Bid Tabulations
Letting of
07/21/2010
LA DOTD Headquarters
| Lead Project: 742-55-0113 | |
| Parish: Terrebonne | |
| Routes: | |
| Description: TERREBONNE PARISH CONCRETE SECTION REPAIRS, PHASE II | |
| Type Const: PAVEMENT PATCHING AND RELATED WORK | |
| Estimated Construction Cost: $2,725,724.20 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 10830 | G & W Construction Co., Inc. | $2,849,027.10 |
| 2 | 21982 | Forby Contracting, Inc. | $2,970,722.45 |
| 3 | 48896 | Command Construction Industries LLC | $3,347,777.77 |
| 4 | 24901 | Hard Rock Construction Co. | $3,547,609.15 |
| 5 | 34263 | La Contracting Enterprises Llc | $3,705,281.80 |
| 6 | 49954 | Plus Concrete Inc. | $3,795,335.90 |
| 7 | 02179 | Boh Bros. Construction Co., LLC. | $4,009,427.00 |
| 8 | 12198 | Byron E. Talbot Contractor, Inc. | $5,032,578.36 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - G & W Construction Co., Inc. |
- 2 - Forby Contracting, Inc. |
- 3 - Command Construction Industries LLC |
- 4 - Hard Rock Construction Co. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 602-05-01120 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) | 50.2 | SQYD | 95.00 | 4,769.00 | 135.00 | 6,777.00 | 200.00 | 10,040.00 | 127.00 | 6,375.40 |
| 0002 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 2,264 | SQYD | 95.00 | 215,080.00 | 115.00 | 260,360.00 | 125.00 | 283,000.00 | 127.00 | 287,528.00 |
| 0003 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 10,884.3 | SQYD | 95.00 | 1,034,008.50 | 95.00 | 1,034,008.50 | 112.00 | 1,219,041.60 | 127.00 | 1,382,306.10 |
| 0004 | 707-01-00300 | Concrete Curb (Mountable) | 5,680 | LNFT | 10.00 | 56,800.00 | 10.75 | 61,060.00 | 10.00 | 56,800.00 | 8.00 | 45,440.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 125,000.00 | 125,000.00 | 25,000.00 | 25,000.00 | 500.00 | 500.00 | 25,000.00 | 25,000.00 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 88,000.00 | 88,000.00 | 75,000.00 | 75,000.00 | 302,085.47 | 302,085.47 | 87,000.00 | 87,000.00 |
| 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 164 | EACH | 7.50 | 1,230.00 | 5.00 | 820.00 | 6.00 | 984.00 | 5.25 | 861.00 |
| 0008 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 60 | LNFT | 7.00 | 420.00 | 4.00 | 240.00 | 6.00 | 360.00 | 4.50 | 270.00 |
| 0009 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.228 | MILE | 3,300.00 | 752.40 | 4,100.00 | 934.80 | 2,600.00 | 592.80 | 2,500.00 | 570.00 |
| 0010 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.134 | MILE | 1,200.00 | 1,360.80 | 1,150.00 | 1,304.10 | 900.00 | 1,020.60 | 850.00 | 963.90 |
| 0011 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 | 500.00 | 500.00 | 5,000.00 | 5,000.00 |
| SUBTOTAL GENERAL | 1,552,421 | 1,475,504 | 1,874,924 | 1,841,314 | ||||||||
| Alternate DA1 | ||||||||||||
| 0012 | 602-05-01120 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) | 42.6 | SQYD | 95.00 | 4,047.00 | 142.50 | 6,070.50 | 200.00 | 8,520.00 | 127.00 | 5,410.20 |
| 0013 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 623.7 | SQYD | 95.00 | 59,251.50 | 122.50 | 76,403.25 | 125.00 | 77,962.50 | 127.00 | 79,209.90 |
| 0014 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 1,449.3 | SQYD | 95.00 | 137,683.50 | 102.50 | 148,553.25 | 112.00 | 162,321.60 | 127.00 | 184,061.10 |
| 0015 | 707-01-00300 | Concrete Curb (Mountable) | 775 | LNFT | 10.00 | 7,750.00 | 10.75 | 8,331.25 | 10.00 | 7,750.00 | 8.00 | 6,200.00 |
| 0016 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 64 | LNFT | 7.00 | 448.00 | 2.00 | 128.00 | 2.00 | 128.00 | 1.50 | 96.00 |
| 0017 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 30 | LNFT | 8.00 | 240.00 | 4.00 | 120.00 | 6.00 | 180.00 | 4.50 | 135.00 |
