 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 918 | INLF | 2.00 | 1,836.00 | 2.00 | 1,836.00 | 0.91 | 835.38 | 1.00 | 918.00 |
| 0026 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,568 | INLF | 1.50 | 3,852.00 | 2.00 | 5,136.00 | 1.02 | 2,619.36 | 1.00 | 2,568.00 |
| CONTRACTOR TOTAL | 108,506.10 | 113,192.95 | 118,656.42 | 123,687.60 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Stranco, Inc. |
- 6 - Hhp Construction Group Llc |
- 7 - Byron E. Talbot Contractor, Inc. |
- 8 - Boh Bros. Construction Co., LLC. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 66.7 | SQYD | 10.00 | 667.00 | 8.50 | 566.95 | 12.25 | 817.08 | 15.00 | 1,000.50 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 321 | SQYD | 8.00 | 2,568.00 | 11.50 | 3,691.50 | 17.00 | 5,457.00 | 10.00 | 3,210.00 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 100 | LNFT | 5.00 | 500.00 | 5.00 | 500.00 | 2.00 | 200.00 | 9.00 | 900.00 |
| 0004 | 202-03-38000 | Relocation of Sign (Sta. 26+00) | 1 | EACH | 100.00 | 100.00 | 60.00 | 60.00 | 150.00 | 150.00 | 55.00 | 55.00 |
| 0005 | 202-03-38020 | Relocation of Sign Pole (Sta. 26+00) | 1 | EACH | 100.00 | 100.00 | 60.00 | 60.00 | 55.00 | 55.00 | 55.00 | 55.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | 6,000.00 | 6,000.00 | 6,300.00 | 6,300.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 30 | EACH | 20.00 | 600.00 | 18.00 | 540.00 | 20.00 | 600.00 | 16.50 | 495.00 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 4.00 | 4,000.00 | 2.50 | 2,500.00 | 2.45 | 2,450.00 | 1.75 | 1,750.00 |
| 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 20 | CUYD | 95.00 | 1,900.00 | 110.00 | 2,200.00 | 105.00 | 2,100.00 | 89.00 | 1,780.00 |
| 0010 | 701-06-01040 | Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) | 27 | LNFT | 85.00 | 2,295.00 | 118.00 | 3,186.00 | 75.00 | 2,025.00 | 150.00 | 4,050.00 |
| 0011 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 3,000.00 | 3,000.00 | 2,700.00 | 2,700.00 | 3,200.00 | 3,200.00 | 3,600.00 | 3,600.00 |
| 0012 | 706-01-00300 | Concrete Walk (6" Thick) | 940.6 | SQYD | 60.00 | 56,436.00 | 55.00 | 51,733.00 | 94.75 | 89,121.85 | 70.00 | 65,842.00 |
| 0013 | 706-02-00200 | Concrete Drive (6" Thick) | 31.4 | SQYD | 58.00 | 1,821.20 | 70.00 | 2,198.00 | 88.00 | 2,763.20 | 110.00 | 3,454.00 |
| 0014 | 706-04-00100 | Handicapped Curb Ramps | 9 | EACH | 700.00 | 6,300.00 | 600.00 | 5,400.00 | 600.00 | 5,400.00 | 1,670.00 | 15,030.00 |
| 0015 | 707-01-00200 | Concrete Curb (Barrier) | 122 | LNFT | 23.00 | 2,806.00 | 16.00 | 1,952.00 | 12.00 | 1,464.00 | 30.00 | 3,660.00 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,000.00 | 7,000.00 | 12,500.00 | 12,500.00 | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 8,000.00 | 8,000.00 | 10,000.00 | 10,000.00 | 7,500.00 | 7,500.00 | 11,000.00 | 11,000.00 |
| 0018 | 729-01-00100 | Sign (Type A) | 31.3 | SQFT | 30.00 | 939.00 | 20.00 | 626.00 | 19.60 | 613.48 | 17.50 | 547.75 |
| 0019 | 729-21-00100 | U-Channel Post | 5 | EACH | 95.00 | 475.00 | 150.00 | 750.00 | 150.00 | 750.00 | 134.00 | 670.00 |
| 0020 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 75 | LNFT | 10.00 | 750.00 | 9.00 | 675.00 | 3.00 | 225.00 | 8.25 | 618.75 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 265 | LNFT | 20.00 | 5,300.00 | 18.00 | 4,770.00 | 6.15 | 1,629.75 | 16.50 | 4,372.50 |
| 0022 | 739-01-00100 | Hydro-Seeding Sta. 14+45 to 14+93, 19+69 to 19+99, 25+35 to 25+85, 33+00 to 34+30 | 0.3 | ACRE | 3,500.00 | 1,050.00 | 4,300.00 | 1,290.00 | 4,400.00 | 1,320.00 | 2,860.00 | 858.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 3,500.00 | 3,500.00 | 1,000.00 | 1,000.00 | 8,300.00 | 8,300.00 |
