Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 829-26-0016 | |
| Parish: Lafourche | |
| Routes: LA 3235 | |
| Description: LA 1 - GOLDEN MEADOW | |
| Type Const: GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING,SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK. | |
| Estimated Construction Cost: $3,214,848.14 | |
| Maximum Number of Days Allowed for Construction: 300 | |
| Calculated Daily User Cost: $1,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $3,523,175.40 | 180 | $3,703,175.40 |
| 2 | 06487 | Huey Stockstill, Inc. | $3,643,274.85 | 200 | $3,843,274.85 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Huey Stockstill, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06140 | Removal of Curbs (Concrete) | 523 | LNFT | 5.00 | 2,615.00 | 14.00 | 7,322.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 106 | CUYD | 50.00 | 5,300.00 | 40.00 | 4,240.00 |
| 0003 | 203-08-00100 | Geotextile Fabric | 11 | SQYD | 5.00 | 55.00 | 30.00 | 330.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 23,136.6 | TON | 85.00 | 1,966,611.00 | 86.00 | 1,989,747.60 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 477.2 | TON | 85.00 | 40,562.00 | 280.00 | 133,616.00 |
| 0006 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 2,000 | SQYD | 45.00 | 90,000.00 | 60.00 | 120,000.00 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,000 | SQYD | 90.00 | 90,000.00 | 130.00 | 130,000.00 |
| 0008 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 102,000 | LNFT | 1.10 | 112,200.00 | 1.10 | 112,200.00 |
| 0009 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 41,000 | LNFT | 1.20 | 49,200.00 | 1.50 | 61,500.00 |
| 0010 | 701-12-01020 | Corrugated Metal Pipe (Extension) (15") | 8 | LNFT | 125.00 | 1,000.00 | 300.00 | 2,400.00 |
| 0011 | 701-13-01060 | Corrugated Metal Pipe Arch (Extension) (30" Equiv.) | 8 | LNFT | 150.00 | 1,200.00 | 350.00 | 2,800.00 |
| 0012 | 702-04-00200 | Adjusting Catch Basins | 12 | EACH | 100.00 | 1,200.00 | 3,000.00 | 36,000.00 |
| 0013 | 707-01-00200 | Concrete Curb (Barrier) | 523 | LNFT | 10.00 | 5,230.00 | 23.00 | 12,029.00 |
| 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 300,000.00 | 300,000.00 | 260,000.00 | 260,000.00 |
| 0015 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,113 | LNFT | 0.10 | 111.30 | 0.25 | 278.25 |
| 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 24 | LNFT | 0.10 | 2.40 | 1.00 | 24.00 |
| 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.08 | MILE | 175.00 | 539.00 | 500.00 | 1,540.00 |
| 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 3.5 | MILE | 10.00 | 35.00 | 1,000.00 | 3,500.00 |
| 0019 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 5 | EACH | 10.00 | 50.00 | 50.00 | 250.00 |
| 0020 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 10.00 | 40.00 | 50.00 | 200.00 |
| 0021 | 717-01-00100 | Seeding | 24 | LB | 5.00 | 120.00 | 25.00 | 600.00 |
| 0022 | 718-01-00100 | Fertilizer | 800 | LB | 0.50 | 400.00 | 1.00 | 800.00 |
| 0023 | 726-01-00100 | Bedding Material | 1.6 | CUYD | 200.00 | 320.00 | 250.00 | 400.00 |
| 0024 | 727-01-00100 | Mobilization | 1 | LUMP | 350,000.00 | 350,000.00 | 360,000.00 | 360,000.00 |
| 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,251 | EACH | 5.50 | 6,880.50 | 5.50 | 6,880.50 |
| 0026 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,113 | LNFT | 1.40 | 1,558.20 | 1.50 | 1,669.50 |
| 0027 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 24 | LNFT | 5.00 | 120.00 | 6.00 | 144.00 |
| 0028 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7 | MILE | 2,500.00 | 17,500.00 | 3,500.00 | 24,500.00 |
| 0029 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.16 | MILE | 850.00 | 5,236.00 | 1,000.00 | 6,160.00 |
| 0030 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 5 | EACH | 215.00 | 1,075.00 | 250.00 | 1,250.00 |
| 0031 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 225.00 | 900.00 | 250.00 | 1,000.00 |
| 0032 | 735-01-00100 | Mailboxes | 18 | EACH | 1.00 | 18.00 | 7.00 | 126.00 |
| 0033 | 735-02-00100 | Mailbox Supports (Single) | 12 | EACH | 100.00 | 1,200.00 | 200.00 | 2,400.00 |
| 0034 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 200.00 | 400.00 | 420.00 | 840.00 |
| 0035 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 |
| 0036 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 102,000 | LNFT | 1.00 | 102,000.00 | 1.10 | 112,200.00 |
| 0037 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 41,000 | LNFT | 1.00 | 41,000.00 | 1.20 | 49,200.00 |
| 0038 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 143,000 | LNFT | 2.00 | 286,000.00 | 1.00 | 143,000.00 |
| 0039 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 43,200 | INLF | 0.01 | 432.00 | 0.10 | 4,320.00 |
| 0040 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 24,600 | INLF | 0.50 | 12,300.00 | 1.00 | 24,600.00 |
| 0041 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 6.51 | MILE | 1,500.00 | 9,765.00 | 800.00 | 5,208.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 3,523,175.40 | 3,643,274.85 | ||||||
| NUMBER OF DAYS BID AT $1000 PER DAY. | 180,000.00 | 200,000.00 | ||||||
| TOTAL BID | 3,703,175.40 | 3,843,274.85 | ||||||