Bid Tabulations
Letting of
03/30/2011
LA DOTD Headquarters
| Lead Project: 808-06-0018 | |
| Parish: Bossier | |
| Routes: LA 782-2 | |
| Description: LA 782-2 (INDUSTRIAL DR) IMPROVEMENTS (PHASE I) | |
| Type Const: Base Course P.C.C. Pavement, Incidental Pavement, Pavement Markings and Related Work | |
| Estimated Construction Cost: $419,580.72 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 28218 | F. J. Burnell, Inc. | $465,361.61 |
| 2 | 12135 | Blount Bros. Construction, Inc. | $525,290.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - F. J. Burnell, Inc. |
- 2 - Blount Bros. Construction, Inc. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 |
| 0002 | 202-02-06060 | Removal of Concrete Catch Basin | 3 | EACH | 700.00 | 2,100.00 | 1,500.00 | 4,500.00 |
| 0003 | 202-02-06140 | Removal of Curbs (Concrete) | 1,360.1 | LNFT | 13.00 | 17,681.30 | 10.00 | 13,601.00 |
| 0004 | 202-02-26300 | Removal of Median / Island | 58.5 | SQYD | 15.00 | 877.50 | 12.00 | 702.00 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 625 | LNFT | 2.00 | 1,250.00 | 3.00 | 1,875.00 |
| 0007 | 302-02-05120 | Class II Base Course (10" Thick) (Stone or Recycled Portland Cement Concrete) | 471.9 | SQYD | 27.75 | 13,095.23 | 30.00 | 14,157.00 |
| 0008 | 601-01-00500 | Portland Cement Concrete Pavement (10" Thick) | 380.9 | SQYD | 90.00 | 34,281.00 | 90.00 | 34,281.00 |
| 0009 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 380.9 | SQYD | 150.00 | 57,135.00 | 200.00 | 76,180.00 |
| 0010 | 701-03-01040 | Storm Drain Pipe (24" RCP/PP) | 3 | LNFT | 1,000.00 | 3,000.00 | 100.00 | 300.00 |
| 0011 | 702-03-00500 | Catch Basins (CB-06) | 1 | EACH | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 |
| 0012 | 702-03-00800 | Catch Basins (CB-09) | 3 | EACH | 5,000.00 | 15,000.00 | 4,500.00 | 13,500.00 |
| 0013 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 |
| 0014 | 704-03-00100 | Blocked Out Guard Rail | 518.75 | LNFT | 21.00 | 10,893.75 | 30.00 | 15,562.50 |
| 0015 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 63.00 | 6,300.00 | 70.00 | 7,000.00 |
| 0016 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 3 | EACH | 2,800.00 | 8,400.00 | 2,500.00 | 7,500.00 |
| 0017 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 8.3 | SQYD | 100.00 | 830.00 | 40.00 | 332.00 |
| 0018 | 707-01-00200 | Concrete Curb (Barrier) | 764.2 | LNFT | 8.00 | 6,113.60 | 10.00 | 7,642.00 |
| 0019 | 707-01-00300 | Concrete Curb (Mountable) | 14 | LNFT | 8.00 | 112.00 | 20.00 | 280.00 |
| 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 11,000.00 | 11,000.00 | 15,000.00 | 15,000.00 |
| 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 103 | LNFT | 2.25 | 231.75 | 2.00 | 206.00 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.19 | MILE | 1,200.00 | 228.00 | 2,000.00 | 380.00 |
| 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.146 | MILE | 1,200.00 | 1,375.20 | 800.00 | 916.80 |
| 0024 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 3,000.00 | 600.00 | 7,000.00 | 1,400.00 |
| 0025 | 717-01-00100 | Seeding | 3 | LB | 60.00 | 180.00 | 20.00 | 60.00 |
| 0026 | 718-01-00100 | Fertilizer | 100 | LB | 1.00 | 100.00 | 7.00 | 700.00 |
| 0027 | 727-01-00100 | Mobilization | 1 | LUMP | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 |
| 0028 | 730-15-01000 | Relocate Light Poles Relocate light pole | 2 | EACH | 2,000.00 | 4,000.00 | 5,000.00 | 10,000.00 |
| 0029 | 731-02-00100 | Reflectorized Raised Pavement Markers | 31 | EACH | 17.00 | 527.00 | 15.00 | 465.00 |
| 0030 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 152.9 | LNFT | 5.75 | 879.18 | 7.00 | 1,070.30 |
| 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.142 | MILE | 3,400.00 | 482.80 | 4,000.00 | 568.00 |
| 0032 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.125 | MILE | 6,000.00 | 750.00 | 6,000.00 | 750.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.401 | MILE | 2,300.00 | 922.30 | 2,000.00 | 802.00 |
| 0034 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 230.00 | 690.00 | 200.00 | 600.00 |
| 0035 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 230.00 | 230.00 | 200.00 | 200.00 |
| 0036 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 230.00 | 920.00 | 220.00 | 880.00 |
| 0037 | 732-05-00100 | Removal of Existing Markings | 0.72 | MILE | 5,800.00 | 4,176.00 | 4,000.00 | 2,880.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 12,000.00 | 12,000.00 |
| 0039 | NS-713-00001 | Dynamic Message Sign Unit | 1 | EACH | 2,000.00 | 2,000.00 | 8,000.00 | 8,000.00 |
| 0040 | NS-800-00120 | Pier Protection System (Vehicle) | 4 | EACH | 52,000.00 | 208,000.00 | 55,000.00 | 220,000.00 |
| CONTRACTOR TOTAL | 465,361.61 | 525,290.60 | ||||||