Bid Tabulations
Letting of
02/23/2011
LA DOTD Headquarters
| Lead Project: 827-22-0008 | |
| Parish: Jefferson Davis | |
| Routes: LA 395 | |
| Description: US 90 - LA 102 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $2,488,620.74 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 00183 | R. E. Heidt Construction Co., Inc. | $2,153,579.46 |
| 2 | 34356 | Prairie Contractors Inc. | $2,220,910.58 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $2,443,388.73 |
| 4 | 14096 | Bessette Development Corp. | $2,533,332.10 |
| 5 | 33663 | Glenn Lege Construction Inc | $2,708,734.30 |
| 6 | 12312 | Gilchrist Construction Co. LLC | $2,773,552.80 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - R. E. Heidt Construction Co., Inc. |
- 2 - Prairie Contractors Inc. |
- 3 - Diamond B Construction Co., L.L.C. |
- 4 - Bessette Development Corp. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 14 | SQYD | 10.00 | 140.00 | 5.10 | 71.40 | 11.00 | 154.00 | 10.00 | 140.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 626 | LNFT | 4.04 | 2,529.04 | 6.00 | 3,756.00 | 6.10 | 3,818.60 | 4.00 | 2,504.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) S. D. (Sta. 25+21) | 35 | LNFT | 20.20 | 707.00 | 7.40 | 259.00 | 22.00 | 770.00 | 20.00 | 700.00 |
| 0004 | 202-02-32120 | Removal of Pipe (Side Drain) (Sta 30+35 Lt of Centerline) | 6 | LNFT | 10.10 | 60.60 | 7.40 | 44.40 | 11.00 | 66.00 | 10.00 | 60.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 67.3 | SQYD | 5.05 | 339.87 | 4.60 | 309.58 | 5.50 | 370.15 | 5.00 | 336.50 |
| 0006 | 203-02-00100 | Drainage Excavation | 90 | CUYD | 20.20 | 1,818.00 | 15.00 | 1,350.00 | 41.00 | 3,690.00 | 8.00 | 720.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 46,500.00 | 46,500.00 | 2,000.00 | 2,000.00 | 4,000.00 | 4,000.00 | 66,600.00 | 66,600.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,118 | CUYD | 54.00 | 168,372.00 | 29.50 | 91,981.00 | 1.00 | 3,118.00 | 69.25 | 215,921.50 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 21,619.6 | TON | 72.00 | 1,556,611.20 | 77.12 | 1,667,303.55 | 80.50 | 1,740,377.80 | 77.45 | 1,674,438.02 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,333.9 | TON | 67.00 | 89,371.30 | 30.00 | 40,017.00 | 137.00 | 182,744.30 | 90.00 | 120,051.00 |
| 0011 | 509-01-00100 | Cold Planing Asphaltic Pavement | 131,245 | SQYD | 0.46 | 60,372.70 | 0.99 | 129,932.55 | 1.00 | 131,245.00 | 1.43 | 187,680.35 |
| 0012 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,738 | CUYD | 2.50 | -6,845.00 | 40.00 | -109,520.00 | 0.10 | -273.80 | 0.50 | -1,369.00 |
| 0013 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 742 | SQYD | 30.00 | 22,260.00 | 247.00 | 183,274.00 | 98.00 | 72,716.00 | 67.75 | 50,270.50 |
| 0014 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 42 | LNFT | 111.10 | 4,666.20 | 80.00 | 3,360.00 | 115.00 | 4,830.00 | 110.00 | 4,620.00 |
| 0015 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 8 | LNFT | 60.60 | 484.80 | 56.10 | 448.80 | 65.00 | 520.00 | 60.00 | 480.00 |
| 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 1,868.50 | 1,868.50 | 2,860.00 | 2,860.00 | 1,900.00 | 1,900.00 | 1,850.00 | 1,850.00 |
| 0017 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 25 | LNFT | 55.55 | 1,388.75 | 40.00 | 1,000.00 | 40.00 | 1,000.00 | 39.00 | 975.00 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 310.5 | LNFT | 19.19 | 5,958.50 | 18.00 | 5,589.00 | 18.00 | 5,589.00 | 17.50 | 5,433.75 |
