LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 850-02-0015
Parish: St. Martin
Routes: LA 686
Description: LITTLE PLATTE CANAL AND CREEK BRIDGES
Type Const: GRADING, DRAINAGE STRUCTURES, LIME TREATMENT, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, REINFORCED CONCRETE BOX CULVERTS AND RELATED WORK,
Estimated Construction Cost: $1,541,157.50


RankLicenseBidderConstruction Bid
1 25088 RCS Contractors, Inc. $1,425,627.98
2 39462 Jb James Construction Llc $1,460,499.70
3 09090 Guinn Brothers, LLC. $1,605,677.00
4 51821 Elliott Construction, LLC $1,642,176.53
5 02179 Boh Bros. Construction Co., LLC. $1,668,831.07
6 12198 Byron E. Talbot Contractor, Inc. $1,705,456.58


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
RCS Contractors, Inc.
- 2 -
Jb James Construction Llc
- 3 -
Guinn Brothers, LLC.
- 4 -
Elliott Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 10,000.00 10,000.00 50,000.00 50,000.00 15,000.00 15,000.00 35,000.00 35,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 10,000.00 10,000.00 3,000.00 3,000.00 3,000.00 3,000.00 7,500.00 7,500.00
0003 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 310+06.50, 26' X 20' ) 1      EACH 3,000.00 3,000.00 6,000.00 6,000.00 6,000.00 6,000.00 7,500.00 7,500.00
0004 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 210+20.00, 26' X 40') 1      EACH 5,000.00 5,000.00 8,000.00 8,000.00 8,000.00 8,000.00 7,500.00 7,500.00
0005 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 110+19.10, 26' X 40') 1      EACH 5,000.00 5,000.00 8,000.00 8,000.00 8,000.00 8,000.00 5,000.00 5,000.00
0006 202-02-14500 Removal of Guard Rail 1,310      LNFT 1.00 1,310.00 4.00 5,240.00 2.00 2,620.00 5.25 6,877.50
0007 202-02-38500 Removal of Surfacing and Stablized Base 1,208.5    SQYD 4.00 4,834.00 6.00 7,251.00 4.00 4,834.00 12.00 14,502.00
0008 203-02-00100 Drainage Excavation 1,275      CUYD 5.00 6,375.00 12.00 15,300.00 4.00 5,100.00 15.00 19,125.00
0009 203-05-00100 Excavation and Embankment 1      LUMP 60,000.00 60,000.00 140,000.00 140,000.00 55,000.00 55,000.00 60,000.00 60,000.00
0010 204-05-00100 Temporary Sediment Check Dams (Hay) 12      EACH 121.00 1,452.00 110.00 1,320.00 100.00 1,200.00 121.00 1,452.00
0011 204-06-00100 Temporary Silt Fencing 1,315      LNFT 2.00 2,630.00 2.00 2,630.00 1.50 1,972.50 1.98 2,603.70
0012 302-02-01000 Class II Base Course (4" Thick) STONE OR RECYCLED PCCP 1,451.4    SQYD 25.00 36,285.00 15.00 21,771.00 12.00 17,416.80 28.50 41,364.90
0013 302-02-02000 Class II Base Course (6" Thick) SOIL CEMENT 1,451.4    SQYD 25.00 36,285.00 18.00 26,125.20 18.00 26,125.20 27.25 39,550.65
0014 304-05-00100 Lime Treatment (Type E) 50% OF PROJECT LENGTH 10.3    TON 500.00 5,150.00 500.00 5,150.00 500.00 5,150.00 2,000.00 20,600.00
0015 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 53.45   CUYD 100.00 5,345.00 120.00 6,414.00 100.00 5,345.00 295.00 15,767.75
0016 502-01-00100 Superpave Asphaltic Concrete 257.3    TON 200.00 51,460.00 180.00 46,314.00 200.00 51,460.00 175.00 45,027.50
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 70.3    TON 250.00 17,575.00 220.00 15,466.00 225.00 15,817.50 250.00 17,575.00
0018 701-05-01020 Side Drain Pipe (15" RCP/PP/CMP) 10      LNFT 50.00 500.00 80.00 800.00 100.00 1,000.00 175.00 1,750.00