| SUBTOTAL ALT DA1 | 209,420 | 239,606 | 256,862 | 275,112 | ||||||||
| Alternate EA1 | ||||||||||||
| 0018 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 858.4 | SQYD | 95.00 | 81,548.00 | 135.00 | 115,884.00 | 125.00 | 107,300.00 | 127.00 | 109,016.80 |
| 0019 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 3,553.7 | SQYD | 95.00 | 337,601.50 | 125.00 | 444,212.50 | 112.00 | 398,014.40 | 127.00 | 451,319.90 |
| 0020 | 707-01-00300 | Concrete Curb (Mountable) | 202 | LNFT | 10.00 | 2,020.00 | 10.75 | 2,171.50 | 10.00 | 2,020.00 | 8.00 | 1,616.00 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 15 | LNFT | 8.00 | 120.00 | 4.00 | 60.00 | 6.00 | 90.00 | 4.50 | 67.50 |
| SUBTOTAL ALT EA1 | 421,290 | 562,328 | 507,424 | 562,020 | ||||||||
| Alternate FA1 | ||||||||||||
| 0022 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 454.1 | SQYD | 95.00 | 43,139.50 | 117.50 | 53,356.75 | 125.00 | 56,762.50 | 127.00 | 57,670.70 |
| 0023 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 6,169.5 | SQYD | 95.00 | 586,102.50 | 97.50 | 601,526.25 | 100.00 | 616,950.00 | 127.00 | 783,526.50 |
| 0024 | 707-01-00200 | Concrete Curb (Barrier) | 240 | LNFT | 10.00 | 2,400.00 | 15.00 | 3,600.00 | 10.00 | 2,400.00 | 8.00 | 1,920.00 |
| 0025 | 707-01-00300 | Concrete Curb (Mountable) | 3,061 | LNFT | 10.00 | 30,610.00 | 10.75 | 32,905.75 | 10.00 | 30,610.00 | 8.00 | 24,488.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 74 | EACH | 7.50 | 555.00 | 5.00 | 370.00 | 6.00 | 444.00 | 5.25 | 388.50 |
| 0027 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 284 | LNFT | 7.00 | 1,988.00 | 2.00 | 568.00 | 2.00 | 568.00 | 1.50 | 426.00 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 39 | LNFT | 8.00 | 312.00 | 4.00 | 156.00 | 6.00 | 234.00 | 4.50 | 175.50 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.047 | MILE | 3,300.00 | 155.10 | 4,100.00 | 192.70 | 2,600.00 | 122.20 | 2,500.00 | 117.50 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.529 | MILE | 1,200.00 | 634.80 | 1,150.00 | 608.35 | 900.00 | 476.10 | 850.00 | 449.65 |
| SUBTOTAL ALT FA1 | 665,896.90 | 693,283.80 | 708,566.80 | 869,162.35 | ||||||||
| CONTRACTOR TOTAL | 2,849,027.10 | 2,970,722.45 | 3,347,777.77 | 3,547,609.15 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - La Contracting Enterprises Llc |
- 6 - Plus Concrete Inc. |
- 7 - Boh Bros. Construction Co., LLC. |
- 8 - Byron E. Talbot Contractor, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 602-05-01120 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) | 50.2 | SQYD | 150.00 | 7,530.00 | 140.00 | 7,028.00 | 330.00 | 16,566.00 | 250.00 | 12,550.00 |
| 0002 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 2,264 | SQYD | 136.00 | 307,904.00 | 122.00 | 276,208.00 | 140.00 | 316,960.00 | 175.00 | 396,200.00 |
| 0003 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 10,884.3 | SQYD | 128.00 | 1,393,190.40 | 110.00 | 1,197,273.00 | 120.00 | 1,306,116.00 | 175.00 | 1,904,752.50 |
| 0004 | 707-01-00300 | Concrete Curb (Mountable) | 5,680 | LNFT | 15.00 | 85,200.00 | 24.00 | 136,320.00 | 26.00 | 147,680.00 | 15.00 | 85,200.00 |
| 0005 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 | 10,000.00 | 10,000.00 | 60,000.00 | 60,000.00 | 55,000.00 | 55,000.00 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 490,000.00 | 490,000.00 | 337,000.00 | 337,000.00 | 170,000.00 | 170,000.00 |
| 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 164 | EACH | 6.50 | 1,066.00 | 6.00 | 984.00 | 9.00 | 1,476.00 | 6.00 | 984.00 |
| 0008 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 60 | LNFT | 5.00 | 300.00 | 5.00 | 300.00 | 7.00 | 420.00 | 5.00 | 300.00 |