| 0019 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 65.65 | 6,565.00 | 54.00 | 5,400.00 | 55.00 | 5,500.00 | 53.00 | 5,300.00 |
| 0020 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,222.00 | 8,888.00 | 2,100.00 | 8,400.00 | 2,100.00 | 8,400.00 | 2,050.00 | 8,200.00 |
| 0021 | 706-01-00100 | Concrete Walk (4" Thick) | 28.3 | SQYD | 38.38 | 1,086.15 | 41.00 | 1,160.30 | 39.00 | 1,103.70 | 38.00 | 1,075.40 |
| 0022 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 235.3 | SQYD | 35.35 | 8,317.86 | 40.00 | 9,412.00 | 36.00 | 8,470.80 | 35.00 | 8,235.50 |
| 0023 | 706-04-00100 | Handicapped Curb Ramps | 4 | EACH | 464.60 | 1,858.40 | 640.00 | 2,560.00 | 500.00 | 2,000.00 | 460.00 | 1,840.00 |
| 0024 | 707-03-00100 | Combination Concrete Curb and Gutter | 301.4 | LNFT | 32.32 | 9,741.25 | 17.24 | 5,196.14 | 33.00 | 9,946.20 | 32.00 | 9,644.80 |
| 0025 | 710-01-00100 | Flowable Fill | 62 | CUYD | 85.85 | 5,322.70 | 112.30 | 6,962.60 | 90.00 | 5,580.00 | 85.00 | 5,270.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,868.00 | 6,868.00 | 12,800.00 | 12,800.00 | 15,000.00 | 15,000.00 | 7,925.00 | 7,925.00 |
| 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,676 | LNFT | 0.30 | 502.80 | 0.01 | 16.76 | 0.60 | 1,005.60 | 0.30 | 502.80 |
| 0028 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,006 | LNFT | 0.90 | 1,805.40 | 0.01 | 20.06 | 1.10 | 2,206.60 | 0.90 | 1,805.40 |
| 0029 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.876 | MILE | 338.00 | 6,042.09 | 400.00 | 7,150.40 | 160.00 | 2,860.16 | 227.75 | 4,071.26 |
| 0030 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.564 | MILE | 303.00 | 4,109.89 | 0.01 | 0.14 | 210.00 | 2,848.44 | 300.00 | 4,069.20 |
| 0031 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 39.766 | MILE | 505.00 | 20,081.83 | 0.01 | 0.40 | 410.00 | 16,304.06 | 500.25 | 19,892.94 |
| 0032 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 8 | EACH | 50.50 | 404.00 | 0.01 | 0.08 | 41.00 | 328.00 | 50.00 | 400.00 |
| 0033 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 202.00 | 808.00 | 0.01 | 0.04 | 71.00 | 284.00 | 200.00 | 800.00 |
| 0034 | 717-01-00100 | Seeding | 11 | LB | 37.00 | 407.00 | 20.00 | 220.00 | 31.00 | 341.00 | 23.65 | 260.15 |
| 0035 | 718-01-00100 | Fertilizer | 180 | LB | 4.50 | 810.00 | 3.00 | 540.00 | 3.60 | 648.00 | 2.15 | 387.00 |
| 0036 | 726-01-00100 | Bedding Material | 7.1 | CUYD | 70.70 | 501.97 | 91.00 | 646.10 | 71.00 | 504.10 | 70.00 | 497.00 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 27,000.00 | 27,000.00 | 55,300.00 | 55,300.00 | 116,700.00 | 116,700.00 | 43,441.93 | 43,441.93 |
| 0038 | 729-16-00200 | Object Marker Assembly (Type 2) | 7 | EACH | 101.00 | 707.00 | 66.50 | 465.50 | 66.00 | 462.00 | 65.00 | 455.00 |
| 0039 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 101.00 | 404.00 | 76.50 | 306.00 | 76.00 | 304.00 | 75.00 | 300.00 |
| 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,053 | EACH | 4.55 | 9,341.15 | 5.10 | 10,470.30 | 5.10 | 10,470.30 | 4.50 | 9,238.50 |
| 0041 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 838 | LNFT | 1.01 | 846.38 | 1.55 | 1,298.90 | 1.60 | 1,340.80 | 1.00 | 838.00 |
| 0042 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,003 | LNFT | 4.04 | 4,052.12 | 3.60 | 3,610.80 | 3.60 | 3,610.80 | 4.00 | 4,012.00 |
| 0043 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 19.883 | MILE | 2,323.00 | 46,188.21 | 2,450.00 | 48,713.35 | 2,500.00 | 49,707.50 | 2,300.00 | 45,730.90 |