0019 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 504      LNFT 55.00 27,720.00 58.00 29,232.00 85.00 42,840.00 60.00 30,240.00
0020 701-05-01100 Side Drain Pipe (36" RCP/PP/CMP) 80      LNFT 75.00 6,000.00 90.00 7,200.00 165.00 13,200.00 102.00 8,160.00
0021 701-09-00100 Fabricating Pipe Fittings 15"X24"X24" 1      EACH 950.00 950.00 700.00 700.00 1,650.00 1,650.00 1,125.00 1,125.00
0022 701-15-00100 Concrete Collar 2      EACH 500.00 1,000.00 400.00 800.00 2,000.00 4,000.00 1,275.00 2,550.00
0023 702-08-00100 Side Drain Safety End (Type I) 10      EACH 2,200.00 22,000.00 1,400.00 14,000.00 1,850.00 18,500.00 1,450.00 14,500.00
0024 702-08-00200 Side Drain Safety End (Type 2) 2      EACH 4,350.00 8,700.00 3,200.00 6,400.00 5,000.00 10,000.00 3,600.00 7,200.00
0025 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 137.5    LNFT 66.00 9,075.00 57.00 7,837.50 65.00 8,937.50 104.50 14,368.75
0026 704-03-00100 Blocked Out Guard Rail 31.25   LNFT 27.50 859.38 20.00 625.00 30.00 937.50 27.50 859.38
0027 704-11-00100 Guard Rail End Treatment (Flared) 3      EACH 2,640.00 7,920.00 2,000.00 6,000.00 2,500.00 7,500.00 3,025.00 9,075.00
0028 705-06-00100 Chain Link Fence (4-Foot Height) 50      LNFT 32.00 1,600.00 30.00 1,500.00 20.00 1,000.00 31.90 1,595.00
0029 713-01-00100 Temporary Signs and Barricades 1      LUMP 20,000.00 20,000.00 24,000.00 24,000.00 28,000.00 28,000.00 15,000.00 15,000.00
0030 722-01-00100 Project Site Laboratory 1      EACH 5,000.00 5,000.00 5,000.00 5,000.00 10,000.00 10,000.00 7,500.00 7,500.00
0031 726-01-00100 Bedding Material 378.4    CUYD 100.00 37,840.00 75.00 28,380.00 100.00 37,840.00 158.00 59,787.20
0032 727-01-00100 Mobilization 1      LUMP 55,000.00 55,000.00 140,000.00 140,000.00 125,000.00 125,000.00 100,000.00 100,000.00
0033 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 88.00 352.00 80.00 320.00 100.00 400.00 82.50 330.00
0034 731-02-00100 Reflectorized Raised Pavement Markers 26      EACH 27.50 715.00 25.00 650.00 50.00 1,300.00 5.78 150.28
0035 732-02-01000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) 0.243  MILE 5,500.00 1,336.50 5,000.00 1,215.00 7,000.00 1,701.00 2,750.00 668.25
0036 732-02-02060 Plastic Pavement Striping (Solid Line) (12" Width) (Thermoplastic 90 mil) 0.007  MILE 60,000.00 420.00 75,000.00 525.00 65,000.00 455.00 8,250.00 57.75
0037 732-03-01000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) 0.109  MILE 3,900.00 425.10 4,000.00 436.00 5,000.00 545.00 880.00 95.92
0038 739-01-00100 Hydro-Seeding 0.6    ACRE 3,000.00 1,800.00 2,300.00 1,380.00 6,000.00 3,600.00 2,530.00 1,518.00
0039 740-01-00100 Construction Layout 1      LUMP 10,000.00 10,000.00 30,000.00 30,000.00 10,000.00 10,000.00 10,500.00 10,500.00
0040 805-01-00300 Class A Concrete (Box Culvert Headwalls) 146.56   CUYD 1,400.00 205,184.00 1,000.00 146,560.00 1,250.00 183,200.00 1,250.00 183,200.00
0041 805-12-05040 Reinforced Concrete Box Culverts (10' x 8') 759      LNFT 955.00 724,845.00 820.00 622,380.00 1,100.00 834,900.00 1,050.00 796,950.00
0042 806-01-00100 Deformed Reinforcing Steel 12,815      LB 1.00 12,815.00 1.20 15,378.00 2.00 25,630.00 2.00 25,630.00
0043 NS-700-00240 Special Guard Rail Anchor Section 1      EACH 1,870.00 1,870.00 1,200.00 1,200.00 1,500.00 1,500.00 2,420.00 2,420.00
                         