| 0009 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.228 | MILE | 5,000.00 | 1,140.00 | 4,500.00 | 1,026.00 | 6,200.00 | 1,413.60 | 2,750.00 | 627.00 |
| 0010 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.134 | MILE | 1,400.00 | 1,587.60 | 2,000.00 | 2,268.00 | 1,500.00 | 1,701.00 | 935.00 | 1,060.29 |
| 0011 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 80,000.00 | 80,000.00 | 35,000.00 | 35,000.00 |
| SUBTOTAL GENERAL | 1,937,918 | 2,129,407 | 2,269,333 | 2,661,674 | ||||||||
| Alternate DA1 | ||||||||||||
| 0012 | 602-05-01120 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (8" Thick) | 42.6 | SQYD | 150.00 | 6,390.00 | 200.00 | 8,520.00 | 330.00 | 14,058.00 | 250.00 | 10,650.00 |
| 0013 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 623.7 | SQYD | 136.00 | 84,823.20 | 150.00 | 93,555.00 | 140.00 | 87,318.00 | 175.00 | 109,147.50 |
| 0014 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 1,449.3 | SQYD | 128.00 | 185,510.40 | 125.00 | 181,162.50 | 120.00 | 173,916.00 | 175.00 | 253,627.50 |
| 0015 | 707-01-00300 | Concrete Curb (Mountable) | 775 | LNFT | 15.00 | 11,625.00 | 30.00 | 23,250.00 | 26.00 | 20,150.00 | 15.00 | 11,625.00 |
| 0016 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 64 | LNFT | 3.00 | 192.00 | 10.00 | 640.00 | 2.00 | 128.00 | 1.65 | 105.60 |
| 0017 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 30 | LNFT | 5.00 | 150.00 | 10.00 | 300.00 | 7.00 | 210.00 | 5.00 | 150.00 |
| SUBTOTAL ALT DA1 | 288,691 | 307,428 | 295,780 | 385,306 | ||||||||
| Alternate EA1 | ||||||||||||
| 0018 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 858.4 | SQYD | 136.00 | 116,742.40 | 122.00 | 104,724.80 | 140.00 | 120,176.00 | 175.00 | 150,220.00 |
| 0019 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 3,553.7 | SQYD | 128.00 | 454,873.60 | 112.00 | 398,014.40 | 120.00 | 426,444.00 | 175.00 | 621,897.50 |
| 0020 | 707-01-00300 | Concrete Curb (Mountable) | 202 | LNFT | 15.00 | 3,030.00 | 30.00 | 6,060.00 | 26.00 | 5,252.00 | 15.00 | 3,030.00 |
| 0021 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 15 | LNFT | 5.00 | 75.00 | 10.00 | 150.00 | 7.00 | 105.00 | 5.00 | 75.00 |
| SUBTOTAL ALT EA1 | 574,721 | 508,949 | 551,977 | 775,223 | ||||||||
| Alternate FA1 | ||||||||||||
| 0022 | 602-05-02120 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (8" Thick) | 454.1 | SQYD | 136.00 | 61,757.60 | 122.00 | 55,400.20 | 140.00 | 63,574.00 | 175.00 | 79,467.50 |
| 0023 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 6,169.5 | SQYD | 128.00 | 789,696.00 | 112.00 | 690,984.00 | 120.00 | 740,340.00 | 175.00 | 1,079,662.50 |
| 0024 | 707-01-00200 | Concrete Curb (Barrier) | 240 | LNFT | 17.00 | 4,080.00 | 30.00 | 7,200.00 | 26.00 | 6,240.00 | 15.00 | 3,600.00 |
| 0025 | 707-01-00300 | Concrete Curb (Mountable) | 3,061 | LNFT | 15.00 | 45,915.00 | 30.00 | 91,830.00 | 26.00 | 79,586.00 | 15.00 | 45,915.00 |
| 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 74 | EACH | 6.50 | 481.00 | 10.00 | 740.00 | 8.00 | 592.00 | 6.00 | 444.00 |
| 0027 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 284 | LNFT | 3.00 | 852.00 | 3.00 | 852.00 | 3.00 | 852.00 | 1.65 | 468.60 |
| 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 39 | LNFT | 5.00 | 195.00 | 5.00 | 195.00 | 7.00 | 273.00 | 5.00 | 195.00 |
| 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.047 | MILE | 5,000.00 | 235.00 | 5,000.00 | 235.00 | 4,100.00 | 192.70 | 2,750.00 | 129.25 |
| 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.529 | MILE | 1,400.00 | 740.60 | 4,000.00 | 2,116.00 | 1,300.00 | 687.70 | 935.00 | 494.62 |
| SUBTOTAL ALT FA1 | 903,952.20 | 849,552.20 | 892,337.40 | 1,210,376.47 | ||||||||
| CONTRACTOR TOTAL | 3,705,281.80 | 3,795,335.90 | 4,009,427.00 | 5,032,578.36 | ||||||||