| 0044 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.782 | MILE | 808.00 | 5,479.86 | 615.00 | 4,170.93 | 610.00 | 4,137.02 | 800.00 | 5,425.60 |
| 0045 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 252.50 | 1,010.00 | 310.00 | 1,240.00 | 310.00 | 1,240.00 | 250.00 | 1,000.00 |
| 0046 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 404.00 | 808.00 | 410.00 | 820.00 | 410.00 | 820.00 | 400.00 | 800.00 |
| 0047 | 735-01-00100 | Mailboxes | 30 | EACH | 1.01 | 30.30 | 1.05 | 31.50 | 1.10 | 33.00 | 1.00 | 30.00 |
| 0048 | 735-02-00100 | Mailbox Supports (Single) | 23 | EACH | 118.17 | 2,717.91 | 120.00 | 2,760.00 | 120.00 | 2,760.00 | 117.00 | 2,691.00 |
| 0049 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 176.75 | 176.75 | 180.00 | 180.00 | 180.00 | 180.00 | 175.00 | 175.00 |
| 0050 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 322.19 | 644.38 | 325.00 | 650.00 | 320.00 | 640.00 | 319.00 | 638.00 |
| 0051 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 100.00 | 100.00 | 6,000.00 | 6,000.00 | 3,518.50 | 3,518.50 |
| 0052 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 6,272 | INLF | 0.55 | 3,449.60 | 1.00 | 6,272.00 | 0.80 | 5,017.60 | 0.55 | 3,449.60 |
| CONTRACTOR TOTAL | 2,153,579.46 | 2,220,910.58 | 2,443,388.73 | 2,533,332.10 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Glenn Lege Construction Inc |
- 6 - Gilchrist Construction Co. LLC |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 14 | SQYD | 35.00 | 490.00 | 20.00 | 280.00 |
| 0002 | 202-02-14500 | Removal of Guard Rail | 626 | LNFT | 6.00 | 3,756.00 | 7.00 | 4,382.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) S. D. (Sta. 25+21) | 35 | LNFT | 10.00 | 350.00 | 25.00 | 875.00 |
| 0004 | 202-02-32120 | Removal of Pipe (Side Drain) (Sta 30+35 Lt of Centerline) | 6 | LNFT | 10.00 | 60.00 | 15.00 | 90.00 |
| 0005 | 202-02-38500 | Removal of Surfacing and Stablized Base | 67.3 | SQYD | 10.00 | 673.00 | 10.00 | 673.00 |
| 0006 | 203-02-00100 | Drainage Excavation | 90 | CUYD | 18.00 | 1,620.00 | 25.00 | 2,250.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 1,650.00 | 1,650.00 | 2,500.00 | 2,500.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,118 | CUYD | 75.00 | 233,850.00 | 75.00 | 233,850.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 21,619.6 | TON | 82.00 | 1,772,807.20 | 85.00 | 1,837,666.00 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 1,333.9 | TON | 107.50 | 143,394.25 | 145.00 | 193,415.50 |
| 0011 | 509-01-00100 | Cold Planing Asphaltic Pavement | 131,245 | SQYD | 1.50 | 196,867.50 | 0.80 | 104,996.00 |
| 0012 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -2,738 | CUYD | 0.50 | -1,369.00 | 1.00 | -2,738.00 |
| 0013 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 742 | SQYD | 80.00 | 59,360.00 | 115.00 | 85,330.00 |
| 0014 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 42 | LNFT | 170.00 | 7,140.00 | 125.00 | 5,250.00 |
| 0015 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 8 | LNFT | 75.00 | 600.00 | 75.00 | 600.00 |
| 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 3,000.00 | 3,000.00 | 3,500.00 | 3,500.00 |
| 0017 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 25 | LNFT | 42.58 | 1,064.50 | 45.00 | 1,125.00 |
| 0018 | 704-03-00100 | Blocked Out Guard Rail | 310.5 | LNFT | 19.11 | 5,933.66 | 20.00 | 6,210.00 |
| 0019 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 57.87 | 5,787.00 | 60.00 | 6,000.00 |