    CONTRACTOR TOTAL       1,425,627.98   1,460,499.70   1,605,677.00   1,642,176.53



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Boh Bros. Construction Co., LLC.
- 6 -
Byron E. Talbot Contractor, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 35,322.64 35,322.64 25,000.00 25,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 23,548.41 23,548.41 12,000.00 12,000.00
0003 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 310+06.50, 26' X 20' ) 1      EACH 7,064.53 7,064.53 7,500.00 7,500.00
0004 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 210+20.00, 26' X 40') 1      EACH 11,774.21 11,774.21 7,500.00 7,500.00
0005 202-02-04000 Removal of Bridge REMOVE EXISTING TIMBER BRIDGE (STA. 110+19.10, 26' X 40') 1      EACH 11,774.21 11,774.21 7,500.00 7,500.00
0006 202-02-14500 Removal of Guard Rail 1,310      LNFT 1.07 1,401.70 5.00 6,550.00
0007 202-02-38500 Removal of Surfacing and Stablized Base 1,208.5    SQYD 6.82 8,241.97 12.00 14,502.00
0008 203-02-00100 Drainage Excavation 1,275      CUYD 13.21 16,842.75 20.00 25,500.00
0009 203-05-00100 Excavation and Embankment 1      LUMP 115,262.50 115,262.50 56,000.00 56,000.00
0010 204-05-00100 Temporary Sediment Check Dams (Hay) 12      EACH 117.62 1,411.44 140.00 1,680.00
0011 204-06-00100 Temporary Silt Fencing 1,315      LNFT 1.92 2,524.80 3.00 3,945.00
0012 302-02-01000 Class II Base Course (4" Thick) STONE OR RECYCLED PCCP 1,451.4    SQYD 9.95 14,441.43 15.50 22,496.70
0013 302-02-02000 Class II Base Course (6" Thick) SOIL CEMENT 1,451.4    SQYD 24.09 34,964.23 12.50 18,142.50
0014 304-05-00100 Lime Treatment (Type E) 50% OF PROJECT LENGTH 10.3    TON 804.03 8,281.51 650.00 6,695.00
0015 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 53.45   CUYD 142.04 7,592.04 105.00 5,612.25
0016 502-01-00100 Superpave Asphaltic Concrete 257.3    TON 224.23 57,694.38 242.00 62,266.60
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 70.3    TON 224.23 15,763.37 264.00 18,559.20
0018 701-05-01020 Side Drain Pipe (15" RCP/PP/CMP) 10      LNFT 53.46 534.60 50.25 502.50
0019 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 504      LNFT 58.81 29,640.24 57.00 28,728.00
0020 701-05-01100 Side Drain Pipe (36" RCP/PP/CMP) 80      LNFT 80.19 6,415.20 93.50 7,480.00
0021 701-09-00100 Fabricating Pipe Fittings 15"X24"X24" 1      EACH 1,015.79 1,015.79 850.00 850.00
0022 701-15-00100 Concrete Collar 2      EACH 534.63 1,069.26 600.00 1,200.00
0023 702-08-00100 Side Drain Safety End (Type I) 10      EACH 2,352.36 23,523.60 1,600.00 16,000.00
0024 702-08-00200 Side Drain Safety End (Type 2) 2      EACH 4,651.26 9,302.52 4,000.00 8,000.00
0025 704-01-01000 Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) 137.5    LNFT 64.16 8,822.00 70.00 9,625.00
0026 704-03-00100 Blocked Out Guard Rail 31.25   LNFT 26.73 835.31 22.00 687.50
0027 704-11-00100 Guard Rail End Treatment (Flared) 3      EACH 2,566.21 7,698.63 2,200.00 6,600.00
0028 705-06-00100 Chain Link Fence (4-Foot Height) 50      LNFT 31.01 1,550.50 40.00 2,000.00
0029 713-01-00100 Temporary Signs and Barricades 1      LUMP 27,963.75 27,963.75 26,000.00 26,000.00
0030 722-01-00100 Project Site Laboratory 1      EACH 6,922.41 6,922.41 6,500.00 6,500.00
0031 726-01-00100 Bedding Material 378.4    CUYD 89.10 33,715.44 86.65 32,788.36
0032 727-01-00100 Mobilization 1      LUMP 165,000.00 165,000.00 65,000.00 65,000.00
0033 729-16-00300 Object Marker Assembly (Type 3) 4      EACH 85.54 342.16 80.00 320.00
0034 731-02-00100 Reflectorized Raised Pavement Markers 26      EACH 31.54 820.04 6.00 156.00
0035 732-02-01000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) 0.243  MILE 17,642.71 4,287.18 2,750.00 668.25
0036 732-02-02060 Plastic Pavement Striping (Solid Line) (12" Width) (Thermoplastic 90 mil) 0.007  MILE 64,155.32 449.09 8,400.00 58.80
0037 732-03-01000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) 0.109  MILE 12,831.06 1,398.59 880.00 95.92
0038 739-01-00100 Hydro-Seeding 0.6    ACRE 2,459.29 1,475.57 1,450.00 870.00
0039 740-01-00100 Construction Layout 1      LUMP 91,532.33 91,532.33 5,500.00 5,500.00
0040 805-01-00300 Class A Concrete (Box Culvert Headwalls) 146.56   CUYD 1,050.26 153,926.11 1,200.00 175,872.00
0041 805-12-05040 Reinforced Concrete Box Culverts (10' x 8') 759      LNFT 923.45 700,898.55 1,310.00 994,290.00
0042 806-01-00100 Deformed Reinforcing Steel 12,815      LB 1.09 13,968.35 1.00 12,815.00
0043 NS-700-00240 Special Guard Rail Anchor Section 1      EACH 1,817.73 1,817.73 1,400.00 1,400.00
                 
    CONTRACTOR TOTAL       1,668,831.07   1,705,456.58