Bid Tabulations
Letting of
06/09/2010
LA DOTD Headquarters
| Lead Project: 853-28-0007 | |
| Parish: Tangipahoa | |
| Routes: LA 1064 | |
| Description: SB RIGHT TURN LANE ON LA 1064 @ U.S. 190 | |
| Type Const: CLEARING & GRUBBING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT WIDENING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $181,015.19 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $135,878.10 |
| 2 | 06276 | Barriere Construction Co., LLC. | $144,291.10 |
| 3 | 05693 | Industrial Enterprises, Inc. | $194,940.43 |
| 4 | 12487 | Diamond B Construction Co., L.L.C. | $428,075.16 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Boh Bros. Construction Co., LLC. |
- 2 - Barriere Construction Co., LLC. |
- 3 - Industrial Enterprises, Inc. |
- 4 - Diamond B Construction Co., L.L.C. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,000.00 | 1,000.00 | 8,000.00 | 8,000.00 | 5,750.00 | 5,750.00 | 38,300.00 | 38,300.00 |
| 0002 | 202-03-38000 | Relocation of Sign stop sign to be relocated as directed by project engineer | 1 | EACH | 100.00 | 100.00 | 120.00 | 120.00 | 115.00 | 115.00 | 3,060.00 | 3,060.00 |
| 0003 | 203-02-00100 | Drainage Excavation | 20 | CUYD | 30.00 | 600.00 | 247.00 | 4,940.00 | 28.75 | 575.00 | 285.00 | 5,700.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 3,000.00 | 3,000.00 | 7,500.00 | 7,500.00 | 24,375.00 | 24,375.00 | 203,100.00 | 203,100.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 250 | CUYD | 30.00 | 7,500.00 | 30.00 | 7,500.00 | 23.00 | 5,750.00 | 43.00 | 10,750.00 |
| 0006 | 204-02-00100 | Temporary Hay or Straw Bales | 6 | EACH | 20.00 | 120.00 | 75.00 | 450.00 | 23.00 | 138.00 | 251.00 | 1,506.00 |
| 0007 | 204-06-00100 | Temporary Silt Fencing | 365 | LNFT | 3.50 | 1,277.50 | 4.00 | 1,460.00 | 4.03 | 1,470.95 | 18.00 | 6,570.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 159.3 | TON | 150.00 | 23,895.00 | 125.00 | 19,912.50 | 190.90 | 30,410.37 | 170.00 | 27,081.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 7 | TON | 200.00 | 1,400.00 | 125.00 | 875.00 | 201.25 | 1,408.75 | 315.00 | 2,205.00 |
| 0010 | 510-02-00100 | Pavement Widening | 526 | SQYD | 80.00 | 42,080.00 | 60.00 | 31,560.00 | 89.70 | 47,182.20 | 55.00 | 28,930.00 |
| 0011 | 701-13-01160 | Corrugated Metal Pipe Arch (Extension) (60" Equiv.) | 10 | LNFT | 400.00 | 4,000.00 | 375.00 | 3,750.00 | 356.51 | 3,565.10 | 775.00 | 7,750.00 |
| 0012 | 701-15-00100 | Concrete Collar | 1 | EACH | 2,000.00 | 2,000.00 | 5,000.00 | 5,000.00 | 2,300.00 | 2,300.00 | 3,400.00 | 3,400.00 |
| 0013 | 710-01-00100 | Flowable Fill | 4.1 | CUYD | 750.00 | 3,075.00 | 200.00 | 820.00 | 345.00 | 1,414.50 | 1,000.00 | 4,100.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 14,000.00 | 14,000.00 | 17,204.00 | 17,204.00 | 9,000.00 | 9,000.00 |
| 0015 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 100 | LNFT | 0.25 | 25.00 | 0.40 | 40.00 | 1.15 | 115.00 | 1.10 | 110.00 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 24 | LNFT | 0.75 | 18.00 | 1.00 | 24.00 | 2.30 | 55.20 | 2.10 | 50.40 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.072 | MILE | 500.00 | 36.00 | 200.00 | 14.40 | 7,590.00 | 546.48 | 1,100.00 | 79.20 |
| 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.072 | MILE | 500.00 | 36.00 | 550.00 | 39.60 | 690.00 | 49.68 | 610.00 | 43.92 |
| 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.152 | MILE | 550.00 | 83.60 | 700.00 | 106.40 | 1,035.00 | 157.32 | 910.00 | 138.32 |
| 0020 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 2 | EACH | 40.00 | 80.00 | 50.00 | 100.00 | 86.25 | 172.50 | 85.00 | 170.00 |
| 0021 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 2,200.00 | 1,320.00 | 2,900.00 | 1,740.00 | 2,530.00 | 1,518.00 | 13,500.00 | 8,100.00 |
| 0022 | 717-01-00100 | Seeding | 9 | LB | 20.00 | 180.00 | 28.00 | 252.00 | 23.00 | 207.00 | 271.00 | 2,439.00 |
| 0023 | 718-01-00100 | Fertilizer | 300 | LB | 1.00 | 300.00 | 2.00 | 600.00 | 1.15 | 345.00 | 13.00 | 3,900.00 |
| 0024 | 726-01-00100 | Bedding Material | 20 | CUYD | 100.00 | 2,000.00 | 52.00 | 1,040.00 | 57.50 | 1,150.00 | 177.00 | 3,540.00 |
| 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 13,500.00 | 13,500.00 | 14,000.00 | 14,000.00 | 24,572.50 | 24,572.50 | 34,300.00 | 34,300.00 |
| 0026 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 100.00 | 200.00 | 110.00 | 220.00 | 115.00 | 230.00 | 850.00 | 1,700.00 |
| 0027 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 100 | LNFT | 1.50 | 150.00 | 2.00 | 200.00 | 2.30 | 230.00 | 2.10 | 210.00 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 24 | LNFT | 5.00 | 120.00 | 6.00 | 144.00 | 5.75 | 138.00 | 5.10 | 122.40 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.072 | MILE | 2,500.00 | 180.00 | 3,000.00 | 216.00 | 3,105.00 | 223.56 | 2,800.00 | 201.60 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.152 | MILE | 1,000.00 | 152.00 | 1,100.00 | 167.20 | 1,035.00 | 157.32 | 910.00 | 138.32 |
| 0031 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 225.00 | 450.00 | 250.00 | 500.00 | 207.00 | 414.00 | 190.00 | 380.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 7,500.00 | 7,500.00 | 5,750.00 | 5,750.00 | 3,000.00 | 3,000.00 |
| 0033 | NS-500-00280 | Surface Preparation | 1 | LUMP | 5,000.00 | 5,000.00 | 11,500.00 | 11,500.00 | 17,250.00 | 17,250.00 | 18,000.00 | 18,000.00 |
| CONTRACTOR TOTAL | 135,878.10 | 144,291.10 | 194,940.43 | 428,075.16 | ||||||||