Bid Tabulations
Letting of
04/27/2011
LA DOTD Headquarters
| Lead Project: 809-07-0011 | |
| Parish: Desoto, Caddo | |
| Routes: LA 789 | |
| Description: Keatchie to Preston Road | |
| Type Const: Grading, Cold Planing Asphaltic Concrete, Pavement Patching, Superpave Asphaltic Concrete Pavement Overlay and Related Work | |
| Estimated Construction Cost: $1,589,515.71 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $1,766,269.37 |
| 2 | 17464 | Benton & Brown, LLC. | $1,883,477.32 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Benton & Brown, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,800 | CUYD | 14.00 | 81,200.00 | 15.00 | 87,000.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 180 | CUYD | 55.00 | 9,900.00 | 100.00 | 18,000.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 15,329.5 | TON | 87.50 | 1,341,331.25 | 91.00 | 1,394,984.50 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 435 | TON | 65.00 | 28,275.00 | 111.00 | 48,285.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,467 | SQYD | 4.30 | 6,308.10 | 8.00 | 11,736.00 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | 47 | CUYD | 1.00 | 47.00 | 0.01 | 0.47 |
| 0008 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 1,000 | SQYD | 55.00 | 55,000.00 | 50.00 | 50,000.00 |
| 0009 | 701-08-00100 | Relaying Pipe | 30 | LNFT | 160.00 | 4,800.00 | 100.00 | 3,000.00 |
| 0010 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 16 | LNFT | 260.00 | 4,160.00 | 230.00 | 3,680.00 |
| 0011 | 701-15-00100 | Concrete Collar | 4 | EACH | 1,000.00 | 4,000.00 | 800.00 | 3,200.00 |
| 0012 | 712-04-00100 | Flexible Revetment | 106 | SQYD | 80.00 | 8,480.00 | 90.00 | 9,540.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 57,100.00 | 57,100.00 | 65,000.00 | 65,000.00 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 66 | LNFT | 0.10 | 6.60 | 1.00 | 66.00 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.292 | MILE | 325.00 | 2,694.90 | 350.00 | 2,902.20 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.452 | MILE | 1.00 | 1.45 | 1.00 | 1.45 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 30.948 | MILE | 1.00 | 30.95 | 1.00 | 30.95 |
| 0018 | 716-01-00100 | Mulch (Vegetative) | 21.5 | TON | 600.00 | 12,900.00 | 1,100.00 | 23,650.00 |
| 0019 | 717-01-00100 | Seeding | 369 | LB | 10.00 | 3,690.00 | 8.00 | 2,952.00 |
| 0020 | 718-01-00100 | Fertilizer | 12,240 | LB | 0.50 | 6,120.00 | 0.50 | 6,120.00 |
| 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 57,100.00 | 57,100.00 | 65,000.00 | 65,000.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 552 | EACH | 4.50 | 2,484.00 | 5.00 | 2,760.00 |
| 0023 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 33 | LNFT | 5.00 | 165.00 | 5.50 | 181.50 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 15.474 | MILE | 2,600.00 | 40,232.40 | 2,700.00 | 41,779.80 |
| 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.726 | MILE | 800.00 | 580.80 | 825.00 | 598.95 |
| 0026 | 735-01-00100 | Mailboxes | 35 | EACH | 1.00 | 35.00 | 1.10 | 38.50 |
| 0027 | 735-02-00100 | Mailbox Supports (Single) | 30 | EACH | 125.00 | 3,750.00 | 135.00 | 4,050.00 |
| 0028 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 175.00 | 875.00 | 200.00 | 1,000.00 |
| 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 16,000.00 | 16,000.00 |
| 0030 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 192 | INLF | 0.01 | 1.92 | 10.00 | 1,920.00 |
| CONTRACTOR TOTAL | 1,766,269.37 | 1,883,477.32 | ||||||