| 0024 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 240 | INLF | 1.00 | 240.00 | 1.10 | 264.00 | 1.25 | 300.00 | 0.75 | 180.00 |
| 0025 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 918 | INLF | 1.00 | 918.00 | 1.30 | 1,193.40 | 1.85 | 1,698.30 | 0.75 | 688.50 |
| 0026 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,568 | INLF | 1.00 | 2,568.00 | 1.20 | 3,081.60 | 1.85 | 4,750.80 | 1.00 | 2,568.00 |
| CONTRACTOR TOTAL | 125,333.20 | 125,937.45 | 146,590.46 | 146,985.00 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - T.N.T. Construction Group LLC |
- 10 - Task Force Llc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-02020 | Removal of Asphalt Pavement | 66.7 | SQYD | 2.00 | 133.40 | 29.43 | 1,962.98 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 321 | SQYD | 5.00 | 1,605.00 | 36.62 | 11,755.02 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 100 | LNFT | 5.00 | 500.00 | 13.08 | 1,308.00 |
| 0004 | 202-03-38000 | Relocation of Sign (Sta. 26+00) | 1 | EACH | 350.00 | 350.00 | 327.00 | 327.00 |
| 0005 | 202-03-38020 | Relocation of Sign Pole (Sta. 26+00) | 1 | EACH | 100.00 | 100.00 | 327.00 | 327.00 |
| 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 24,341.50 | 24,341.50 | 26,160.00 | 26,160.00 |
| 0007 | 204-02-00100 | Temporary Hay or Straw Bales | 30 | EACH | 8.00 | 240.00 | 9.81 | 294.30 |
| 0008 | 204-06-00100 | Temporary Silt Fencing | 1,000 | LNFT | 0.25 | 250.00 | 1.91 | 1,910.00 |
| 0009 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 20 | CUYD | 50.00 | 1,000.00 | 98.11 | 1,962.20 |
| 0010 | 701-06-01040 | Side Drain Pipe Arch (24" Equiv. RCPA/CMPA) | 27 | LNFT | 120.00 | 3,240.00 | 52.32 | 1,412.64 |
| 0011 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 2,000.00 | 2,000.00 | 1,962.00 | 1,962.00 |
| 0012 | 706-01-00300 | Concrete Walk (6" Thick) | 940.6 | SQYD | 60.00 | 56,436.00 | 102.02 | 95,960.01 |
| 0013 | 706-02-00200 | Concrete Drive (6" Thick) | 31.4 | SQYD | 65.00 | 2,041.00 | 102.02 | 3,203.43 |
| 0014 | 706-04-00100 | Handicapped Curb Ramps | 9 | EACH | 3,000.00 | 27,000.00 | 209.28 | 1,883.52 |
| 0015 | 707-01-00200 | Concrete Curb (Barrier) | 122 | LNFT | 20.00 | 2,440.00 | 39.24 | 4,787.28 |
| 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 22,500.00 | 22,500.00 | 7,848.00 | 7,848.00 |
| 0017 | 727-01-00100 | Mobilization | 1 | LUMP | 18,000.00 | 18,000.00 | 20,928.00 | 20,928.00 |
| 0018 | 729-01-00100 | Sign (Type A) | 31.3 | SQFT | 18.40 | 575.92 | 32.70 | 1,023.51 |
| 0019 | 729-21-00100 | U-Channel Post | 5 | EACH | 140.30 | 701.50 | 130.80 | 654.00 |
| 0020 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 75 | LNFT | 8.50 | 637.50 | 9.81 | 735.75 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 265 | LNFT | 16.00 | 4,240.00 | 19.62 | 5,199.30 |
| 0022 | 739-01-00100 | Hydro-Seeding Sta. 14+45 to 14+93, 19+69 to 19+99, 25+35 to 25+85, 33+00 to 34+30 | 0.3 | ACRE | 3,600.00 | 1,080.00 | 6,540.00 | 1,962.00 |
| 0023 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 5,232.00 | 5,232.00 |
| 0024 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 240 | INLF | 0.75 | 180.00 | 8.50 | 2,040.00 |
| 0025 | NS-500-00360 | Saw Cutting Asphaltic Concrete Pavement Over Portland Cement Concrete Composite Pavement | 918 | INLF | 0.85 | 780.30 | 15.70 | 14,412.60 |
| 0026 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,568 | INLF | 0.85 | 2,182.80 | 8.50 | 21,828.00 |
| CONTRACTOR TOTAL | 182,554.92 | 237,078.54 | ||||||