| 0020 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,240.00 | 8,960.00 | 2,300.00 | 9,200.00 |
| 0021 | 706-01-00100 | Concrete Walk (4" Thick) | 28.3 | SQYD | 55.00 | 1,556.50 | 50.00 | 1,415.00 |
| 0022 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 235.3 | SQYD | 42.00 | 9,882.60 | 45.00 | 10,588.50 |
| 0023 | 706-04-00100 | Handicapped Curb Ramps | 4 | EACH | 600.00 | 2,400.00 | 600.00 | 2,400.00 |
| 0024 | 707-03-00100 | Combination Concrete Curb and Gutter | 301.4 | LNFT | 30.00 | 9,042.00 | 35.00 | 10,549.00 |
| 0025 | 710-01-00100 | Flowable Fill | 62 | CUYD | 120.00 | 7,440.00 | 92.00 | 5,704.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 60,150.00 | 60,150.00 | 35,000.00 | 35,000.00 |
| 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,676 | LNFT | 0.22 | 368.72 | 0.25 | 419.00 |
| 0028 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,006 | LNFT | 0.98 | 1,965.88 | 1.00 | 2,006.00 |
| 0029 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.876 | MILE | 650.00 | 11,619.40 | 400.00 | 7,150.40 |
| 0030 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.564 | MILE | 436.75 | 5,924.08 | 110.00 | 1,492.04 |
| 0031 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 39.766 | MILE | 584.16 | 23,229.71 | 110.00 | 4,374.26 |
| 0032 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 8 | EACH | 71.00 | 568.00 | 75.00 | 600.00 |
| 0033 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 71.00 | 284.00 | 75.00 | 300.00 |
| 0034 | 717-01-00100 | Seeding | 11 | LB | 20.00 | 220.00 | 120.00 | 1,320.00 |
| 0035 | 718-01-00100 | Fertilizer | 180 | LB | 2.50 | 450.00 | 4.25 | 765.00 |
| 0036 | 726-01-00100 | Bedding Material | 7.1 | CUYD | 85.00 | 603.50 | 75.00 | 532.50 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 31,530.00 | 31,530.00 | 100,000.00 | 100,000.00 |
| 0038 | 729-16-00200 | Object Marker Assembly (Type 2) | 7 | EACH | 71.00 | 497.00 | 75.00 | 525.00 |
| 0039 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 82.00 | 328.00 | 85.00 | 340.00 |
| 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,053 | EACH | 5.30 | 10,880.90 | 5.25 | 10,778.25 |
| 0041 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 838 | LNFT | 1.10 | 921.80 | 1.10 | 921.80 |
| 0042 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,003 | LNFT | 4.40 | 4,413.20 | 4.35 | 4,363.05 |
| 0043 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 19.883 | MILE | 2,512.00 | 49,946.10 | 2,500.00 | 49,707.50 |
| 0044 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.782 | MILE | 900.00 | 6,103.80 | 900.00 | 6,103.80 |
| 0045 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 195.00 | 780.00 | 195.00 | 780.00 |
| 0046 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 440.00 | 880.00 | 435.00 | 870.00 |
| 0047 | 735-01-00100 | Mailboxes | 30 | EACH | 1.00 | 30.00 | 10.00 | 300.00 |
| 0048 | 735-02-00100 | Mailbox Supports (Single) | 23 | EACH | 130.00 | 2,990.00 | 165.00 | 3,795.00 |
| 0049 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 195.00 | 195.00 | 245.00 | 245.00 |
| 0050 | 735-04-00100 | Mailbox Supports (Multiple) | 2 | EACH | 350.00 | 700.00 | 495.00 | 990.00 |
| 0051 | 740-01-00100 | Construction Layout | 1 | LUMP | 9,000.00 | 9,000.00 | 10,000.00 | 10,000.00 |
| 0052 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 6,272 | INLF | 1.25 | 7,840.00 | 0.60 | 3,763.20 |
| CONTRACTOR TOTAL | 2,708,734.30 | 2,773,552.80 | ||||||